Test Borings
Soil Testing
Placed 100 - 500 feet apart
50 feet apart for large structures
placed with one at each building corner and one in the center
should extend 20’ beyond firm strata
Soil testing
wash boring / auger boring / core boring / test pit
Ultimate Bearing Capacity
Safe bearing capacity
Maximum unit pressure to which the foundation soil may be subjected without detrimental settlement
Ultimate bearing capacity of the soil divided by a safety factor of 2 to 4 times
Bearing capacity of typical soils
well graded gravel and sand 3000 - 12000 psf
compacted sand and fill 2000 to 3000 psf
silt and clay 1000 to 4000 psf
bedrock 10000 psf
General Rules of Thumb for grading
Less than 4% slope is considered flat and suitable for all activities
between 4 % to 10% is moderate - this requires some effort to climb or descend
between 10% and 50% is steep This may only be suitable for limited activity
over 50% is very steep - subject to soil erosion and landslides
summer solstice
winter solstice
summer equinox
winter quinox
summer solstice occurs june 21 with longest daylighting
winter solstice occurs on december 21 and is shortest day
summer equinox occurs march 21 and is equal sun and dark
winter equinox occurs september 21 and is equal sun and dark
Gross and net
To find net from gross find mechanical amount and subtract. Usually 9% for office
Room data sheet
Questionnaire used for gathering room usage info
General obligation bond
Approved by taxpayers used to fund public projects that don’t produce revenue like schools
Uniform Capital recovery
Uniform present worth
Uniform sinking fund
Uniform capital recovery is used to calculate the annual value of a present value. Using a discount rate puts the future amount into terms of today’s dollars.
Uniform present worth expresses a series of uniform annual amounts (such as an annual maintenance fee) in today’s dollars.
Uniform sinking fund is used to calculate the amount that will have to be invested today at a certain interest rate to have a specified amount of money at some point in the future (such as savings for a roof replacement in five years.