Pre Qual Case Study Flashcards

1
Q

What is shell & core

A

Concrete shell
Metal frame
Weather proofed
Communal areas (usually completed)
Without services
With cores built (stairs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is CAT A fit out

A

Fully functional but empty space
Raised access floors
Suspended ceilings
AC
Lights
Basic fire detection & protection in place
Basic installations M&E in place
No fixtures or fittings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is CAT B

A

Fully fitted out
Partitioning installed
Joinery
Door & floor finishes
Meeting rooms
IT/ AV fitted out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What contract is used

A

JCT standard building contract 2016 with amendments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How was the contract procured

A

2 stage tender process, traditional procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why use a 2 stage tender process

A

Involve contractors early - Contractor design portion included - helps with build ability
More collaboration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens in first stage of 2 stage tender

A

Competitive tender of package
Tender interviews
Review of programme
Overheads, profit & prelims
Ends with appointment of preferred contractor under PCSA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Second stage tender of 2 stage

A

Pre construction service agreement
Negotiation between client and contractor on price
Firm up programme
Agree contract requirements
Ends with agreement of lump sum contract sum
Novation of consultants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why traditional

A

Blp wanted to maintain control of design
Cost certainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is novation?

A

Legal term- replacement of party X in an agreement with a new party, with consent of all parties.
Eg on Bloomberg- Novation of SAS (ceilings) to ISG

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the RIBA stages

A

Stage 0: Strategic Definition.
Stage 1: Preparation and Briefing.
Stage 2: Concept Design.
Stage 3: Spatial Coordination.
Stage 4: Technical Design.
Stage 5: Manufacturing and Construction.
Stage 6: Handover.
Stage 7: Use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Key activities in riba stage 0

A

Stage 0 is about the discussions you need to have and the calculations you need to make before you are ready to commit to a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Key activities in riba stage 1

A

Preparation & briefing
Architect is onboarded

Project Outcomes
Sustainability Outcomes
Quality Aspirations
Spatial Requirements
Undertake feasibility studies & agree overall budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Key activities Tina stage 2

A

Concept design
Design & build contracts when the contractor would be onboarded / start tender process
Consultants are onboarded

design reviews happen – you and the design team work together, exploring ideas and analysing options, to get to a concept that fulfils both your wants and needs. It starts with rough ideas and evolves towards a workable design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Key activities RIBA stage 3

A

Spatial coordination
Structural engineer onboarded
Building regulations checklist
Design shouldn’t change much between stage 3-4

sustainability strategy, and all consultant recommendations should be incorporated into the design

Normally prepare planning documents for submitting planning applications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Key activities RIBA stage 4

A

Technical design
Usually when contractor is onboarded in traditional (no CDP)
Building regulations checklist
Design finalised ready for construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Key activities RIBA stage 5

A

Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Key activities in stage 6

A

Handover
O&Ms handed over

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What amendments are in your contract

A

Rectification period is 12 months
IDF room sectional completion is 6 weeks prior to PC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Did you select the contract?

A

No I personally didn’t, this was preselected prior to arcadis involvement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Do you think this contract form was suitable

A

Yes as design control remained with the client, early build ability input from the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How would design risk vary depending in different forms of contract

A

D&B design risk would sit with the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Could you use other forms of contract?

A

Yes- we could have used JCT D&B or NEC

24
Q

Why didn’t you use NEC

A

NEC is typically used for public sector but could have been adapted for use on this project.
The client was more familiar with JCT contracts and therefore that’s why JCT was used

25
Q

What were the contract Amendments

A

Rectification period is 12months instead of 6.
Sectional completion of IDF rooms, 6 weeks prior to handover

26
Q

Why did you go to tender in stage 2 for traditional project

A

Wanted early build ability from contractor
Staircase CDP

27
Q

Why 2 stage?

A

Early contractor involvement
Increased collaboration with consultants
Build ability to help reduce design risk

28
Q

What is CDP

A

Contractor design portion
Agreement for contractor design specific parts of work
Staircase for Bloomberg

29
Q

Why use traditional if you want CDP?

A

Client wanted to maintain control on the design but wanted the build ability input from the contractor to gain expertise
Risk was around the structural impact of the stair and client wanted this risk to be passed onto contractor

30
Q

Stair issues

A

Understanding necessity to back prop to L2
Where to cut the slab
How to reinforce the structural load
Need for hoarding and how it would impact the critical path when completing floors

31
Q

Did you use PCSA

A

Yes

32
Q

What does PCSA stand for

A

Pre construction service agreement

33
Q

Typical activities under PCSA

A

Overheads and profit agreed
Programme agreed
Build ability input
Agree on nominated subcontractors
Agree any novation

34
Q

Did you issue an early orders under PCSA

A

Yes, early orders for M&E - EPIC valves, more sustainable raised access flooring

35
Q

Sustainable construction in the project

A

Raised access flooring is recycled
EPIC valves within fan coil units- give better control of temperature

36
Q

With the late addition of the stair did you have to change any contracts

A

Yes- I advised the client that the scope of the consultants needed to be enhanced for the stair.

37
Q

Did you draft change in contracts ?

A

No I advised the client and their legal team drafted change in contract for the client to issue

38
Q

Why did you undertake an options appraisal

A

To further detail each option, highlight the cost impact and the programme impact

39
Q

How did you review programme impact of the stair

A

Looked at benchmarked dates for similar projects
Reviewed the impact on the critical path
- fire hoarding
- impact on the live floors
- OOH work

40
Q

How were the external walls built

A

Stone facade
Bronze
Curtain walling

41
Q

What surveys did you undertake

A

Instructed asbestos survey despite the base build being complete in 2017, there may be an asbestos risk
Condition survey

42
Q

What is an F10

A

Notification of a construction project sent to health & safety executive

43
Q

Does every project need an f10?

A

No, only needs one if longer than 30 days and less than 20workers
Or
Exceeds 500 person days

Construction regulations 2015

44
Q

what is status A

A

approved with no comments

45
Q

what is status B

A

approved with comments

46
Q

what is status C

A

rejected & to be revised with the comments issued by design approver

47
Q

CDP design approval

A

schedule 1 design submission procedure

48
Q

how is the slab cut

A

track saw cuts through the concrete
oxyacertaline cuts through the steel ( a really hot blow torch)
weight is held from the top and lifted out through sections using an A frame
around the edge is broken back to 1m to expose the rebar
additional rebar is added around the edge to strength the slab and then refilled to 1m for hole

49
Q

what is the bloomberg fire strategy

A

Phased evacuation- once smoke is found that floor and two floors above evacuate and then 2 floors down from L8 at a time.

50
Q

whats passive fire protection

A

contain fire within a space- use of intumescent paint (once chipped is redundant) or fire rated plaster board (pink)

51
Q

intumescent paint

A

it expands when hot

52
Q

whats active fire protection

A

detecting & stopping- sprinklers

53
Q

why have a gas suppresion system?

A

when you cant use water sprinklers eg comms room

54
Q

which building regulations document deal with fire

A

approved document B

55
Q

what order do you cut the slab

A

top down. crash matts on floor below

56
Q

how much is the ergonom advance payment bond

A

30%, £1.8m

57
Q

what does privacy of contract mean?

A

a common law principle which provides that a contract cannot confer rights or impose obligations upon anyone who is not a party to that contract.