Commercial Management (of construction works) Flashcards

1
Q

How would manage/monitor overall project costs?

A
  • Cashflow forecasting
  • Operate change control processes
  • Regular cost reporting
  • Manage expenditure of provisional sums
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is “Cost Value Reconciliation”?

A
  • CVRs are carried to monitor expenditure against budgets on construction projects.
  • Value (Revenue) - Cost = Profit (Reconciliation)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How would go about undertaking financial due diligence of a contractor?

A
  • Credit check at PQQ or tender stage - identify % risk of going insolvent.
  • Request company financial reports.
  • Consider the structure of the company - can PCG be obtained?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How can we proactively control costs during construction for a client?

A
  • Robust change control procedures
  • Regular attendance on site to keep track of the works
  • Regular dialogue with design team and contractor to keep informed of progress and issues
  • Risk management meetings
  • Rigorous payment process - interim valuations - payment certificate
  • Hold retention on payments
  • Use of cashflows to forecast future payments
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a “Purchase Order”?

A
  • a PO is a commercial document issued to a buyer by a seller
  • Client arranges for the PO to be raised
  • Sending a PO to a supplier constitutes a legal offer to buy a product / service
  • Acceptance of a purchase order by a seller usually forms a contract between the buyer and the seller, so no contract may exist until the purchase order is accepted.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are “Capital Allowances”?

A

Capital allowances is the practice of allowing a company to get tax relief on tangible capital expenditure by allowing it to be expensed against its annual pre-tax income.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the reason for capital allowances?

A

Capital allowances are used by the government as an investment incentive to encourage business to spend money on assets that are desirable for policy reasons.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Is there any legislation related to capital allowances?

A

Capital Allowances Act 2001 (CAA 2001).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is “Earned Value Analysis”?

A

In its most simple terms, EVA can be seen as an extension to the CVR, as it brings the project programme into the equation, linking cost, value and time. The additional dimension of time is used to
assist in forecasting and to provide a cross-reference to
operations as a further indicator of performance and
delivery output.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a “Cost to Complete” exercise?

A

A Cost-To-Complete estimate allows us to account for performance, progress, revenue and costs to-date on the project, and forecast the remaining revenue, budget and profitability for the rest of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are “Accruals”?

A

Accruals are made in the financial accounting system of a contracting organization to represent the difference between the total liability assessed as owed to a
subcontractor and the amount already paid to that
subcontractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the two key areas that should be considered in the UK in regard to subcontract payment timescales?

A
  • The Construction Industry Scheme (CIS), under which
    contractors must deduct accrued amounts for tax and
    National Insurance from a subcontractor’s payments
    and pass it to HMRC.
  • The HGCRA. Among many other matters, this piece of
    legislation sets out the key documents, stages and
    timescales that define the payment for works under a construction contract in the UK.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is CAPEX?

A
  • “Capital Expenditure”

- They are funds used by a company to acquire or upgrade physical assets such as property or equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is OPEX?

A
  • “Operational Expenditure

- Expenditure a business incurs performing its normal business operations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Businesses typically split expenditure into capital and revenue - why?

A

You can claim capital allowances on qualifying capital expenditure but not on revenue expenditure. Capital expenditure goes onto your balance sheet whereas revenue goes onto the profit and loss account.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How would you produce a subcontract final account?

A

It should generally be geared towards the following (and, in the absence of any other specific requirements, should include these):

• the original subcontract agreement, including the BoQ
or alternative pricing document
• all records and correspondence with the
subcontractor (as discussed in 3.3.3.1)
• the latest subcontract application for payment (or final
account if submitted)
• details of all variations or changes, with full
substantiation
• any remeasures (if applicable)
• full substantiation of any cost-based elements

It is good practice to deal with outstanding matters as
soon as possible, while they are fresh in the memory