Procurement & Tendering Flashcards

1
Q

RICS Tender Strategies 2014 Guidance Note - what does this cover?

A

This guidance note summarises what tendering is and how tendering processes are used to establish a contract price.

It also reviews different types of tendering and negotiation strategies and their advantages and disadvantages. It seeks to enhance the knowledge and understanding of the tendering and negotiation processes involved in procurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Post covid 19 why have two stage approaches been more preferred by main contractors

A

A single stage tender shifts a number of risks to the main contractor in terms of cost of materials and the requirement for these to be fixed.

A two stage approach will give the contractor greater opportunities to review costs in terms of materials before being fixed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When would you recommend a negotiated tender?

A

A negotiated route would be recommended if there is a clear programme restriction and no time to tender.

One contractor has far more superior knowledge specific to the building and project.

There is an existing client relationship and under standing given previous jobs completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

At what stage of the RIBA plan of work would you issue your tender documents for:
- Single stage
- Two stage
- D&B?

A

Single stage - RIBA Stage 4
Two Stage - RIBA Stage 3 for first stage
D&B - Stage 2-4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a tender opening form and why is this used?

A

Each tender should be opened and the general raw information noted on the tender opening form. This typically includes:
* the tender price (perhaps split into preliminaries,
overheads and profit and prime cost)
* the proposed programme
* any key comments/exclusions
* any alternative tender offers; and
* a confirmation that all documents have been
submitted or not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is covered in the JCT 2017 Tendering Practice Note

A

From looking at different types of selective tendering procedure, the Note focuses on the following main sections:

  1. Preliminary Enquiry - including a project information schedule and pre-qualification questionnaire.
  2. Invitation to Tender and Tender - covering the documents involved, the criteria and compliance.
  3. Assessment and Award - covering assessment, examination of priced documents and related matters, and notification to tenderers.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you level bids?

A

This is a process of clarification with the main contractors and reviews with the QS. Further clarity will be provided by certain contractors and exclusions clearly defined to ensure bids are compared on a like for like basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you ensure equal information flows to all parties during the tender process?

A

RFI schedules updated and circulated to all parties with all queries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the difference between procurement and tendering?

A

Procurement is the act of purchasing good and services.

Tendering is a procurement strategy in order to gain market costs and competitive prices for the goods and services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did you agree a contractor long list?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a PQQ? What questions were included in this process?

A

Pre Qualification Questionnaire.

Includes:
- Company details (including legal status).
- Details of insurance
- Financial information (such as recent accounts).
- Relevant experience.
- Information about technical and professional ability.
- Information about capability and capacity.
- Health and safety policy.
- Quality assurance policy.
- Environmental management policy.
- Equal opportunities policy.
- Relevant references.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What contract was used in your White City tender issue example?

A

D&B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are employer’s requirements? And how do these differ from a traditional contract?

A

ERs are part of a D&B contract where as traditional contracts include a specification and contract design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How were post tender queries managed?

A

RFI schedules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the form of tender?

A

This is the form that the contractor signs and returns with their proposed tender, in terms of both price and programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are preliminaries ?

A

Items that are priced for construction but included in the fished product. Site set up, scaffolding, temp lights etc.

17
Q

What are the contract particulars?

A

Contract particulars are a section of the contract that include the ERs, retention rate, defect period, insurance options etc

18
Q

What contract amendments were included?

A
  • defect period from 6 to 12 months
  • retention rate from 3% to 5%
  • Payment terms from 14 to 21 days
19
Q

Are there any codes of practice you consider when issuing tenders or legislation?

A

RICS Tendering Strategies Guidance Note 2014

20
Q

what is the difference between procurement and tendering?

A

Procurement is the overall act of obtaining goods and services from external sources (i.e. a building contractor) and includes deciding the strategy on how those goods are to be acquired by reviewing the client’s requirements (i.e. time, quality and cost) and their attitude to risk.

Tendering is an important phase in the
procurement strategy but procurement involves
much more than simply obtaining a price.
Tendering is:
* the bidding process, to obtain a price; and
* how a contractor is actually appointed.

21
Q

What do you do if a contractor pulls out of the tender process?

A

Review with the client and understand if they wish to add an additional party to the process. if so all tendering parties should be notified to any extension to the timelines pre agreed.

22
Q

How do you ensure the competence of Principal Contractors?

A
  1. Review relevant experience and case studies
  2. PAS (Publicly Available Standard) 8672 - Framework for the competence of principal contactors
23
Q

What does PAS 8672 include?

A

PAS 8672 specifies competence requirements for the role of Principal Contractor with regard to:

Roles and responsibilities
Skills, knowledge and experience
Behaviours and ethics
Additional competences for higher-risk buildings (HRBs)
Limits of competence

It can be used as a benchmark to help assess the competence of teams,

24
Q

How did you assess the competence of the Principle Designer

A

If there are RIBA registered and trained.

PAS 8671 - Principle Designer Competence

25
Q

What happens if there is an error in tenders received?

A

JCT Tendering Practice Note 2017

This process should be set in the instruction to tender.

Alternative option 1 - do not allow change
Alternative option 2 - errors can be amended

26
Q

Case study - why did you use an expression of interest not a PQQ

A

An expression of interest is an usually issued to the open market to allow contractors to return confirmation they are keen to tender for an instruction.

A PQQ - is a set of pre defined questions such as financial standing, case studies, ability to tender, agreement to procurement route, insurance details, references.