Contract Practice Flashcards
You mention you have undertaken structured CPD - what was this and what were the key learnings?
When are the new JCT contract suite of contracts being released and why are they being updated? What are the changes?
2024
They are being released to better align with legislation changes such as the Building Safety Act 2022.
The duration to review an EOT claim is going from 12wks to 8wks.
When would you levy LDs other than a delay to works?
When a performance specification has not been met.
What is the impact if LDs are set at too high a rate?
Not enforceable and can be challenged in court
Also disincentive to tender / price in greater risks.
Who issues a payless notice?
Employer issues the final certificate.
What takes precedent the ERs or CPs?
CPs
How would you check a hard hat is ok to use?
CE stamp and visual inspection for any damage
Who calculates LDs?
LDs are pre-determined damages set at the time that a contract is entered into, based on a calculation of the actual loss the client is likely to incur if the contractor fails to meet the completion date. They are generally set as a fixed daily or weekly sum.
The can include:
- Loss of rent / rental costs
- Additional professional team fees
- Storage costs
LDs are calculated by the client supported by the professional team.
What are the different sections of a contract? Preamble / prelims etc?
- Agreement
- Recitals / preamble (a statement of facts or reasons that explain why a contract exists. Sometimes called a ‘whereas’ or ‘preamble’ clause, it provides context information.)
- Articles:
Article 1: Contractor’s obligations
Article 2: Contract Sum
Article 3: Employer’s Agent
Article 4: Employer’s Requirements and Contractor’s Proposals
Article 5: Principal Designer
Article 6: Principal Contractor
Article 7: Adjudication
Article 8: Arbitration
Article 9: Legal proceedings - Contract Particulars
ERs
CPs
CSA
Base date (The Base Date is usually stated to be the date of the tender or priced offer, which means that the risk of inflation between the tender and contact execution lies with the supplying party)
PC Date
LDs
Rectification period
Retention rate
PI insurance for contractor
Insurance details
Bond and PCG requirements
Adjudication body - Attestation - The attestation clause is the place in the agreement where the parties sign to indicate their consent to the provisions of the agreement. The execution clauses and signature blocks are found at the end of the agreement. Under hand or as a deed.
- Conditions and definitions
What is meant by contractors design portion?
It is an agreement for the contractor to design specific parts of the works. The contractor may in turn sub-contract this design work to specialist sub-contractors. Set out in the tedner documetns.
Are meeting minutes a contract document?
Meeting minutes are not a contract document.
What is an NEC contract and name some key differences.
New Engineering Contract. Usually used for engineering projects.
NEC contracts include a defined role as a PM, note the programme as a contract document and do not allow for provisional sums. NEC includes an incentive bonus for early completion of works.
What is the difference between under hand and as a deed contract signatures?
Under hand - 6yr limitation period.
As a deed 12yr limitation period.
What section of the contract would the contract sum be found?
In the Article section of the contract.
What do you mean ‘contract mechanism’?
These are clauses within the contract noting specific areas for consideration to protect the client - rectification period, retention sum etc.
What is a bond?
Bonds are a means of protection against the non-performance of the contractor. They are an undertaking by a bondsman or surety to make a payment to the client in the event of non-performance of the contractor. The cost of the bond is usually borne by the contractor, although this is likely to be reflected in the contractor’s tender price.
Bonds can be ‘on demand’ or ‘conditional’, with conditional bonds requiring that the client provides evidence that the contractor has not performed their obligations under the contract and that they have suffered a loss as a consequence.
A performance bond is commonly used as a means of insuring a client against the risk of a contractor failing to fulfil contractual obligations to the client, although they can also be required from other parties.
Advance payment bond - If the client agrees to make an advance payment to the contractor, (for example where the contractor incurs significant start-up and procurement costs before construction begins), a bond may be required to secure the payment against default by the contractor. This will normally be an on-demand bond.
Performance bonds are typically set at 10% of the contract value. This compensation can enable the client to overcome difficulties that have been caused by non-performance of the contractor, such as, finding a new contractor to complete the works.
Who advises and issues a bond?
A bondsman or bank can issue.
What is a parent company guarantee?
A parent company guarantee (PCG) is a guarantee given by one contracting party’s ultimate or intermediate holding company in favour of the other contracting party to secure the performance of that party’s obligations under the contract.
How do you ensure the financial suitability of the parent company?
Due diligence was undertaken by the client’s financial team. Including a request for company accounts.
What is a collateral warranty?
A collateral warranty creates a contractual link between the third party and the contractor or professional consultant. A collateral warranty is a contract that sits alongside the underlying contract, such as a building contract or consultant appointment, and grants rights to a third party which can be sued upon.
Normally between a sub-contractor to the client.
What is the difference between a warranty and a guarantee?
A guarantee offered to a consumer is a ‘promise’ that problems with a product or service that occur within a specified period of time will be rectified. Typically guarantees are not paid for.
A warranty on the other hand (or an ‘extended guarantee’) generally is paid for and is similar to an insurance policy.
What is an alternative to a collateral warranty? Third party rights?
Third-party rights can be used where a collateral warranty will not be issued. They allow someone who is not a signatory to a contract to enforce the benefit of a term contained in the contract.
The right created is to enforce a term of a contract, not the whole contract itself. For example, if a building contract contains a term that the contractor is required to use materials of good quality, then that term might be the subject of a third party enforcement right.
Despite collateral warranties tending to be the preferred option, third party rights are increasing in popularity since they can be incorporated into building contracts, subcontracts, etc., with a simple notice; avoiding the need to produce detailed additional agreements. The administrative exercise of organising collateral warranties can be considerable, sometimes costing more in money and time than their actual value.
However, collateral warranties can be perceived as being more effective since they mirror the responsibilities of the underlying contract. The construction industry is also more used to using them.
When would you expect to see a warranty?
Typically product warranties will be provided by the manufacturer. the warranty will detail the rights of both parties and obligations in the event of a dispute.
What are sub-contractor warranties?
Also noted as a collateral warranty - makes a contractual link between in the client and subcontractor not noted in the main contract.