Procurement & Tendering Flashcards

1
Q

What is procurement?

A

Overall process of acquiring construction work or services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What should be considered when selecting a procurement route?

A
  • Specifics of the project
  • Client objectives (cost, time, quality, risk, control)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main procurement methods?

A

Traditional & General Contracting
Design & Build
Management Contract
Construction Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is traditional procurement?

A

Design is completed by the client’s design team before competitive tenders are invited and a main contractor is employed to build what the designers have specified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How does Traditional Procurement work?

A

Contractor takes responsibility and financial risk for the construction of the works to the design produced by the client’s design team for the contract sum within the contract period

The client takes responsibility and risk for the design and design team performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When is traditional procurement appropriate?

A

If the employer has had the design prepared

If the design is substantially complete at the time of contractor selection

If the client wishes to retain control over the design and specification

If cost certainty at start on site is important

The shortest overall programme is not the client’s main priority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the advantages of traditional procurement?

A

Retaining control over the design can lead to higher quality

It offers increased levels of cost certainty before commencement

Design changes are reasonably easy to arrange and value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the disadvantages of traditional procurement?

A

The overall project duration may be longer than others due to lack of overlap between design and construction

There is no input into design and planning by the contractor (no buildability advice)

A strategy based on price competition can lead to adverse relations

There is a dual point of responsibility with the design team controlling the design and the contractor retaining responsibility for the construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is design and build?

A

Where the contractor is responsible for the design, planning, organisation, control and construction of the works to the employer’s requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How does D&B work?

A

The employer gives the tenderers the ‘Employer’s Requirements’ and the contractor responds with the ‘Contractor’s Proposals’ which include the price for the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When is D&B appropriate?

A

Where there is a need to make an early start on site as there can be an overlap between design and construction

Where the client wishes to minimise their risk as they transfer design responsibility to the Main Contractor

For technically complex projects requiring the contractor’s expertise

Where the employer does not want to retain control over design development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the advantages of D&B?

A

There is a single point of responsibility for the design and construction

There is earlier commencement on site

Early price certainty is increased

The client can benefit from the contractor’s experience harnessed during the design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the disadvantages of D&B?

A

Clients may find it hard to prepare a sufficiently comprehensive brief

The Client has to commit to a concept design early

Variations from the original brief are difficult to arrange and are often expensive

It is harder to compare tenders and harder to determine whether value for money is being achieved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How much design input will the contractor have in a D&B situation?

A

It depends on the amount of design work the employer has already completed at time of tender

This can range from full design to production of information and coordination only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who carries out the design for the contractor under D&B?

A

It can be outsourced to a separate design company (contractor retains responsibility)

They may have in-house capabilities or the client’s design team may be novated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who carries out the design for the contractor under D&B?

A

It can be outsourced to a separate design company (contractor retains responsibility)

They may have in-house capabilities or the client’s design team may be notated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is management contracting?

A

A management contractor is employed to contribute their expertise to the design and to manage construction with a management fee being paid to them for doing so

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How does management contracting work?

A

The management contractor has direct contractual links with all the works contractors

They have the responsibility for the construction works without actually carrying them out

Not all of the design needs to be completed before the first works contractors start work

The MC selects the works contractors through competitive open book tender

The client reimburses the cost of these packages to the MC plus their management fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

When is management contracting appropriate?

A

When the client does not want cost certainty before commencement

Where an early start on site is a priority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the advantages of management contracting?

A

Overall project duration is shorter due to overlapping design and construction

There is contractor contribution to the design and planning process

Changes can be accommodated in packages not yet let if they have no further impact

The works are let competitively at current market prices on a firm price basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the disadvantages of management contracting?

A

The price for the works is not received until the last package has been let

Changes to the design of later packages may affect packages already let

There is little incentive for the management contractor to reduce costs

In practice, the MC has little legal responsibility for the defaults of the works contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is construction management?

A

The employer places a direct contract with each of the trade contractors and utilises the expertise of a construction manager who acts as a consultant to manage the contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How does a CM contract work?

A

The trade contractors carry out the work

The construction managers supervises the construction process and coordinates the design team

The CM has no contractual links with the trade contractors or members of the design team

Their role includes preparation of the programme, determining requirements for site facilities, breaking down the project into suitable works packages, obtaining and evaluating tenders, co-ordinating and supervising the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

When is CM appropriate?

A

On large, complex projects where the advantages of CM can be utilised - e.g. using upfront buildability knowledge of the CM and their programme advice including specialist input from race contractors

Where an early start on site date is key

Maintenance of flexibility in design and construction strategy

Where price certainty before commencement is not considered a key driver

Where the client is experienced in construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are the advantages of Construction Management?

A

Overall project duration is reduced by overlapping design and construction

The construction manager can contribute to the design and project planning process

Roles, risks and relationships for all parties are clear

Changes in design can be accommodated without paying a premium

Prices may be lower due to direct contacts with trade contractors

The client has means of redress to trade contractors through direct contractual links

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What are the disadvantages of construction management?

A

Price certainty is not achieved until the last trade package is let

Changes to packages may adversely affect packages that are already let

The client must be proactive and hands on

The client has a lot of consultants and contractors to deal with

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is the difference between management contracting and construction management?

A

Under construction management the client is in direct contractual relationships with each of the trade contractors and the construction manager isn’t

Under management contracting the Main Contractor is in direct contractual relationships with the trade contractors and the client is in contract with the MC only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

How do you identify client requirements before recommending a procurement route?

A

Through detailed discussions with the client and design team to identify their priorities in terms of cost, time, quality, risk, experience and control requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

If the client wants to start on site asap, what route would you recommend?

A

Need to consider other requirements in terms of cost and quality
If time = paramount, then CM or MC may be the best solution
This is because the start on site is not dependent upon a long tender period, however this results in lower cost certainty

30
Q

What procurement route would you recommend if the client wanted an early start on site but also cost certainty?

A

Design and Build procurement may be best
Allows the design and construction to be overlapped rather than sequential
Design and construction risk is transferred to the Main Contractor with their tender based on a lump sum price to offer high levels of cost certainty

31
Q

What is GMP and what does it mean?

A

Guaranteed Maximum Price

A lump sum contract under which their is no adjustment in tender price unless design changes are requested by the client

The contractor includes the additional risks involved in the design development process in their tender price

32
Q

What is PFI?

A

Private Finance Initiative

A government programme launched in 1992 to bring private sector project management and expertise into the public sector

The private sector is granted a concession to finance, design & build, and operate major public projects such as schools and hospitals.

33
Q

What are the three types of PFI projects?

A
  1. Financially free-standing - Project costs are recovered by charging users (e.g. toll roads and bridges)
  2. Joint Venture - Public and private sector stakeholders both invest however the private sector has overall control. Contributions and allocation of risk are clearly defined
  3. Services Sold - The capital expenditure for the project is financed by the private sector and then sold back to the public sector. The public sector requires clear demonstration that this provides better value for money than option 1 and 2
34
Q

What sort of projects is PFI used for?

A

Recommended where it offers clear value for money when compared against traditional public sector procurement

Generally considered more appropriate for projects with large values over £20m and where there are significant ongoing maintenance requirements

35
Q

What are the disadvantages of PFI?

A

High bidding costs are associated with PFI as projects can take longer to procure than traditional projects

Value for money is hard to achieve as the cost of private borrowing is more expensive than public sector borrowing

Long term and inflexible contracts are formed which cannot respond to demographic changes. E.g. a reduction in school cohort numbers can lead to empty classrooms being paid for my local authorities

36
Q

What is Build Lease Transfer (BLT)?

A

A facility is designed, financed and constructed by the private sector and then leased back to the government for a predetermined period of time and a pre-agreed rental cost

The facility is owned by the private sector partner during the lease period, at the end the government can renew the lease, buy out the private sector partner or walk away from the deal

Operation and maintenance during the lease period is usually the government’s responsibility

Provides the public sector with a way of financing large-scale infrastructure projects based on ongoing revenue rather than using high levels of capital expenditure

Primary disadvantage is that legal ownership remains with the private sector

37
Q

What is Build Operate Transfer (BTO)?

A

The facility is designed, financed, operated and maintained by a concession company, for the period of the concession

Ownership of the facility is vested in the host government from the time of construction completion

At the end of the period, the concessionaire’s involvement in the project ends and all operating rights and maintenance responsibilities revert to the host government

The concessionaire retains all toll income during the agreed period

38
Q

What is Build Own Operate Transfer (BOOT)?

A

A variation on BOT where ownership stays with the concessionaires until the end of the concession period at which time it is transferred free of charge to the host government

39
Q

What is partnering?

A

A long term approach of structuring business relationships

It involves two or more organisations working together to achieve specific mutual objectives and deliver continuous measurable improvements

40
Q

What is Project Partnering?

A

All members of the professional team become involved in the partnering process at the design stage including contractors

Ownership of risk is spread between the parties and a collaborative approach is encouraged to delivering the solution and overcoming problems

41
Q

What is strategic partnering?

A

A long-term relationship that is established with a view to undertaking a number of projects over a long period

Framework agreements are used to set out the overriding contractual terms with fixed terms and conditions for future purchases

Projects and services are then drawn down on a project-by-project basis

42
Q

What are the key characteristics of partnering?

A

More trust is achieved between the parties

There is a reduced rusk of adversarial relationships as pre-determined contract conditions are agreed by all parties in advance

Increased cost certainty and speed of calling off contracts is gained

43
Q

What are the benefits of partnering?

A

Overall construction and design programme is shortened as their is prior understanding of the Client and their needs from previous projects

Potential for conflict is reduced

Communication is improved

Pooling of resources and ideas should result in innovative solutions

Improved client satisfaction

Protection of profit margin for contractors and suppliers

Team environment is formed

Improved buildability

Better predictability of time and cost

44
Q

What is tendering?

A

A structured procedure for generating quotations from suppliers or contractors looking to obtain an award of business activity either under competition or negotiation with a single contractor

45
Q

What are the main methods of choosing a contractor?

A

Open tendering
Selective tendering (single or two stage)
Negotiated tendering
Serial tendering

46
Q

What is open tendering

A

This is an indiscriminate request for tenders to be submitted to the open market

Could be achieved by advert placement in local papers or technical press inviting contractors to apply for the tender documentation

There are little to no barriers to entry needed to submit a tender

47
Q

What are the advantages of open tendering?

A

It provides opportunities for capable firms which the clients may not have previously considered

It should secure maximum competition from the open market

48
Q

What are the disadvantages of open tendering?

A

There is a danger of increased errors within the tender submission due to a risk of inexperienced contractors that have no prior understanding of the client’s requirements

There is no assurance that the lowest tenderer is capable or financially stable

The total cost and time needed to review the tenders is increased

49
Q

What is selective tendering?

A

Restricting the number of tenderers by pre-selecting a limited number of contractors to tender for the work

50
Q

What are the two types of selective tendering?

A

Single stage and two stage

51
Q

What is single stage tendering?

A

A structured process of receiving competitive tenders from a number of pre-selected capable contractors
Contractors are preselected based on:
- financial stability
- qualifications and certifications
- previous track record
- references
- organisational structure
- capacity and resources
- size of work previously undertaken

52
Q

What are the advantages of single-stage tendering?

A

It ensures only capable and approved firms submit tenders

It tends to reduce the aggregate cost of tendering

It reduces the risk of receiving tenders from unsuitable contractors

53
Q

What is two stage tendering?

A

Where the client seeks to appoint the contractor based on an outline scope of works that is not fully defined

The client then works with the appointed contractor to develop the scope of work and reaches an agreed price

It can be used when it is useful to obtain the contractors buildability expertise on the planning of the project and gain an earlier contractor involvement

54
Q

What is the purpose of the first stage (in two stage tendering)?

A

The client provides an outline project design to each of the tenderers

The tendering contractors will submit prices for helping the client develop and finalise the design using their buildability expertise

Tender submissions will usually consist of:
- A schedule of rates that will be used to calculate the agreed price during stage 2
- A price for assisting the client with design development and buildability expertise during stage 2
- Confirmation of the contractors OH&P percentage

55
Q

What is the purpose of the second stage (in two stage tendering)?

A

Following development of the design to a defined stage, a formal negotiation process is undertaken during stage 2 to agree:
- The final price
- The contract conditions
- Programme

56
Q

What do tenderers return as part of the first stage?

A

Detailed build up of prices for the preliminaries items

Percentage additions for profit and overheads

A construction programme

Proposed sub-letting of the works

57
Q

What are the advantages of two stage tendering?

A

Early involvement of the contractor

Encouragement of collaborative working

Potential for an earlier start on site

Greater client involvement in selecting the supply chain

The contractor can help identify and manage risk

58
Q

What are the disadvantages of two stage tendering?

A

Cost certainty may not be achieved before construction starts

Additional pre-construction fees are incurred for the main contractor

The contractor could take advantage of second stage negotiation and increase costs

There is the potential for parties to not agree the contract sum with risk of retendering

59
Q

When should you use two stage tendering?

A

With a complex building

Where the magnitude of work is unknown at time of contractor selection

If early completion is required

Where the design team would like to make use of contractors expertise on buildability issues

60
Q

What is negotiated tendering?

A

Where the client has an existing preference for appointing a particular firm and only negotiates with one contractor

61
Q

When is negotiated tendering used?

A

When the contractor has carried out work successfully for the client previously where they have an existing relationship

62
Q

How does negotiated tendering work?

A

There is no competition and only one contractor is invited to tender

The contract sum is arrived at by a process of negotiation

Schedule of rates or prices from previous projects may be used as the basis of agreeing a price

63
Q

What is serial tendering?

A

Contractors are asked to bid for a project on the basis that if they complete the initial project satisfactorily, other projects of a similar type will follow and the same bill of rates will be applied

64
Q

What could selecting the wrong contractor lead to?

A

A bad client & contractor relationship

A dissatisfied client

An insolvent contractor

65
Q

How would you put together a set of tender documents?

A

In accordance with JCT practice note 2017 I would include:

An ITT (Invitation to Tender) letter

Instruction to tenderers with:
- The date and time for return, to whom, details for site visits, programme etc
- Conditions of proposed contract
- Pricing documentation
- Specifications
- Drawings
- Employers Requirements
- Pre-construction H&S info
- Form of tender

66
Q

What is the form of tender?

A

A preprinted formal statement in which the tenderer fills in the blank spaces

The tenderer provides their name, address, and the sum of money for which they offer to carry out the works

67
Q

What are the Employer’s Requirements?

A

They set out the client’s requirements including the function, size, accommodation and quality requirements of the project

Their level of detail depends on how much design development has been carried out prior to tender

They normally include the current state of planning permission

It should also detail the level of design, structure, and specification information to be provided by the tenderers

68
Q

What are the Contractor’s Proposals?

A

The contractor’s response to the Employer’s Requirements

They are the key documentation for the client to consider the tender review

They often include plans, elevations, sections and typical details

Layout drawings and specification materials and workmanship are also provided

69
Q

What would you include in a PQQ (Pre-Qualification Questionnaire)?

A

Details of contract particulars

Company turnover & accounts

Previous relevant experience and references

Management and organisational structure

Health and safety records

Quality systems and environmental policy

Provision of bonds, warranties and PCGs

70
Q

How would you determine the duration of the tender period?

A

It depends on the procurement process and size of the project

Traditional procurement with a BOQ - allow usually a month for contractors to obtain pricing information from sub contractors

Large complex schemes will need a longer tender period

If it is the first of a two stage tender, then it may be shorter, around 2-3 weeks.

It is better to ensure there is sufficient time so contractors can price the project correctly than rush and encourage contractors to price a high risk element into the tender