Project Finance Flashcards
What are the typical cost manager responsibilities on a construction project?
- Manage risk allowance expenditure
- Initiate action to avoid overspend
- Prepare pricing documents for tendering
- Evaluate and analyze tender bids
- Prepare interim valuations
- Value variations and compensation events
- Assess the contractor’s financial claims
- Negotiate and agree final accounts
- Issue financial reports or statements
- Provide initial cost advice on capital investment costs
- Produce cost estimates and cost plans
- Provide advice on whole life costs
- Produce cost reports, estimates and forecasts
- Prepare and maintain cash flow forecasts
If you are producing cost estimates and cost plans, which measurements rules represent industry best practice?
New Rules of Measurement (NRM)
Can you name the 3 documents in the NRM suite?
- NRM1 - Order of cost estimating and cost planning for capital building works
- NRM2 - Detailed measurement for building works
- NRM3 - Order of cost estimating and cost planning for building maintenance works
Can you provide a brief overview of each of the NRM documents?
NRM1 - Provides guidance on quantification of building works for the purpose of preparing cost estimates and cost plans. It is the “cornerstone” of good cost management of construction projects, enabling more effective and accurate cost advice to be given to clients and other project team members, as well as facilitating better cost control.
NRM2 - Is written mainly for the preparation of BOQs and quantified schedules of works, although the rules will be invaluable for designing and developing standard or bespoke schedules of rates.
NRM3 - Gives guidance on the quantification and description of maintenance works for the purpose of preparing initial order of cost estimates. The rules also aid in the procurement and cost control of maintenance works.
What is the structure of the NRM 1?
Part 1: General Introduction
Part 2: Measurement rules for order of cost estimate
Part 3: Measurement rules for cost planning
Part 4: Tabulated rules of measurement for elemental cost planning
- Appendices
What is the structure of the NRM 2?
Part 1: General introduction
Part 2: Rules for detailed measurement of building works
Part 3: Tabulated rules of measurement for building works
- Appendices
What is the structure of the NRM 3?
Part 1: General introduction
Part 2: New rules of measurement for building maintenance works
Part 3: Measurement rules for order of cost estimating (renewal and maintain)
Part 4: Measurement rules for cost planning and renewal (R) and maintain (M) works
Part 5: Calculation of annualized costs for renewal (R) and maintain (M) works
Part 6: Tabulated rules of measurement for elemental cost planning
- Appendices
Why is it important to measure the works according to industry standards and best practice?
- To provide consistency and greater accuracy of pricing
- To ensure that all parties price on the same basis and therefore reduce the risk of dispute
Is it mandatory for chartered surveyors to follow the procedures set out in the NRM?
Following NRM is not a mandatory requirement. However, when an allegation of professional negligence is made against a surveyor, the court is likely to take account of the contents of any relevant guidance notes published by the RICS in deciding whether the surveyor had acted with reasonable competence
How is risk dealt with under NRM?
NRM recommends that risk allowances are not a standard percentage, but a properly considered assessment of risk, considering completeness of the design and other uncertainties such as the extent of the site investigation undertaken
Can you tell me the 4 risk categories identified in NRM?
- Employer Change Risk
- Employer Other Risk
- Design Development Risk
- Construction Risk
How does NRM define the “cost limit” of the project?
Cost limit (or authorized budget or approved estimate) - means the maximum expenditure that the employer is prepared to make in relation to the completed building
Can you explain what the “base cost estimate” should include?
Base cost estimate - means an evolving estimate of known factors without any allowance for risk and uncertainty, or element of inflation. The base cost estimate is the sum of the works cost estimate, the project/design team fees estimate and the other development/project costs estimate
What are the GRIP stages of work?
- Output definition
- Project feasibility
- Option Selection
- Single Option Selection
- Detailed Design
- Construction, Test, Commission
- Scheme Handback
- Project Closeout
What is a Cost Plan?
- The cost plan is typically prepared by the cost consultant and provides an estimate of what the actual project cost is likely to be
- The cost plan identifies the client’s agreed cost limit and how the money is allocated to the different parts fo the project
Other than predicting the final project cost, what other benefits does the cost plan provide to the project and the project team?
- Designers are aware of the cost implications of their proposals which enables them to arrive at practical and balanced designs
- Provides information upon which the employer can make informed commercial decisions
What sources of cost information and data are available when preparing a new cost estimate or cost plan?
- Information produced by the BCIS (Building Cost Information Service), data is available on a wide range of building types
- Published pricing books such as SPON’s and BCIS (the information may need adjusting for inflation)
- Pricing documents and other information from previous projects
- Cost analysis and cost models produced in-house
- Speaking directly to contractors, subcontractors and suppliers for cost information
- Existing client information - benchmark data from previous projects
How do you take account of the project location and why?
A location factor is usually applied to recognize differences in construction prices. For example, a project in London is typically more expensive than a similar project in Nottingham
What are some of the key reasons why we have cost overrun on a project?
- Ambiguous client brief or changes in the later stages of the project
- Unrealistic cost estimates
- Project risk is realized or not properly managed
- Inadequate management control or processes
- Uncoordinated design
- Unknown external factors (for example global pandemics)
- Unsuitable tendering and/or procurement strategy selection
- Statutory authority influences such as onerous planning permission conditions
What is BWIC?
- BWIC stands for builder’s work in connection and is usually set as a percentage of the services cost
- BWIC refers to builder’s work that is necessary to allow other works to proceed (typically mechanical and electrical services but also other specialist installations)
Why is VAT usually excluded from the cost plan?
Employers my incur different levels of VAT (some might be exempt). Therefore, VAT is usually excluded to ensure the incorrect tax rate is not applied.
Can you tell me what you understand by the term benchmarking?
- Benchmarking is the use of historical data from projects of a similar nature
- Can be used as a comparison or check for cost planning purposes
- Benchmarking can highlight areas of design that are not value for money; or, if the price offered by the contractor is in line with market conditions
How would you undertake a benchmarking exercise for your client?
Produce a clear document which shows the various cost plan elements side-by-side with the benchmark project(s). This process will identify items which are considered abnormal, I would then endeavor to justify cost anomalies for flagged items
What are prime cost sums?
- A sum of money included in a unit rate to be expended on materials or goods from suppliers (e.g. supply only ceramic walls tiles at £36.00/m2)
- It is a supply only rate for materials or good where the precise quality is unknown
- Prime cost sums exclude all costs associated with fixing or installation, all ancillary and sundry materials and goods required for the fixing or installation of the materials or goods.
What is the difference between prime cost sums and defined provisional sums?
- A prime cost is limited to the cost of supplying the relevant item and does not include the cost of any work that relates to it (such as its installation)
- In contract, defined provisional sums include allowances for supplying the item and all related work to be performed by the contractor
Can you name some of the pricing documents we might use at tender stage?
- Bill of Quantities (BoQ)
- Schedule of Rates (SoR)
- Contract sum analysis
- Schedule of work
- Priced activity schedule
Can you name some of the pricing options for construction contract?
- Lump sum
- Cost reimbursable
- Remeasurement
- Target cost
- Guaranteed maximum price (GMP)
What is value engineering?
Value engineering is typically done when something goes over budget - by looking at the selection of materials, plant, equipment and processes to see if a more cost-effective solution exists that will achieve the same project objectives.
What is value management?
Value management is a team-based approach used to define the client’s objectives and ensure best value, whole-life solutions are selected to satisfy those objectives. It is not necessarily about cost cutting.
Where could you find tender pricing information?
- SPONS
- BCIS (Building Cost Information Service)
- In-house data
What are the payment timescales for the JCT Design and Build 2016 Contract?
- Contractor required to make an interim payment application before each INTERIM VALUATION DATE (Cl. 4.7.3)
- Subsequent 7 days is the Due Date (Cl 4.7.2)
- Then no later than 5 days a PAYMENT NOTICE is issued by Employer stating the sum it considers to have been due on the Due Date. Other application becomes a payment notice (Cl. 4.7.5)
- A payless Notice may be issued no later than 5 days before Final Date for Payment (Cl 4.9.5)
- 14 days (Cl. 4.9.1) from due date is final date for payment
What is a lump sum contract?
- Fixed price lump sum pricing, provides payment for a set amount
- The amount of the fixed price or lump sum is determined by a contractor by estimating their cost to provide the work, and then adding overhead and profit margin.
What are the key advantages and disadvantages of lump sum contracts?
Advantage: the contractor takes on the pricing risk but stands to benefit from increased profit if actuals costs turn out to below the estimated costs.
Advantage: Cost certainty from the employer
Disadvantage: this agreement represents a higher risk to the contractor. if the contractor underestimates their cost, the profit margin decreases and may disappear altogether
Disadvantage: As a result of the additional risks faced by the contractor, they may increase their tender price
What is a cost plus contract? (cost reimbursable)
Cost-plus contracts involve the employer paying the contractor for the costs incurred during the project, plus a pre-agreed percentage for profit
What are the key advantages and disadvantages of cost plus contracts?
Advantage: Inaccuracies in the initial bid aren’t as detrimental as they are with lump sum contracts
Advantage: Allow employers to make design changes along the way, contractors know they’ll be paid for the extra time for materials which those charges incur
Disadvantage: The final price is uncertain until the end of the project
Disadvantage: Contractor may deliberately incur higher costs to increase profit (no incentive for efficiency)
What is a remeasurement contract?
- Works are carried out based on pre-agreed unit rates
- The actual quantities of work carried out are measured and the tendered rates are applied to those quantities
- The contractor is paid for the actual work they have done so the final value of the project will be derived based on the unit prices and exact quantities
What are the key advantages and disadvantages of remeasurement contracts?
Advantage: Since the work is tendered on approx quantities, the contractor will submit competitive prices in their tender.
Advantage: The contractor’s risk is comparatively low
Disadvantage: There is less cost certainty until the project is complete
Disadvantage: General accuracy of cost forecasting
Disadvantage: the risk for the employer is higher (compared to a lump sum contract)
What is a target price contract?
- The main difference between a target and conventional contract is the mechanism for sharing risk and opportunity
- The target cost is set early in the project, upon completion, cost savings or overruns are shared between the contractor and the employer based on a pre-arranged agreed formula or percentage. This is often termed the ‘pain & gain’ mechanism
What are the key advantages and disadvantages of target price contracts?
Advantage: the contractor and employer are incentivized to reduce costs
Advantage: Encourages active and equitable risk sharing, based on a clearly defined allocation of risk agreed at the outset of the project
Disadvantage: The employer and contractor must share pain and gain, this exposes the employer to greater risk, pain/gain share may not be easily understood by all parties
What is a guaranteed maximum price (GMP) contract?
- A guaranteed maximum price contract (GMP) set a limit that the employer will pay their contractor, regardless of actual costs incurred
- If the actual costs of the works is lower than the guaranteed maximum price, the contract should set out which party will benefit from the savings. Usually, the savings will be split between the employer and contractor using a pre-agreed formula or percentage
What are the key advantages and disadvantages of GMP?
Advantage: Establishes the employer’s maximum financial commitment (subject to employer variations). If the contractor’s costs exceed the target cost, only the target cost sum is paid
Advantage: Both the contractor and employer have potential to benefit from the savings
Disadvantage: The contractor will have to share any savings made while taking on the risk of cost overrun