Project and Practice Management Flashcards
During negotiations to develop a final, fixed con struction cost with a preselected contractor, the owner wants to reduce the cost of construction suggested by the architect’s original cost estimate. The architect should advise the owner to
A. suggest that the project be put out to bid if the price is too high
B. set a fixed limit on the construction cost, and negotiate directly with the subcontractors
C. establish contractual penalties for exceeding the architects original estimate
D. consider the contractor’s recommendations for alternate construction methods
The answer is D.
Solution
On a negotiated project, the contractor is in the best posi tion to recommend alternate materials and construction methods that will lower costs while still meeting the owners design requirements.
Bidding the project is no guarantee that the price will be lower; in fact, it may go up. The owner should not negoti ate with subcontractors; that is the contractor’s responsibil ity. Simply setting an arbitrary limit on construction cost does not encourage a lower price and is a punitive way to limit costs during negotiation.
An architect has been hired to design an addition to a building of historical significance. Part of the project includes renovating and remodeling a portion of the exist ing building. The architect suggests that the owner retain the services of a historic preservation consultant. In order for the architect to make optimal use of the consultant’s work, the owner should hire the consultant
A. as soon as possible
B. after schematic design work has been completed
C. after the design development phase
D. on an as-needed basis for technical questions
The answer is A.
Solution
In general, consultants should be hired as soon as possible on a project so they can advise on initial scope and design direction as well as on more technical questions.
For aesthetic reasons, the architects specifications on a building project call for a specific method of constructing a concrete wall and slab that is not in accordance with nor mal construction practices. The contractor tells the architect that the contractor believes the specified method will create unsafe conditions. According to AlA Document A201 (CCAC Document 2), what action must the contractor take?
A. Proceed with construction following the instructions in the specifications.
B. Notify the architect in writing, and propose alternate methods of construction.
C. Give written notice to both the owner and architect of the safety concerns, and wait for instruction from the architect.
D. Modify the method to make it safe, and proceed with construction.
The answer is C.
Solution
Generally, the contractor is solely responsible for the means and methods of construction, unless the contract docu ments give specific instructions to the contrary. However, upon determining that the instructions create an unsafe sit uation, the contractor must give timely written notice to the owner and architect and not proceed with the unsafe por tion of the work until receipt of further written instructions from the architect. If the contractor is instructed to proceed regardless of the safety concerns raised, the owner becomes solely responsible for any resulting loss or damage.
- Study Note: Review the provisions of the standard general conditions that relate to the contractors responsibilities.
If a general contractor fails to pay a subcontractor, the subcontractor can protect its financial interests by using
A. a performance bond
B. a contractor’s affidavit of payment
C. builders risk insurance
D. a mechanic’s lien
The answer is D.
Solution
A mechanic’s lien is a claim by one party against the property of another party for the satisfaction of a debt. It can be used by a material supplier, subcontractor, or contractor who has a financial interest in the project to gain payment. In some states, the architect can file a mechanics lien to obtain pay ment for professional services rendered. In extreme cases, a mechanics lien can force the sale of the owner’s property to satisfy the debt. A lien encumbers the owner’s property, making it impossible to sell or transfer the property until the lien is satisfied. This is usually enough pressure to force the owner to resolve the situation.
- Study Note: As an alternative to liens, a labor and mate rial payment bond can protect the owner against claims by subcontractors and suppliers who are not paid by the general contractor. The bond gives these parties the right to collect payment from the surety (the company that issued the bond). Review and understand the various types of bonds used on a construction project, including a bid bond, a per formance bond, and a labor and material payment bond. Also understand the different types of insurance and how insurance differs from a bond.
According to AlA Document B141, Standard Form of Agreement Between Owner and Architect (RAIC Document 6), the architect must prepare cost estimates for the project during the
A. schematic design phase
B. design development phase
C. schematic and design development phases
D. schematic, design development, and construction documents phases
The answer is D.
Solution
AlA Document Bl41 (RAIC Document 6) requires the architect to develop a preliminary cost estimate based on area, volume, or a similar conceptual estimating technique, and subsequently update it at each phase through to the construction documents phase.
- Study Note: Know the different types of estimating used for the various phases of design.
When deciding on the types and amounts of insur ance needed for a project, which of the following sources should the owner rely on?
I. architect
II. contractor
III. owners attorney
IV owner’s insurance agent
A. I only
B. I and IV only
C. II and III only
D. III and IV only
The answer is D.
Solution
The owner should seek advice from his or her legal counsel and insurance agent on matters of insurance.
The architect should not give insurance advice. The archi tect can assist the owner and insurance agent by providing AlA Document G612, Owner’s Instructions Regarding the Construction Contract, Insurance and Bonds, and Bidding (CCDC 21, A Guide to Construction Insurance). The contrac tor should only be involved with the various types of insur ance that contractors must carry for the project.
- Study Note: Review the various provisions and require ments for insurance in Article 11 in AlA Document A201 (or the appropriate sections of CCAC Document 2).
According to AlA Document Al01 (CCDC Document 2), the owners final payment must be made
A. no later than 30 days after issuance of the final certificate for payment
B. no later than 30 days following substantial completion (substantial performance)
C. upon approval by the architect following correction of final punch list items
D. within 30 days following issuance of the certificate of occupancy
The answer is A.
Solution
Article 5 of AlA Document Al01 (CCDC Document 2) states that final payment to the contractor shall be made no later than 30 days after the issuance of the architect’s final certificate for payment, unless other provisions are written in.
- Study Note: Review the owner-contractor agreements (AlA Documents A201 and Al01, CCDC Document 2) and understand the basic provisions, including begin ning dates of construction, substantial completion, liqui dated damages, and payment processes.
On a large, privately funded project, the lowest bid is 5% higher than the owner’s original budget. Under the pro visions of AlA Document B141 (RAIC Document 6), the owner elects to revise the project scope and quality to reduce the cost. In this case the architect must
A. proceed to reduce the project scope and quality on a time and materials basis
B. develop an addendum to the owner-architect agreement for additional services
C. work with the owner to revise the project with additional compensation
D. modify the contract documents as necessary, without additional compensation, to comply with the budget
The answer is D.
Solution
Article 2.1.7 of AlA Document B141 (RAIC Document 6) requires that the architect shall, without additional com pensation, modify the documents for which the architect is responsible as necessary to comply with the budget.
- Study Note: Under the same article, the architect is enti tled to compensation for all services performed, even if the owner elects to terminate the agreement and not build the project. Additionally, the architect does not warrant or represent that bids or negotiated prices will not vary from the owners budget or from any estimate of the cost of the work prepared or agreed to by the archi tect.
Under the provisions of AlA Document B141 (RAIC Document 6), the architect is NOT required to
A. review laws and regulations applicable to the project
B. commission tests for possible groundwater pollution
C. develop a schedule of performance for architectural services
D. name a designated representative to act on the architects behalf
The answer is B.
Solution
Article 1.2.2 of AlA Document Bl41 (RAIC Document 6) clearly states that one of the responsibilities of the owner is to furnish tests, inspections, and reports required by law or by the contract documents. These include structural, mechanical, and chemical tests for air and water pollution or for hazardous materials.
For the remodeling and renovation of a historic build ing, the architect retains the services of a historic preserva tion consultant using AlA Document C141, Standard Form of Agreement Between Architect and Consultant (RAIC Docu ment 9). The consultant’s services include developing draw ings showing the repair and anchoring of existing stonework. During construction the contractor discovers that the anchoring methods specified by the consultant vio late the local building code and have to be modified at addi tional cost. The party responsible for the cost of the modifications is the
A. architect
B. consultant
C. contractor
D. owner
The answer is B.
Solution
Under the provisions of AlA Document Cl41 (RAIC Docu ment 9), consultants are responsible for code compliance regarding their area of work and for the accurate production of their drawings.
Prior to the commencement of design work, furnishing a site survey is the responsibility of the
A. architect
B. civil engineer
C. contractor
D. owner
The answer is D.
Solution
The owner is required to furnish and pay for site surveys according to both AlA Document B141 and AlA Document A201 (RAIC Document 6 and CCDC Document 2).
During design development for a small corporate headquarters building, the client informs the architect that the estimated construction costs must be reduced. Which three of the following actions would most likely reduce these costs?
I. Design and specify larger tolerances.
II. Examine areas of high maintenance and improve their quality.
III. Suggest changes that would make custom details closer to industry standards.
IV Examine ways to reduce the number of pieces in the details.
V Try to reduce the number of different details involved in the project.
A. I, II, and IV
B. I, III, and V
C. II, III, and IV
D. III, IV, and V
The answer is D.
Solution
Using industry standard details, reducing the number of components in the construction assembly, and reducing the number of unique details would all help reduce construc tion costs. There is not enough information given to deter mine if tolerances smaller than industry standards have been specified. Simply increasing tolerances greater than normal will not decrease the cost because contractors will price standard tolerances unless there is reason to do other wise.
Although it is implied that life-cycle costs are a considera tion because this is a corporate headquarters (presumably owner occupied and maintained), the question clearly states that “estimated construction costs” should be reduced, which means initial costs.
According to AlA Document B141 (RAIC Document 6), which of the following services is NOT part of the architects basic services for project closeout?
A. forwarding written warranties to the owner
B. sending a consent of surety to the owner
C. providing start-up assistance
D. meeting with the owner to determine the need for facility operation services
The answer is C.
Solution
Article 2.8.3 of AlA Document B141 (RAIC Document 6) lists services that the architect will provide only if specifi cally designated. Start-up assistance is one of these services.
Study Note: Review the list of extra services that are not normally part of the architect’s standard services. These include, among others, programming, geotechnical ser vices, existing facilities surveys, site analysis, landscape design, interior design, detailed cost estimating, on-site project representation, record drawings, and post contract evaluation.
What is one way an architect can ensure that the clients design goals will be satisfied by the final set of con struction documents?
A. Meet periodically with the project designer, job captain, and programmer to compare the cur rent status of the construction drawings with schematic design documents.
B. Have another architect in the office who is not working on the project review the drawings for compliance with the original program report.
C. Send the client periodic check sets of drawings, and request that any corrections be communi cated to the architect’s office within a set time period.
D. Make a checklist of design requirements based on the original design goals, and give this to the people working on the job so that they have a constant reminder of the client’s needs.
The answer is A.
Solution
Meeting regularly with the people responsible for the pro gramming, design, and execution of the project is the best way to facilitate communication.
Having another architect look at the drawings may be a good way to do a technical check, but that person may not be aware of the client’s design goals. It is common to request from the client information necessary to design the project and complete the working drawings, but isolating the client in reviewing them (unless specifically requested) does not encourage an exchange of ideas and information. Some clients are not savvy enough to understand the drawings or may feel uncomfortable asking questions, so issues may go unaddressed. Making a checklist for the drafting staff is a good way to communicate project goals to the team, but realization of the client’s objectives will require more coor dination than a checklist will allow.
Which type of architectural services fee structure is preferable when a client is embarking on his or her first architectural project and does not yet have a program?
A. fixed sum
B. multiple of direct personnel expense
C. percentage of construction cost
D. unit cost based on square footage
The answer is B.
Solution
It is very likely that clients undertaking their first construc tion project without a program would spend a great deal of their time and the architect’s time determining needs and making decisions. Programming is not considered to be part of the architect’s basic services. A cost plus fee method such as multiple of direct personnel expense would ensure that no matter how much time was spent on the project, the architect would still cover expenses and make a profit.