Explain Change Control Process on Project Winchester

A
  1. Change Control is raised (should include scope of the change, originator, indication of programme and cost impact).
  2. Cost estimate of the change is produced and/or programme impact ( if programme permits request for quotation is issued)
  3. Change submitted for approval to the Client
    - ————–
    4a. If rejected - reason for rejection is recorded and change closed.
    - ————–
    5a. If approved change to be instructed, CE to be raised if relevant
    5b. cost agreed between Contractor and us
    5c. budget allocation adjusted
    5d. Client’s cost approval before the implementation
    5e. CE implemented.