Construction Contracts Flashcards

1
Q

What is a Construction Contract?

A

A private law agreement between

  • a person wanting something built (Owner)
  • a builder (Contractor)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What items are set out in a Construction Contract?

A
  • The work to be performed
  • The schedule for the work
  • The price for the work
  • Other rights and responsibilities of the parties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main players in Construction Projects?

A
  • Owner
  • General Contractor
  • Architect
  • Engineers
  • Trade Contractors
  • Suppliers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the three main Standard Form Documents for industry in Canada?

A
  • CCDC (Canadian Construction Documents Committee)
  • CCA (Canadian Contractors Association)
  • MMCD (Master Municipal Construction Documents)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the Types of Standard Form Contracts?

A
  • Lump Sum
  • Unit Price
  • Cost Plus Fee (Negotiated)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Lump Sum suitable for?

A

Projects where project scope is well defined, and quantities of materials known

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are advantages of Lump Sum?

A
  • Owner has price certainty
  • Owner knows what the end project will be
  • Contractor can realize profit if project completed below fixed price (incentive to be efficient)
  • Contractor receives monthly progress payments based on job completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are disadvantages of Lump Sum?

A
  • Flexibility to incorporate design changes is limited
  • Complete set of plans required before bidding and construction can begin
  • Can be risky to contractors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Unit Price suitable for?

A
  • Projects where project scope is well defined, but uncertainty in material quantities
  • Projects that can be broken into work items that can be characterized by units
  • Often used on highway projects where earthwork is predominant
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are advantages of Unit Price?

A
  • Allows some flexibility in meeting variations in the quantity of work
  • Contractors don’t need to be as precise in their takeoffs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are disadvantages of Unit Price?

A
  • Owner does not have a precise overall cost for the work until it’s complete
  • Measured field quantities are pay quantities (Owner must measure precisely)
  • Can be manipulated by contractors (unbalancing the bid)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What deviation in Unit Price Contracts requires renegotiating?

A

+/- 15%

+15% Owner will request Unit Price reduction
-15% Contractor will request Unit Price be increased

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the key factors in a Negotiated Contract?

A
  • Owner has flexibility to select contractor on a basis other than low bid
  • Owner invites contractors to review project documents available at time of negotiation
  • Documents can be complete or incomplete
  • Owner will evaluate contractors based on experience, reputation, staff availability etc. all in addition to cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the four common fee structures of a Negotiated Contract?

A
  • Cost + % of Cost
  • Cost + Fixed Fee
  • Cost + Fixed Fee plus profit-sharing clause
  • Cost + Sliding Fee
How well did you know this?
1
Not at all
2
3
4
5
Perfectly