Pre Qual Case Study Flashcards
What is shell & core
Concrete shell
Metal frame
Weather proofed
Communal areas (usually completed)
Without services
With cores built (stairs)
What is CAT A fit out
Fully functional but empty space
Raised access floors
Suspended ceilings
AC
Lights
Basic fire detection & protection in place
Basic installations M&E in place
No fixtures or fittings
What is CAT B
Fully fitted out
Partitioning installed
Joinery
Door & floor finishes
Meeting rooms
IT/ AV fitted out
What contract is used
JCT standard building contract 2016 with amendments
How was the contract procured
2 stage tender process, traditional procurement
Why use a 2 stage tender process
Involve contractors early - Contractor design portion included - helps with build ability
More collaboration
What happens in first stage of 2 stage tender
Competitive tender of package
Tender interviews
Review of programme
Overheads, profit & prelims
Ends with appointment of preferred contractor under PCSA
Second stage tender of 2 stage
Pre construction service agreement
Negotiation between client and contractor on price
Firm up programme
Agree contract requirements
Ends with agreement of lump sum contract sum
Novation of consultants
Why traditional
Blp wanted to maintain control of design
Cost certainty
What is novation?
Legal term- replacement of party X in an agreement with a new party, with consent of all parties.
Eg on Bloomberg- Novation of SAS (ceilings) to ISG
What are the RIBA stages
Stage 0: Strategic Definition.
Stage 1: Preparation and Briefing.
Stage 2: Concept Design.
Stage 3: Spatial Coordination.
Stage 4: Technical Design.
Stage 5: Manufacturing and Construction.
Stage 6: Handover.
Stage 7: Use.
Key activities in riba stage 0
Stage 0 is about the discussions you need to have and the calculations you need to make before you are ready to commit to a project.
Key activities in riba stage 1
Preparation & briefing
Architect is onboarded
Project Outcomes
Sustainability Outcomes
Quality Aspirations
Spatial Requirements
Undertake feasibility studies & agree overall budget
Key activities Tina stage 2
Concept design
Design & build contracts when the contractor would be onboarded / start tender process
Consultants are onboarded
design reviews happen – you and the design team work together, exploring ideas and analysing options, to get to a concept that fulfils both your wants and needs. It starts with rough ideas and evolves towards a workable design
Key activities RIBA stage 3
Spatial coordination
Structural engineer onboarded
Building regulations checklist
Design shouldn’t change much between stage 3-4
sustainability strategy, and all consultant recommendations should be incorporated into the design
Normally prepare planning documents for submitting planning applications
Key activities RIBA stage 4
Technical design
Usually when contractor is onboarded in traditional (no CDP)
Building regulations checklist
Design finalised ready for construction
Key activities RIBA stage 5
Construction
Key activities in stage 6
Handover
O&Ms handed over
What amendments are in your contract
Rectification period is 12 months
IDF room sectional completion is 6 weeks prior to PC
Did you select the contract?
No I personally didn’t, this was preselected prior to arcadis involvement
Do you think this contract form was suitable
Yes as design control remained with the client, early build ability input from the contractor
How would design risk vary depending in different forms of contract
D&B design risk would sit with the contractor
Could you use other forms of contract?
Yes- we could have used JCT D&B or NEC
Why didn’t you use NEC
NEC is typically used for public sector but could have been adapted for use on this project.
The client was more familiar with JCT contracts and therefore that’s why JCT was used
What were the contract Amendments
Rectification period is 12months instead of 6.
Sectional completion of IDF rooms, 6 weeks prior to handover
Why did you go to tender in stage 2 for traditional project
Wanted early build ability from contractor
Staircase CDP
Why 2 stage?
Early contractor involvement
Increased collaboration with consultants
Build ability to help reduce design risk
What is CDP
Contractor design portion
Agreement for contractor design specific parts of work
Staircase for Bloomberg
Why use traditional if you want CDP?
Client wanted to maintain control on the design but wanted the build ability input from the contractor to gain expertise
Risk was around the structural impact of the stair and client wanted this risk to be passed onto contractor