Contract practice Flashcards
What is contract?
A contract is a legally binding agreement between at least two parties in order to fulfil an obligation in exchange for something of value. Contracts can either be written, oral, or a combination of both.
What are the main types of traditional contracts?
- Lump sum contract – where the contract sum is known before works starts on site and the contractor agrees to undertake a defined amount of work for a specific amount. This type of contact is often based on firm bill of quantities and drawings.
- Measurement contracts – where the contract is assessed and remeasured as on previously agreed basis. This type of contract can be based on approximate bill of quantities and drawings.
- Cost reimbursement contracts – where a contractor is reimbursed on the basis of the prime cost of labour materials and plant plus an agreed percentage addition to cover overheads and profits.
- Design and build - where the contractor both designs and builds a project
- Management contracts – a management contractor managing the works although the contractor does not actually carry out any works.
- Target Cost - A target cost contract is a type of cost reimbursable contract under which the contractor is paid the ‘actual cost’ against the target cost and then savings or cost overruns are shared based on an agreed mechanism.
Standard forms of contract in UK
- JCT (The Joint Contracts Tribunal)
o DB: Design and build contract.
o CE: Constructing Excellence contract.
o CM: Construction management contract.
o IFC: Intermediate form of building contract.
o MC: Management building contract.
o MTC: Measured term contract.
o MW: Agreement for minor work.
o PCC: Prime cost building contract.
o MP: Major project construction contract.
o RM: Repair and maintenance contract (commercial).
o SBC: Standard Building Contract. - ACA (Association of Consultant Architects)
a. PPC: Standard form of contract for project partnering.
b. SPC: Standard form of specialist contract for project partnering. - Chartered Institute of Building
a. CPC 2013: CIOB Contract for use with Complex Projects. - FIDIC (Fédération Internationale des Ingénieurs-Conseils - the International Federation of Consulting Engineers)
FIDIC’s core suite of contracts includes:
o Conditions of Contract for Construction. The Red Book.
o Conditions of Contract for Plant & Design-Build. The Yellow Book.
o Conditions of Contract for EPC Turnkey Projects. The Silver Book.
o The Short Form of Contract. The Green Book. - NEC (The New Engineering Contract): Engineering and Construction Contract)
Option A: Priced contract with activity schedule.
Option B: Priced contract with bill of quantities.
Option C: Target contract with activity schedule.
Option D: Target contract with bill of quantities.
Option E: Cost reimbursable contract.
Option F: Management contract.
Option G: Term contract.
Other less commonly used forms of contract include:
• IChemE (The Institution of Chemical Engineers) forms of contract.
• ICC Infrastructure Conditions of Contract. A relaunch of CoC (see below)
• The ICE Conditions of Contract (CoC) (previously maintained by the Institution of Civil Engineers) have been withdrawn in favour of NEC contracts. See ICE Conditions of Contract for more information.
• IMechE/IET (The Institution of Mechanical Engineers / The Institution of Engineering Technology) Model Forms of General Conditions of Contract for electrical works (MF/1-4).
• The Civil Engineering Contractors’ Association (CECA) subcontracts for the ICC (above). Contract conditions
What are typical contract documents?
- the agreement
- General Conditions
- Special conditions
- Scope of work
- drawings
- specifications
- Bill of quantities if required
- Activity Schedule if required
- Programme of work if required
- contract sum analysis
- existing building information
What is required to make a legally binding contract?
- offer by one party
- acceptance by the otter party
- consideration of the offer
- intent to form a contract
- legality of a contract
- capacity to make an agreement
What are the forms of contract executions? What is the difference between the contract executed under seal and under hand and their limitations
a. under seal - signed by the parties, witnessed and most importantly made clear that it is executed as a deed; limitation period 12 years, does not have to be supported by valuable consideration
b. under hand – a ‘simple contract’ that is just signed by the parties- limitation period 6 years – actions cannot be brought after 6 years from the date of which cause of the action occurred.
Valuable consideration – something of value in the eye of law.
What are the principles of NEC 4 Contracts?
- NEC is a family of contracts designed specifically to be flexible, clear and to actively stimulate collaboration and professional project management;
- NEC3 adopts a fundamentally different philosophy and practice to most other standard form construction or engineering contracts. Its three core underlying principles are:
- clarity and simplicity: the contract is well-supported with additional materials, including detailed flow-charts and guidance notes. NEC3 is intended to be clear, simple and easy to use, and is written in the present tense in plain English. However this can lead to problems as its brevity can, in some cases, create ambiguity and much of its terminology is untested in the courts;
- stimulus to good management: overall, NEC3 focuses on ‘real time’ management of the project rather than looking back on what the parties should have done. However it is very heavy on administration, and requires good understanding of its procedures and sufficient resources from both the employer and the contractor to make it a success;
- flexibility: NEC3 can be constructed from nine sections of core clauses, six main options, two dispute resolution options and seventeen secondary options. This flexible approach is intended to avoid the need for lots of bespoke amendments, reduce the need for lengthy negotiation and also reduce the potential for disputes. However, in practice most of NEC3 contracts include considerable bespoke amendments – known as the ‘Z’ clauses as they form part of Option Z under the contract.
NEC Suite structure
The principal NEC3 contracts, short contracts and subcontracts can be broadly grouped into works, services and supply as shown below. The choice of NEC3 form depends on the project complexity and level of risk.
WORKS - Works encompasses purchases such as the construction, refurbishment and decommissioning of buildings, structures, process plants and infrastructure – including everything from houses, schools, hospitals and leisure facilities to infrastructure for water, energy, transport, industry and waste.
SERVICES - Services includes purchases of professional services such as engineering, architectural, project management and consultancy works. It also covers composite services such as facilities management, cleaning, catering, security, maintenance and data processing.
SUPPLY - Supply includes supply of high-value goods and associated services such as transformers, generators, rolling stock, cranes, gantries and complex plant. It also includes lower-risk items such as building materials and products, stationery, personal protective equipment and parts.
NEC Contract structure
- Contract Data Part 1 and 2
- Core Clauses (9)
- Main Options (A to F)
- Despite resolution (W1, W2 and W3(NEC4)
- Secondary Option - X
- Z Clauses
What is a Compensation Event?
A compensation event is a term used in NEC contracts to mean an event which can affect the cost to the Client of the work being carried out, the time when the works will be completed, or both. A compensation event is the only way in which these can be changed
Clause 60 – 65
• Clause 6
• Compensation events are events which are usually not the fault of the contractor and change the cost of the work, or the time needed to complete it. As a result, the prices, key dates or the completion date may be reassessed, and in many cases the contractor will be entitled to more time or money.
• There are 21 reasons for CE stated in Clause 60.1, for example:
o instruction changing the scope (60.1(1))
o Client not providing access to the Site (60.1(2))
o Client does not providing something that they should (60.1(3))
o PM gives instruction to stop/snot to start work (60.1(4))
o The PM changes earlier decision (60.1(8))
o an event which stops contractor t=completing the works that neither Party would prevent (60.1(19)
o if the proposed instruction is not accepted (60.1(20))
• contractor has 8 weeks to notify a CE- PM response in one week
• if the PM fails to response within time allowed, the Contractor may notify PM of its failure, if does not respond in further 2 weeks then the CE is treated as accepted.
• Quotation for a CE included changes to the Prices and any delays
• The Contractor submits a CEQ within 3 weeks, PM to respond in 2 weeks
What is the difference in assessing the payment due depending on main contract options?
• the different payment mechanisms for the six main Options are based on the use of three key defined terms; the Prices, the Price for Work Done to Date and Defined Cost.
• Option A: Priced Contract with Activity Schedule - PWDD is price for the activates completed within the Activity Schedule; in terms of the Defined cost – this is used for CE assessment based on Schedule of Costs Components.
• Option B: priced contract with bill of quantities- The PWDD is calculated using the Bill of Quantities rates and lump sums and the total re-measured quantity of work completed according to the definition and criteria stated in this clause
The basis of the definition of Defined Cost in these Options is the cost of the components in the Schedule of Cost Components less Disallowed Cost.
• Option C: target contract with activity schedule; - Payments are based on the Contractor’s costs rather than what works were carried on; The PWDD is based on the Defined cost plus fee; the Prices in the Activity Schedule are not used to determine the PWDD but the total of the Prices is used when the target is calculated. the Contractor’s share is also calculated taking into account the differences between the total of Prices (contract + CE) and PWDD based on pre-agreed share percentage.
• Option D: target contract with bill of quantities; Payments are based on the Contractor’s costs rather than what works were carried on; The PWDD is based on the Defined cost plus fee; BoQ is used to determine the total of the Prices but no for the PWDD.
The basis of the definition of Defined Cost in these Options is the cost of the components in the Schedule of Cost Components less Disallowed Cost.
• Option E: cost reimbursable contract; the contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee. The financial risk involved is largely taken by the client.
o PWDD is the total Defined Cost plus the Fee
o the Prices are the forecast of the total Defined Cost for the whole of the works plus the Fee.
• Option F: management contract. - Option F is a cost reimbursable management contract in which the works are constructed by a number of different works contractors who are contracted to a management contractor. The management contractor is responsible for the work and is paid a fee (the cost that it pays the works contractors plus an additional fee), while the financial risk is largely taken by the client.
o PWDD is the total Defined Cost plus the Fee
o the Prices are the forecast of the total Defined Cost for the whole of the works plus the Fee.
What is the Construction Act?
The Housing Grants, Construction and Regeneration Act 1996 (HGRA - also known as the Construction Act) is intended to ensure that payments are made promptly throughout the supply chain and that disputes are resolved swiftly.
Provisions of the act include:
• The right to be paid in interim, periodic or stage payments.
• The right to be informed of the amount due, or any amounts to be withheld.
• The right to suspend performance for non-payment.
• The right to adjudication.
• Disallowing pay when paid clauses.
The Act applies to all contracts for ‘construction operations’ (including construction contracts and consultants’ appointments). If contracts fail to comply with the act, then the Scheme for Construction Contracts applies.
How was the contract documentation produced on NCA Project?
• As this was the NEC Option A contract through Design and Build Procurement Route, the following information have been prepared:
• Contract – Contract Data Part 1 and Part 2
o The conditions of contract are the core clauses and the clauses for main Option A, dispute resolution Option W2 and secondary Options X2, X7, X13, X14, X15 and X18 - refer to NEC3 printed form for details], Y(UK)2, Y(UK)3, and Z1 to Z50 (incl.), of the NEC3 Engineering and Construction Contract April 2013.
• Works Information – prepared by the M&E Design, Principal Designer and Architect.
o General
o Background
o scope of works
vertical transportation
architectural
o Existing drawings and documentation
drawings of all floors
Certificate for Identification of Asbestos Fibs to lift motor room and Lift Shafts
existing restaurant doors drawings.
• Pre-Construction Information
o Executive summary
o Descriptions of the project (site location, programme details, key project participants, general descriptions of works)
o Employer’s Considerations and Management Arrangements (Employer’s Safety Standard, communication, monitoring and review, welfare provision, access to site, security requirements, emergency procedures, accident notification and escalation)
o Environmental Restrictions and Existing on-site risk (boundaries and access, deliveries and waste collation and storage, hazardous materials, asbestos, plant and equipment, existing services)
• Programme (ID, Task Name, Start, Finish, Duration & Chart)
• Activity Schedule
1. Preliminaries
o Preconstruction management – staff costs per month
o Construction management staff
o construction multi service gang
o Design fee
o Site set up
o temporary works,
o plant and tools
o safety and welfare
o Temporary service installation
o Office equipment ( telephone, photocopier, site furniture,)
o Site service (rubbish removal, builders clean)
o Performance bond
2. Works
• Sub-contractor’s preliminaries
o Strip out Works’ phase
o Lift car finishes - Phase 1 - lift 2
o Lift company associated BWIC
o Maintenance during Works phase 1
o Phase 1 - lift 8
o Restaurant doors
o Removal of floor finishes
o Restaurant doors removal of existing
o Restaurant doors installation
o Restaurant doors screenwork
o Restaurant doors access route for power
o Restaurant doors alteration to power
o Protect floor in front of lift
o Restaurant doors post and wireless call point
o Decoration to lift entrance wall Works phase 1 - lift 2
• Advance Payment Bond – delivered by deed, contractor, the employer and the guarantor.
What were the main clauses on NCA Project?
• The conditions of contract are the core clauses and the clauses for main Option A, dispute resolution Option W2 and secondary Options X2, X7, X13, X14, X15 and X18 - refer to NEC3 printed form for details], Y(UK)2, Y(UK)3, and Z1 to Z50 (incl.), of the NEC3 Engineering and Construction Contract April 2013.
What is the Works Information and that they include?
• Works information specifies and describes the works the contractor is to provide and sets out any constraints to how the contractor provides the works. It is presented either in the documents which the contract data states it is in, or in an instruction given by the project manager in accordance with the contract (although this may constitute a compensation event).
• Works information may be prepared both by the employer and the contractor. Employer’s works information sets out the works and constraints for the contractor. Contractor’s works information is prepared in relation to those parts of the works the contractor is required to design. The employer’s works information is identified in the contract data part one, whilst the contractor’s works information is identified in the contract data part two. Both sets of works information should be consistent, and where there is disagreement between them, priority is given to the employer’s works information.
• It is important that the employer’s works information creates a complete and precise statement of the employer’s requirements so the risk the contractor may misinterpret or misunderstand them is minimised. Clear, unambiguous language should be used, subjective terms should be avoided and it should not include anything that repeats or contradicts the contract data or conditions of contract. References to standard specifications should be checked for consistency with other parts of the contract.
Works information might include:
• Technical information, specifications and drawings.
• Constraints for how the contractor provides the works, such as safety requirements.
• Work to be designed by the contractor.
Typically, the structure of works Information might include:
• A description of the works.
• General constraints on how the contractor provides the works.
• Contractor’s design.
• Completion.
• Programme.
• Quality assurance.
• Tests and inspections.
• Management of the works.
• Working with the employer and others.
• Services and other things to be provided.
• Health and safety.
• Subcontracting.
• Title.
• Acceptance or procurement procedure.
• Accounts and records.
• Parent company guarantees.
• Performance bonds.
• Advanced payment bonds.
• Low performance damages.
• Employer’s work specifications and drawings.
The contractor’s primary obligation is to provide the works in accordance with the employer’s works information. This means contractors are only obliged to do things the works information says they must do.