Codes and Regulations Flashcards

1
Q

According to ADAAG, what is the minimum clear floor space for one stationary wheelchair?

A. 24 in (610) by 36 in (915)

B. 30 in (760) by 48 in (1220)

C. 32 in (815) by 48 in (1220)

D. 60 in (1525) by 60 in (1525)

A

The answer is B.

Solution

The minimum clear floor space required for one stationary wheelchair is 30 in (760) by 48 in (1220) This critical dimension is the basis for many other accessibility guide­ lines, such as the amount of clear floor space required at a lavatory and the width of a hallway required to allow two wheelchairs to pass (60 in (1525), which is 30 in (760) times two).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

An assembly occupancy with an occupant load of fewer than 50 persons would be classified as occupancy group:

A. M

B. E

C. A

D. B

A

The answer is D.

Solution

An assembly occupancy with an occupant load of fewer than 50 persons would be considered a group B, or busi­ ness, occupancy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which of these events triggered revisions to the building codes?

A. the Chicago Fire of 1871

B. the San Francisco Earthquake and Fire of 1906

C. the terrorist attacks of September 11, 2001

D. all of the above

A

The answer is D.

Solution

As constantly evolving documents, the building codes have undergone many revisions to reflect the introduction of new materials, building technologies, and challenges. The biggest changes to the codes tend to follow disasters, when the shortcomings of the previous requirements become apparent. All the events listed, plus many other natural and human-made disasters, have influenced the thinking behind the requirements of the codes with the intention of making buildings safer and protecting human life.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Occupant load factors are calculated based upon:

A. the number of exits

B. the net floor area

C. the gross floor area

D. the net or gross floor area, depending on the occupancy

A

The answer is D.

Solution

Occupant load factors are calculated based upon either net or gross floor area, depending on the occupancy. The IBC refers to Table 1004.1 to determine which calculation is appropri­ ate for a particular situation. The occupant load represents the number of people that the code assumes will occupy a space or building. This number is then used to determine egress requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

According to ADAAG, what is the maximum distance an object may protrude into the path of travel when it is mounted to a wall between 27 in (685) and 80 in (2030) above finish floor?

A. 2 in (50)

B. 4 in (100)

C. 6 in (150)

D. 8 in (205)

A

The answer is B.

Solution

An object mounted to the wall between 27 in (685) and 80 in (2030) above finish floor may protrude a maximum of 4 in (100) into the path of travel. This requirement is intended to minimize obstructions that a person with impaired vision may possibly walk in to. Obstructions placed lower than 27 in (685) may project more than 4 in (100) as long as other requirements for access are main­ tained, because a person using a cane can detect the obstructions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

An office in an unsprinklered building has an occupant load of 290. Which of the following exit door combinations would minimally satisfy the exit width required?

A. a pair of 30 in (762) entry doors and a 36 in (914) door remotely located

B. two 36 in (914) doors on opposite sides of the building

C. three 32 in (813) doors remotely located

D. three 36 in (914) doors remotely located from each other

A

The answer is B.

Solution

To find the total exit width required, multiply the occupant load, 290 people, by the standard 0.2 in/person (5 mm/per­ son).

In U.S. units:

(290 people)(0.2 in/person) = 58 in

In SI units:

(290 people)(5 mm/person) = 1450 mm

Any exit door must provide a clear width of at least 32 in (813), so choices A and C cannot be correct because their clear widths would be less than 32 in (813). Three 36 in (914) doors would be acceptable, but the question asks for the minimally acceptable solution, which is two 36 in (914) doors; this would provide approximately 66 in (1676) of width (considering the clear width of the door to be from the doorstop to the face of the door when open).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following statements about standards and testing is FALSE?

A. Trade association standards must be followed if they are referred to by a building code adopted in a jurisdiction.

B. The American National Standards Institute

(ANSI) does not write standards.

C. The American Society for Testing and Materials

(ASTM) does not perform tests.

D. Building codes prescribe which laboratories must perform required tests.

A

The answer is D.

Solution

Building codes only prescribe which tests and standards a material or construction element must meet in order to be acceptable. Any qualified Nationally Recognized Testing Laboratory (NRTL) may perform a test, as long as the lab follows the procedures described in the test.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Measured vertically from the nosing of the stair, how high must a handrail be for barrier-free design?

A. 28 in (711) to 32 in (815)

B. 30 in (760) to 34 in (865)

C. 32 in (815) to 36 in (915)

D. 34 in (865) to 38 in (965)

A

The answer is D.

Solution

For barrier-free design, a handrail must be 34 in (865) to 38 in (965) high, measured vertically from the nosing of the stair.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

An architect has been hired to prepare a design for remodeling toilet rooms to make them accessible. The architect finds it is impossible to provide adequate clearance on one side of an entrance door. What is the most econom­ ical course of action?

A. Apply to the building department for a hardship exemption because compliance is not readily achievable.

B. Tell the client that walls should be demolished and the toilet rooms replanned to provide the necessary clearances.

C. Specify a power-assisted door opener that meets accessibility standards for the noncompliant door.

D. Plan for accessible toilet rooms in another loca­ tion in the building where all requirements can be adequately met.

A

The answer is C.

Solution

A power-assisted door would be the least expensive option and require the least construction time. It would be possi­ ble to solve the problem by demolishing the existing restrooms and rebuilding them to comply with accessibility standards, or meet the requirement for accessible facilities in another location in the building, but both of these options are likely to be less economical than the door opener.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following ramp configurations meets barrier-free design requirements?

A. 1:14 slope with maximum rise of 24 in (610)

B. 1:12 slope with maximum rise of 34 in (865)

C. 1:10 slope with maximum rise of 8 in (203)

D. 1:8 slope with maximum rise of 4 in (100)

A

The answer is A.

Solution

The maximum acceptable slope for compliance with acces­ sibility guidelines is 1:12, but the maximum total rise between landings is limited to 30 in (760). A 1:14 slope is less steep than 1:12 and the maximum rise of 24 in (610) given in choice A both comply with the guidelines. A 1:10 slope is allowed if the maximum rise is held to 6 in (150) or less. A 1:8 slope is permitted only if the maximum rise is 3 in (75) or less.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In the diagram shown, what is the minimum distance, x, between two entry doors in the vestibule?

A. 36 in (915)

B. 42 in (1065)

C. 48 in (1220)

D. 60 in (1525)

A

The answer is C.

Solution

The minimum distance between two entry doors forming a vestibule when one opens out and one opens in is 48 in (1220).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The element labeled X in this drawing of an interior windowsill is the:

A. anti-walk block

B. glazing bead

c. setting block

D. removable stop

A

The answer is C.

Solution

In all windowsill details, the glass is placed on two or more setting blocks to support the weight of the glass and cushion it from the frame.

Anti-walk blocks are sometimes used in jamb frames to pre­ vent the glass from touching the jambs. A glazing bead describes a material used to cushion and seal the glass against the stop and the frame. A stop is a removable piece used to hold the glass in place after it has been installed in the frame, which makes it possible to replace the glass when necessary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In a full set of construction drawings, the mechanical engineering drawings are typically placeThe answer is C.d

A. after the civil engineering drawings and before the architectural drawings

B. immediately after the architectural drawings

C. after the structural engineering drawings and before the electrical drawings

D. after the electrical drawings

A

The answer is C.

Solution

The normal sequence of drawings in a full set of drawings is as follows: site drawings, then civil engineering drawings, followed by architectural, structural, mechanical, plumbing (if not included in mechanical), and electrical drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which of the following symbols indicates a floor tele­phone outlet?

A

The answer is A.

Solution

A floor telephone outlet symbol is indicated in Option A.

Option B indicates a floor duplex electrical outlet. Option C is the symbol for a thermostat. Option D indicates a data outlet.

Study Note: Be familiar with standard mechanical and electrical symbols as well as the appearance of architec­ tural, structural, mechanical, and electrical floor plans and other types of drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

During preparation of construction drawings, the architect should coordinate with the structural engineer by

A. requiring the engineer to submit progress draw­

ings when changes are made

B. conducting weekly meetings with the engineer and exchanging progress copies of drawings

C. holding conference calls between staff at both offices at times required by the work progress

D. submitting weekly written memos to the engi­

neer describing the architectural requirements

A

The answer is B.

Solution

Two-way communication of graphic information is critical if the complex coordination required between consultants and the architect is to be successful. Regularly scheduled meetings and exchange of progress documents achieve this goal.

Submission of engineering progress drawings implies only a one-way exchange of information. Conference calls alone cannot fully describe the visual information being developed during production of construction documents. Telephone calls or emails must be supplemented with some type of exchange of visual information through computer network­ ing, faxes, or a physical exchange of printed drawings. The written word is not sufficient to describe drawings, and tends to be a one-way method of communication.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

While the architect is coordinating a set of construc­ tion documents, the interior designer submits the drawing shown.

The drawing is a portion of

A. a finish plan

B. a furniture location plan

C. a telecommunications plan

D. an equipment layout

A

The answer is B.

Solution

This partial drawing shows furniture locations and the indi­ vidual pieces identified with numbers. It would be coordi­ nated with a schedule that would specify each piece of furniture.

17
Q

If this detail is on an east-facing elevation in Boston, what change should the architect make?

A. Modify the drip detail at the top of the window frame.

B. Change the glazing.

C. Add seismic fasteners for the suspended ceiling. D. Increase the shim space.

A

The answer is B.

Solution

The most significant problem with this detail in a cold cli­ mate like that of Boston is the lack of insulated glazing. The detail only indicates a single pane of glass. Although the question does not address this issue, notice also that there is no insulation between the ceiling and the floor above.

18
Q

In the detail shown, which of the following would be of greatest concern?

A. attachment of exterior materials to the structure

B. possible water leakage

C. lack of tolerance for the storefront system

D. cracking from differential movement of materi­als

A

The answer is B.

Solution

Water leakage is the greatest concern in this construction detail. Although flashing is shown and noted below the sill of the second-floor framing, extending it under the framing to the edge of the carpet is inadvisable. In addition, there is no sealant called out for the joint between the sill and the flashing. Water dripping down the window could be drawn into the framing by capillary action.

19
Q

The following symbols may appear on a consultant’s drawings. In order, identify the disconnect switch, the dif­ fuser, the home run to panel board, and the weld.

A. I, III, II, IV

B. II, I, III, IV

C. IV, III, II, I

D. IV, II, I, III

A

The answer is D.

20
Q

Who is responsible for verifying that recessed down­ lights do not interfere with the ductwork shown on the plans?

A. architect

B. electrical engineer

C. lighting designer

D. mechanical engineer

A

The answer is A.

Solution

The architect is responsible for the overall coordination of all the contract documents prepared by his or her consul­ tants.

21
Q

Plans, sections, and elevations are examples of

A. isometric drawings

B. axonometric drawings

C. orthographic drawings

D. oblique drawings

A

The answer is C.

Solution

Plans, sections, and elevations are examples of orthographic projections. These drawings “project” the building onto a drawing surface parallel to the object. This allows the ele­ ments of the building to be shown to scale but eliminates depth from the drawing. Other drawing conventions, such as lineweight, must be used to communicate which parts of the building are closest to the viewer and which portions recede.

Axonometric drawings are prepared by rotating the plan at an angle (usually 45°/45°, 30°/60°, or 60°/30°) and drawing the horizontal and vertical elements of the elevations to scale. They are sometimes called paraline drawings. An iso­ metric drawing is a type of axonometric drawing that pro­ jects the view along x-, y-, and z-axes that are 120° apart.

Oblique drawings can be drawn relative to either the plan or the elevation. A plan oblique is another term for an axono­ metric drawing. An elevation oblique is projected from an elevation; the elevation closest to the viewer is shown to scale and actual shape, but the other sides of the building are foreshortened.

22
Q

A project architect assigns a project to two interns in the office who collaborate to complete the construction drawings and details for the design the project architect has sketched. The project architect answers occasional ques­ tions during the development of the drawings but does not review the drawings until they are 95% complete. Which type of quality management technique best describes the project architect’s approach?

A. total quality management

B. quality control

C. quality assurance

D. coordination

A

The answer is B.

Solution

Quality control requires a project architect or designated quality control reviewer to check the work immediately before it is distributed to the user. It helps to catch any errors that may have been made, but has the disadvantage of detecting them at the very end of the process, when they may be more costly to fix or when time may not allow for comprehensive revision of the drawings affected.

To help offset the disadvantages of quality control, quality assurance was developed. Quality assurance requires peri­ odic checks of the work while it is being developed. For example, periodic “check sets” may be generated for the reviewer when the project is 25%, 50%, and 90% complete. This allows the reviewer to pick up errors earlier in the process and is intended to produce a better-coordinated set of documents.

Total quality management (TQM) goes beyond quality control and quality assurance, with the goal of customer satisfaction.

23
Q

Sound Transmission Class

A

A speech isolation rating given to buliding materials and assemblies.

24
Q

All tests and inspections required for these specifications will be performed by a person of testing laboratory employed by the contractor with the prior approval of the architect. The statement above should be in the following documents.?

A. Instruction to bidders

B. Supplementary conditions

C. General Conditions

D. Special Conditions.

A

D. Special Conditions

25
Q

How many days does the architect have to process a payment to the contractor.

A

7 days