Pre Qual Case Study Flashcards

1
Q

What is shell & core

A

Concrete shell
Metal frame
Weather proofed
Communal areas (usually completed)
Without services
With cores built (stairs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is CAT A fit out

A

Fully functional but empty space
Raised access floors
Suspended ceilings
AC
Lights
Basic fire detection & protection in place
Basic installations M&E in place
No fixtures or fittings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is CAT B

A

Fully fitted out
Partitioning installed
Joinery
Door & floor finishes
Meeting rooms
IT/ AV fitted out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What contract is used

A

JCT standard building contract 2016 with amendments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How was the contract procured

A

2 stage tender process, traditional procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why use a 2 stage tender process

A

Involve contractors early - Contractor design portion included - helps with build ability
More collaboration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens in first stage of 2 stage tender

A

Competitive tender of package
Tender interviews
Review of programme
Overheads, profit & prelims
Ends with appointment of preferred contractor under PCSA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Second stage tender of 2 stage

A

Pre construction service agreement
Negotiation between client and contractor on price
Firm up programme
Agree contract requirements
Ends with agreement of lump sum contract sum
Novation of consultants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why traditional

A

Blp wanted to maintain control of design
Cost certainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is novation?

A

Legal term- replacement of party X in an agreement with a new party, with consent of all parties.
Eg on Bloomberg- Novation of SAS (ceilings) to ISG

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the RIBA stages

A

Stage 0: Strategic Definition.
Stage 1: Preparation and Briefing.
Stage 2: Concept Design.
Stage 3: Spatial Coordination.
Stage 4: Technical Design.
Stage 5: Manufacturing and Construction.
Stage 6: Handover.
Stage 7: Use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Key activities in riba stage 0

A

Stage 0 is about the discussions you need to have and the calculations you need to make before you are ready to commit to a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Key activities in riba stage 1

A

Preparation & briefing
Architect is onboarded

Project Outcomes
Sustainability Outcomes
Quality Aspirations
Spatial Requirements
Undertake feasibility studies & agree overall budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Key activities Tina stage 2

A

Concept design
Design & build contracts when the contractor would be onboarded / start tender process
Consultants are onboarded

design reviews happen – you and the design team work together, exploring ideas and analysing options, to get to a concept that fulfils both your wants and needs. It starts with rough ideas and evolves towards a workable design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Key activities RIBA stage 3

A

Spatial coordination
Structural engineer onboarded
Building regulations checklist
Design shouldn’t change much between stage 3-4

sustainability strategy, and all consultant recommendations should be incorporated into the design

Normally prepare planning documents for submitting planning applications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Key activities RIBA stage 4

A

Technical design
Usually when contractor is onboarded in traditional (no CDP)
Building regulations checklist
Design finalised ready for construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Key activities RIBA stage 5

A

Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Key activities in stage 6

A

Handover
O&Ms handed over

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What amendments are in your contract

A

Rectification period is 12 months
IDF room sectional completion is 6 weeks prior to PC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Did you select the contract?

A

No I personally didn’t, this was preselected prior to arcadis involvement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Do you think this contract form was suitable

A

Yes as design control remained with the client, early build ability input from the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How would design risk vary depending in different forms of contract

A

D&B design risk would sit with the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Could you use other forms of contract?

A

Yes- we could have used JCT D&B or NEC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Why didn’t you use NEC

A

NEC is typically used for public sector but could have been adapted for use on this project.
The client was more familiar with JCT contracts and therefore that’s why JCT was used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What were the contract Amendments
Rectification period is 12months instead of 6. Sectional completion of IDF rooms, 6 weeks prior to handover
26
Why did you go to tender in stage 2 for traditional project
Wanted early build ability from contractor Staircase CDP
27
Why 2 stage?
Early contractor involvement Increased collaboration with consultants Build ability to help reduce design risk
28
What is CDP
Contractor design portion Agreement for contractor design specific parts of work Staircase for Bloomberg
29
Why use traditional if you want CDP?
Client wanted to maintain control on the design but wanted the build ability input from the contractor to gain expertise Risk was around the structural impact of the stair and client wanted this risk to be passed onto contractor
30
Stair issues
Understanding necessity to back prop to L2 Where to cut the slab How to reinforce the structural load Need for hoarding and how it would impact the critical path when completing floors
31
Did you use PCSA
Yes
32
What does PCSA stand for
Pre construction service agreement
33
Typical activities under PCSA
Overheads and profit agreed Programme agreed Build ability input Agree on nominated subcontractors Agree any novation
34
Did you issue an early orders under PCSA
Yes, early orders for M&E - EPIC valves, more sustainable raised access flooring
35
Sustainable construction in the project
Raised access flooring is recycled EPIC valves within fan coil units- give better control of temperature
36
With the late addition of the stair did you have to change any contracts
Yes- I advised the client that the scope of the consultants needed to be enhanced for the stair.
37
Did you draft change in contracts ?
No I advised the client and their legal team drafted change in contract for the client to issue
38
Why did you undertake an options appraisal
To further detail each option, highlight the cost impact and the programme impact
39
How did you review programme impact of the stair
Looked at benchmarked dates for similar projects Reviewed the impact on the critical path - fire hoarding - impact on the live floors - OOH work
40
How were the external walls built
Stone facade Bronze Curtain walling
41
What surveys did you undertake
Instructed asbestos survey despite the base build being complete in 2017, there may be an asbestos risk Condition survey
42
What is an F10
Notification of a construction project sent to health & safety executive
43
Does every project need an f10?
No, only needs one if longer than 30 days and less than 20workers Or Exceeds 500 person days Construction regulations 2015
44
what is status A
approved with no comments
45
what is status B
approved with comments
46
what is status C
rejected & to be revised with the comments issued by design approver
47
CDP design approval
schedule 1 design submission procedure
48
how is the slab cut
track saw cuts through the concrete oxyacertaline cuts through the steel ( a really hot blow torch) weight is held from the top and lifted out through sections using an A frame around the edge is broken back to 1m to expose the rebar additional rebar is added around the edge to strength the slab and then refilled to 1m for hole
49
what is the bloomberg fire strategy
Phased evacuation- once smoke is found that floor and two floors above evacuate and then 2 floors down from L8 at a time.
50
whats passive fire protection
contain fire within a space- use of intumescent paint (once chipped is redundant) or fire rated plaster board (pink)
51
intumescent paint
it expands when hot
52
whats active fire protection
detecting & stopping- sprinklers
53
why have a gas suppresion system?
when you cant use water sprinklers eg comms room
54
which building regulations document deal with fire
approved document B
55
what order do you cut the slab
top down. crash matts on floor below
56
how much is the ergonom advance payment bond
30%, £1.8m
57
what does privacy of contract mean?
a common law principle which provides that a contract cannot confer rights or impose obligations upon anyone who is not a party to that contract.
58
what is the arcadis team structure
senior director Senior PM me- assistant PM
59
what were your typical responsibilities
ran the day to day PMing of the overall works alongside the senior PM, once the contract was signed undertook the contract adminisatrors role with sign off from the director
60
why take on a project at shell and core instead of cat A
- full ownership of design, can be completely tailored to my clients desires. - less likely to have issues with the M&E eg on BDO there are issues with the riser routes
61
why undertake 2 stage
- market preference currently - CDP- needed early contractor input - PCSA to get contractor on board to help with wider buildability
62
what were the funding gateways
at the end of each design stage if there was a design change that costed over $200,000 dollars it had to go through procurement committee for sign off- had CFO team on this board
63
do you think the staircase was a good idea?
yes- from a design perspective it enhanced opulence of the south building - something that is important to the client however, there was an opportunity cost of the staircase that the money could have been used on other initiatives within the building
64
how was the stair constructed
construction of the stair hasnt started yet but, it will be done out of hours to reduce disruption to the staff in the building
65
risks with out of hours working
risk of fatigue from H&S perspective and also from quality perspective. also more expensive to have OOH works
66
what is the fire strategy
once smoke is detected, the floor and the floor above and below are evacuated, then two floors at a time from the top of the building
67
what are the extract systems
there are smoke extracts on both sides of the cores, this takes the smoke out through the risers and out through the roof
68
other options for fire strategy?
fire curtains around the staircase, these did not align with the design intent
69
how did you ensure the hoarding around the stair was fire rated
60min fire rating. slab to slab hoarding
70
is the smoke extract system/hoarding passive or active fire protection
passive
71
what is active fire protection
detects extinguish or aid evacuation
72
examples of passive
intumbescent paint plasterboard
73
why was a mock up needed for the staircase
review the complexity of the design. bronze fixing/ sheets puckering of leather on balustrade
74
how could you value engineer the mock up
could use computer modeling factory visit benchmarking it was CDP so is the contractors risk use other materials/ off cuts