Construction Technology and Environmental Services Flashcards
What is buildability?
- Buildability can be defined as the extent to which the design of a building facilitates the ease of construction.
- To help improve buildability, early contractor involvement should be considered to benefit from their experience and expertise.
What are the benefits of off-site construction over in-situ?
- Safety - Hazards such as falls from height are more likely to occur on site than in the factory
- Efficiency and quality - Construction takes place in a controlled environment
- Sustainability - Reduction in waste produced
- Speed - Work in the factory can be scheduled to begin at the same time as other activities on site, resulting in a shorter build programme.
What are temporary works?
Temporary works are the parts of a construction project that are needed to enable the permanent works to be built, they are usually required for safety or even access reasons. Examples are:
- Propping
- Scaffolding
- Formwork
- Excavation support
- Access and task lighting
What are hoists?
Designed for the vertical transportation of materials and/or people.
What is shoring?
Form of temporary support given to existing buildings and excavations. The purpose is to prevent collapse or excessive movement.
What is substructure?
- Substructure is the lower portion of the building (in the ground) which supports the superstructure.
- Transmits the loads of the building into the ground.
- Includes foundations, basements and retaining walls etc.
What is ground heave?
- Ground heave is usually associated with clay soil which swells when wet, causing the upward movement of the ground.
- As the soil generally cannot expand downwards or sideways, the result is that the exposed upper surface of the soil rises up.
What are some of the techniques available for ground improvement?
- Vibro compaction
- Vibro stone columns
- Vertical drains and vacuum consolidation
- Soil mixing
- Dynamic compaction
- Dynamic replacement
What are the different forms of excavation?
- Site clearance operations (removing vegetation and rubble)
- Stripping topsoil
- Reduced level dig (to reach formation level)
- Cut and fill
- Excavation for foundations
What are the key factors the contractor should consider when excavating?
- Nature of the soil and moisture content of the ground
- Method of excavation
- If ground support systems are required
- Proximity of existing buildings
- Depth of excavation
- Underground services and drainage
Have you come across the terms SUDs?
- Sustainable Urban Drainage Systems
- SUDS are designed to maintain stormwater locally (as close to its source as possible), to mimic natural drainage and to encourage infiltration and/or attenuation.
- SUDS help to reduce the reliance on existing drainage infrastructure.
What is the purpose of a foundation?
- Foundations provide support for structures, transferring their load to the ground to avoid excessive settlement.
- Foundations should bear the load of the superstructure.
What are the typical considerations when selecting the type and size of foundations?
- The total load of the building
- Nature and load bearing capacity of the ground
- Type of structure
- Cost
- Construction constraints (for example, their proximity to adjacent buildings/structures).
What are the different types of foundation?
- Strip foundations
- Pad foundations
- Raft foundations
- Piled foundations
What is a raft foundation?
A raft foundation is essentially a continuous slab that extends over the entire footprint of the building. The raft spreads the load of the building over a larger area than other foundations, the stress acting on the ground below is reduced.
What are pad foundations?
- Pad foundations are typically used to support individual or multiple columns, spreading the load to the ground below.
- They are usually square or rectangular on plan and can be reinforced or non-reinforced.
What are strip foundations?
As the name suggests, the formation is in a strip of linear structure that ultimately serves to spread the weight across the total area of the ground, typically used to support masonry.
What are pile foundations?
- A pile is column (usually concrete) that extends deep into the ground.
- Where the bearing capacity of the soil is poor imposed loads are very heavy, pile foundations may be required.
- There are two main types of pile:
End bearing piles
Friction piles - There are two main construction methods:
Bored piles.
Driven concrete piles.
In what scenarios might a piled foundation be the best solution for a project?
- Where the structure is heavy and the underlying soil is weak
- In areas where settlement issues are common
- Where the sub-soil water table is high
- Where the load distribution of the structure is not uniform
- Presence of horizontal forces
Can you explain how end bearing and friction piles transfer the load of building?
- End bearing piles - The bottom of the pile rests on a layer of strong soil or rock, the load of the building is transferred through the pile onto the strong layer.
- Friction piles - Friction piles work on a different principle, friction piles develop most of the pile-bearing capacity by shear stresses along the sides of the pile. In other words, the surface of the pile works to transfer the forces to the soil.
What are the differences between bored piles and driven piles?
The fundamental difference lies in their point of manufacture. A driven pile is formed off site under factory-controlled conditions and a bored pile is manufacture on site.
What are the advantages and disadvantages of driven piles?
Advantages
- Piles can be precast to the required specifications
- Piles of any size, length and shape can be made in advance
- A pile driven into granular soil compacts the adjacent soil mass, the bearing capacity of the pile increase as a result.
- Fast, neat and clean installation
Disadvantages
- Requires heavy equipment for handling and delivery
- Increased noise and vibrations generated by driving the piles
- Can be costly if the piles are short
What are the key advantages and disadvantages of bored piles?
Advantages
- Any size or shape of pile can be formed on site
- No risk of damage during delivery and handling
- Reduced vibrations and noise
Disadvantages
- Significant spoils are generated that need to be handled
- Reliance and coordination on multiple trades (reinforced crew, piling crew and concrete supplier)
- Unlike driven piles, bored piles do not improve the bearing capacity of the ground.