Project Delivery Methods Flashcards

1
Q

What are the three major classifications of Project Delivery Methods?

A
  • Traditional
  • Design Build
  • Construction Management (CM)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the three linear stages of Traditional project delivery?

A
  • Design
  • Procurement
  • Construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the three prime players in Traditional project delivery?

A
  • Owner
  • Designer
  • Builder
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How many contracts are there in Traditional project delivery, and who are they between?

A

Two contracts:

  • Owner & Designer
  • Owner & Builder
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the advantages of Traditional project delivery?

A
  • Familiar to all parties
  • Initial Final Cost usually known at beginning
  • Open bidding gives Owner lowest price
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the disadvantages of Traditional project delivery?

A
  • No Contract between Designer & Builder

- Parties may interpret details differently

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the two prime player in a Design-Build project delivery?

A
  • Owner

- Design-Build entity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How many contracts does a Design Build project delivery have?

A

Just one - Owner & the Design Build entity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the advantages of Design Build project delivery?

A
  • Owner is single point of contact
  • Good communication between Designer & Builder
  • Project can be fast-tracked
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the disadvantages of Design Build project delivery?

A
  • Lack of direct connection between Owner & Designer

- Lack of check and balances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the Construction Management (CM) project delivery?

A

One firm, representing the owner, coordinates all activities from concept design through to acceptance of the facility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the advantages of CM project delivery?

A
  • Reduced work load for Owner
  • Careful monitoring of costs
  • Fewer change orders
  • Management expertise can shorten project length
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the disadvantages of CM project delivery?

A
  • Added cost of CM

- Potential for confusion and friction among team members

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the two ways an Owner can engage a CM?

A
  • CM without risk

- CM at risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the four prime players in CM without Risk?

A
  • Owner
  • Construction Manager
  • Designer
  • Builder
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the three separate contracts in CM Without Risk?

A
  • Owner & CM
  • Owner & Designer
  • Owner & Builder
17
Q

What are the four prime player in CM at Risk?

A
  • Owner
  • Construction Manager
  • Designer
  • Builder
18
Q

What are the three separate contracts in CM at Risk?

A
  • Owner & CM
  • CM & Designer
  • CM & Builder