Con Tech Flashcards

1
Q

Name a sustainable method on your project

A

The use of EPIV valves for the fan Coil units, more energy efficient by avoiding over pumping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Types of external wall

A

Stone facade
Curtain walling
Brick slips
Brick work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

how is the stair constructed

A

the slab is cut top down- crash matts on floor below.
reviewed with structural engineer to seeif back propping was necessary
then the stair is constructed bottom up
hoarding is put up around where the slab cut is - 60min fire rated due to smoke extract on plant roof not being cut until L8 works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

using recycled steel beam on L6 cut out

A
  • Careful/ controlled demolition of slab above beams, to retain shear studs and avoid damaging the beam flanges
  • Beams temporarily supported to allow for unbolting, current contractor proposals would be to hang from level 08 beams, or MEWPs would be considered at level 06 to move beams into new position.
  • Larger area of slab would be broken out to allow for metal deck to be place and new concrete slab to be poured – this would allow for the composite action be achieved between the beam and concrete, which is critical to control deflection over a long span.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

recycled beam on L6 benefits

A
  • Significant carbon saving, as no need to re-produce sections (particularly fabricated sections, which are more carbon intensive), and reduction in materials delivered to site.
  • Offers benefits to the buildability, as bringing new long-span steel elements to site will be challenging – the original beams were craned in, which is no longer feasible in the current building. New elements would need to be cut into sections small enough to fit into the goods lift, and reformed with splice connections along the length of the beam.
  • Although increasing the scope of slab demolition, this could offer a significant saving overall in terms of cost, programme and carbon.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

recycled beam on L6 negatives

A
  • The beams will be cut shorter than the current span, as the connections will need to be removed. This creates complexity in the new connections to be formed once the beams are in their new position.
  • Beams could be damaged during demolition.
  • The original beams were pre-cambered, which won’t be possible in the proposed condition with beam re-use – may be subject to higher deflections, which needs to be factored into the design.
  • The tonnage of these beams is significant, which will prove challenging when trying to remove and reinstall in a new location.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

how do you test concrete

A

cube test, take samples at 7/14 & 21 days then its crushed, to see how it crushes shows the strength

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

BREEAM Levels

A

outstanding 85% +
excellent 70-85%
very good 55-70%
good 45-55%
pass 30-45%
unclassified below 30%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

BREEAM assessment categories

A

management
water
energy
transport
health & wellbeing
resources
resilience
land use & ecology
pollution
materials
waste
innovation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

BREEAM Standards

A

new construction
refurbishments & fit out
in use
in community

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

building safety act

A

post grenfell tragedy
dame judith hackitts report- building a safe future
new duty holders
principal designer
high risk buildings- 2+ residential units, 7+ storeys or 18m or taller

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

types of concrete

A

pre cast
in situ

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what are the riba stages

A

0- strategic defintion
1- preparation and briefing
2- concept design
3- spatial coordination
4- technical design
5- construction
6- handover
7- in use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

when doing your master programme how did you know how long to have for you design stages

A
  • validated length with similar projects
  • spoke with design team
  • spoke with client
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

steel frame v concrete frame

A

steel:
off site manufacturing
works for constrained sites
reuse

long lead times
expensive during covid- inflated prices

concrete:
shorter lead times
less expensive

design might prefer a certain type

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

difference between Shell & Core, CAT A & CAT B

A

shell & core- weather tight

CAT A- some services are in- major M&E/ first fixes, cant move into it,

CAT B- ready to be moved in, minor client adjustments to be made- FF&E

17
Q

CAT A risks

A

BDO- taking at CAT A, main risks is around the services, not having a dedicated riser or extract by the kitchen, not much room for plant on the roof - dictates what can be done with the space