Contract Practice Flashcards

1
Q

You mention you have undertaken structured CPD - what was this and what were the key learnings?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When are the new JCT contract suite of contracts being released and why are they being updated? What are the changes?

A

2024

They are being released to better align with legislation changes such as the Building Safety Act 2022.

The duration to review an EOT claim is going from 12wks to 8wks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When would you levy LDs other than a delay to works?

A

When a performance specification has not been met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the impact if LDs are set at too high a rate?

A

Not enforceable and can be challenged in court

Also disincentive to tender / price in greater risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who issues a payless notice?

A

Employer issues the final certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What takes precedent the ERs or CPs?

A

CPs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How would you check a hard hat is ok to use?

A

CE stamp and visual inspection for any damage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who calculates LDs?

A

LDs are pre-determined damages set at the time that a contract is entered into, based on a calculation of the actual loss the client is likely to incur if the contractor fails to meet the completion date. They are generally set as a fixed daily or weekly sum.

The can include:
- Loss of rent / rental costs
- Additional professional team fees
- Storage costs

LDs are calculated by the client supported by the professional team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the different sections of a contract? Preamble / prelims etc?

A
  1. Agreement
  2. Recitals / preamble (a statement of facts or reasons that explain why a contract exists. Sometimes called a ‘whereas’ or ‘preamble’ clause, it provides context information.)
  3. Articles:
    Article 1: Contractor’s obligations
    Article 2: Contract Sum
    Article 3: Employer’s Agent
    Article 4: Employer’s Requirements and Contractor’s Proposals
    Article 5: Principal Designer
    Article 6: Principal Contractor
    Article 7: Adjudication
    Article 8: Arbitration
    Article 9: Legal proceedings
  4. Contract Particulars
    ERs
    CPs
    CSA
    Base date (The Base Date is usually stated to be the date of the tender or priced offer, which means that the risk of inflation between the tender and contact execution lies with the supplying party)
    PC Date
    LDs
    Rectification period
    Retention rate
    PI insurance for contractor
    Insurance details
    Bond and PCG requirements
    Adjudication body
  5. Attestation - The attestation clause is the place in the agreement where the parties sign to indicate their consent to the provisions of the agreement. The execution clauses and signature blocks are found at the end of the agreement. Under hand or as a deed.
  6. Conditions and definitions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is meant by contractors design portion?

A

It is an agreement for the contractor to design specific parts of the works. The contractor may in turn sub-contract this design work to specialist sub-contractors. Set out in the tedner documetns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Are meeting minutes a contract document?

A

Meeting minutes are not a contract document.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is an NEC contract and name some key differences.

A

New Engineering Contract. Usually used for engineering projects.

NEC contracts include a defined role as a PM, note the programme as a contract document and do not allow for provisional sums. NEC includes an incentive bonus for early completion of works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the difference between under hand and as a deed contract signatures?

A

Under hand - 6yr limitation period.

As a deed 12yr limitation period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What section of the contract would the contract sum be found?

A

In the Article section of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What do you mean ‘contract mechanism’?

A

These are clauses within the contract noting specific areas for consideration to protect the client - rectification period, retention sum etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a bond?

A

Bonds are a means of protection against the non-performance of the contractor. They are an undertaking by a bondsman or surety to make a payment to the client in the event of non-performance of the contractor. The cost of the bond is usually borne by the contractor, although this is likely to be reflected in the contractor’s tender price.

Bonds can be ‘on demand’ or ‘conditional’, with conditional bonds requiring that the client provides evidence that the contractor has not performed their obligations under the contract and that they have suffered a loss as a consequence.

A performance bond is commonly used as a means of insuring a client against the risk of a contractor failing to fulfil contractual obligations to the client, although they can also be required from other parties.

Advance payment bond - If the client agrees to make an advance payment to the contractor, (for example where the contractor incurs significant start-up and procurement costs before construction begins), a bond may be required to secure the payment against default by the contractor. This will normally be an on-demand bond.

Performance bonds are typically set at 10% of the contract value. This compensation can enable the client to overcome difficulties that have been caused by non-performance of the contractor, such as, finding a new contractor to complete the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Who advises and issues a bond?

A

A bondsman or bank can issue.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a parent company guarantee?

A

A parent company guarantee (PCG) is a guarantee given by one contracting party’s ultimate or intermediate holding company in favour of the other contracting party to secure the performance of that party’s obligations under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How do you ensure the financial suitability of the parent company?

A

Due diligence was undertaken by the client’s financial team. Including a request for company accounts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is a collateral warranty?

A

A collateral warranty creates a contractual link between the third party and the contractor or professional consultant. A collateral warranty is a contract that sits alongside the underlying contract, such as a building contract or consultant appointment, and grants rights to a third party which can be sued upon.

Normally between a sub-contractor to the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the difference between a warranty and a guarantee?

A

A guarantee offered to a consumer is a ‘promise’ that problems with a product or service that occur within a specified period of time will be rectified. Typically guarantees are not paid for.

A warranty on the other hand (or an ‘extended guarantee’) generally is paid for and is similar to an insurance policy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is an alternative to a collateral warranty? Third party rights?

A

Third-party rights can be used where a collateral warranty will not be issued. They allow someone who is not a signatory to a contract to enforce the benefit of a term contained in the contract.

The right created is to enforce a term of a contract, not the whole contract itself. For example, if a building contract contains a term that the contractor is required to use materials of good quality, then that term might be the subject of a third party enforcement right.

Despite collateral warranties tending to be the preferred option, third party rights are increasing in popularity since they can be incorporated into building contracts, subcontracts, etc., with a simple notice; avoiding the need to produce detailed additional agreements. The administrative exercise of organising collateral warranties can be considerable, sometimes costing more in money and time than their actual value.

However, collateral warranties can be perceived as being more effective since they mirror the responsibilities of the underlying contract. The construction industry is also more used to using them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

When would you expect to see a warranty?

A

Typically product warranties will be provided by the manufacturer. the warranty will detail the rights of both parties and obligations in the event of a dispute.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are sub-contractor warranties?

A

Also noted as a collateral warranty - makes a contractual link between in the client and subcontractor not noted in the main contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Why is the JCT the preferred choice of contract?

A

It is a standard form of contract that is commonly used therefore understood by all parties involved.

26
Q

What is included in the ‘Deciding on the Appropriate JCT Contract 2016 Guidance Note’?

A

This guidance includes:
- different procurement methods
- a guide to selecting the appropriate contract inn a flowchart form
- PCSA

27
Q

Why do you have contract amendments? And do you draft these yourself?

A

Contract amendments allow the standard form of contract to be tailored to best meet the client requirements. Drafted by the client legal representative.

28
Q

What are some typical contract amendments?

A
  1. Defect liability period from 6months to 12 months.
  2. Payment terms from 14 to 28 days.
  3. Rate of retention. Typically 3% on D&B contract and updating to 5%.
29
Q

L2 - what contract was progressed in your industrial unit refurbishment?

A

JCT intermediate contract with contractors design portion

30
Q

What is the difference between a minor works, intermediate and traditional contract?

A

A minor works is less detailed than an intermediate uncontract. It does not allow for sectional completion or define relevant events or matters. Not suitable for any design portions of work and the contractor will price a specification.

31
Q

What did you include in the comparison table to present to the client?

A

Included the design allocation, timelines and risk associated with each contract.

32
Q

When would a minor works contract be suitable?

A

For straight forward works of limited contract works where no sections are required and the specification is provided to the contractor.

33
Q

What is the difference between sectional completion, partial possession and early access?

A

Sectional completion is defined in the contract. It will have a separate PC date and LD rate in the contract.

Partial possession is agreed during the contract works and must be agreed between the client legal team and contractor. If this is agreed retention monies for the space must be proportionally released and LDs not levied. Must consider site logistics, insurances and H&S measures

Early use allows the client to use part of the space prior to PC. The risk remains with the contractor unlike sectional completion or partial possession, the contractor will still be liable for LDs if delivered late. Usually used for storage or surveys.

34
Q

What is beneficial occupation?

A

The client is physically able to take occupation of the works and use them for their intended purpose.

35
Q

L3 -0 What is the definition of insolvency?

A

Insolvency is when an individual or company cannot commit to their financial obligations for paying debt to lenders on time. This usually occurs when a person’s debt exceeds the value of their assets. Insolvency is not the same as bankruptcy, but it is criteria for bankruptcy.

Bankruptcy is a legal process. It is undertaken when an individual can no longer afford to pay off their debts.

Difference:
- Bankruptcy is a legal process or court order, while insolvency is a state of financial distress.
- Bankruptcy is a type of insolvency, but there are others.
- Bankruptcy isn’t the only way out of insolvency.
- Bankruptcy applies only to individuals and sole traders with unlimited liability. Insolvency applies to businesses as well as individuals.

Insolvency is a financial state where a person cannot meet debt payments on time. Bankruptcy is a legal process that happens when the individual declares he or she can no longer pay back his or her debts to creditors.

36
Q

Did you undertake the due diligence yourself for the list of contractors?

A
37
Q

What due diligence did you do prior to the instruction?

A
38
Q

Did YOU advise on the PCG? Does your insurance cover this sort of financial advise?

A

I can advise on a PCG from a PM perspective but it would be up to my Client’s discretion and independent advise on which route to proceed.

39
Q

Is a PCG or bond included in the contract?

A

Noted in the contact particulars and appended to the contract

40
Q

What would you expect the value of the bond to be?

A

Typically 10% of the contract sum however this would be up to the client to clarify the amount to be requested given the risk of the project.

41
Q

Who typically requests subcontractor warranties

A

The client

42
Q

What would you typically find in a dunn and bradstreet report?

A
  • Summary of the company (founding date, employees)
  • D&B Rating EG 3A4 (3A financial strength (5A best HH worst) and credit appraisal (1 best 4 worst))
  • Risk of default score
    Officer and director information
43
Q

CPD – What is the role and responsibility of a CA?

A

To impartially administer the contract.

44
Q

CPD – What is PC? What is triggered at PC? What happens when liquidated damages can no longer be claimed?

A

PC is the point at which the client can take beneficial occupation of the space and use it for its intended purpose.

PC will implicate:
1. release half of the retention monies
2. start the defect rectification period
3. LDs can no longer be levied
4. Insurances are passed from the contactors to the client

45
Q

CPD – what do you understand by the different insurance options a,b c?

A

Option A requires the Contractor to take out and maintain all risks insurance of the works;

Option B requires the Employer to take out and maintain all risks insurance of the works; and

Option C requires the Employer to take out and maintain (a) insurance in respect of the existing structures and their contents and (b) all risks insurance of the works.

46
Q

CPD - What are some of insurances you see on projects?

A
  • Professional Indemnity
  • Public liability
  • Employers liability
47
Q

CPD – What is NBS Contract administrator?

A

National Building Specification

NBS Contract Administrator provides an efficient platform to administer your JCT/SBCC contracts. Containing electronic copies of the official RIBA Contract Administration Forms for use with the JCT Standard, Intermediate, Minor Works and Design and Build contracts. The software filters the right forms, for the right contract at the right time.

48
Q

CPD – What is a vesting certificate?

A

Vesting certificate is the transfer of ownership for the value of offsite materials from the contractor to the client.

Includes the transfer of ownership details, decryptions of the items, value, date.

Goods should be clearly labelled and kept separate in the warehouse.

49
Q

What are unliquidated damages?

A

Unliquidated damages are damages, the exact amount of which has not been pre-agreed, and are typically determined by the courts.

50
Q

What is an LOI and how is this different to a PCSA. Why would you recommend each?

A

Letter of intent - drafted by the client legal team

Pre construction services agreement PCSA - a standard JCT template that includes definitive tasks to be completed and a value

51
Q

What is the acceleration quotation in a JCT contract?

A

The employer can request the contractor provides a cost and investigate the possibility to improve the PC date. This must be provided within 21 days and the client as 7 days to review.

52
Q

What is force majeure?

A

An unforeseen event that is not caused by a party within the contract that inhibits the contractual obligations being undertaken

53
Q

Name a force majeure event not Covid-19

A

Earthquake / natural disaster not in a known risk area.

54
Q

Would an EOT be granted for a force majeure event?

A

This under the contract is classed as a relevant event and therefore would allow the contractor time but no monies.

55
Q

What is included in an LOI?

A

This is a detailed intent to enter into the contract. This will include:
1. reference to the contract particulars, ERs, CSA , CPs
2. Scope to be undertaken during the LOI period prior to the execution of contract.
3. A value “maximum amount” to be expended during completing these works.
4. Insurance requirements (as noted in the contract)
5. A termination date for the LOI or upon execution of the contract.
6. Client design ownership
7. Signatures from the client and contractor

56
Q

What is the joint fire code?

A

Introduced in 1992, Refers to the prevention of fires on construction sites and applies to contracts where the value is more than £2.5 million. Or apply to lower contract value where it is deemed high risk.

The code describes a series of simple precautions and safe working practices (to) ensure that adequate detection and prevention measures are incorporated during the design and planning stages and that work on a site is undertaken to the highest standard of fire safety

If not complied it is a breach of the contract

  1. Hot works permits
  2. Weekly testing the fire alarm
  3. Weekly inspections of escape routes
  4. Appointment of fire marshals
  5. Local fire and rescue service invited for inspections
57
Q

What is the retention rate in a minor works, intermediate contract, D&B and trad?

A

5% = minor and intermediate
3% = trad & D&B

58
Q

What is contractors all risk insurance?

A

Contractors’ all risk insurance, also referred to as Contract Works Insurance or Construction Insurance, is a non-standard insurance policy that provides coverage for accidental physical loss or damage that occurs to a property insured during the construction period. It covers the contract works undertaken by the contractor and sub contractors.

59
Q

What is the housing grant, construction and regeneration act? And how does this relate to contractor payments?

A
  • Does not allow pay when paid clauses in a contract.
  • If a contractor is not paid they can suspend works for the period and claim and EOT for the period for the time/ money of suspension.
  • 45 day period plus interim payments valid.
60
Q

What are the JCT provisions for contractor payments?

A

Alternative A: stage payments – the contractor is entitled to be paid on a stage payment basis. A number of work stages will be identified in the contract particulars and priced on a cumulative basis. As stages are completed, the contractor is to submit an application for payment for the cumulative value of the works (taken from the contract
particulars) at that stage.

Alternative B: periodic payments – the contractor is to submit an application for payment on the dates set out in the contract particulars. The payment is based upon the value of work and design work executed by the contractor by that date.

61
Q

What is a purchase order?

A

A purchase order (PO) is a legally binding document created by a buyer and presented to a seller. A purchase order is essentially a list of what you want to buy. It lays out the order details, including quantity and types of products the buyer needs, as well as payment terms and delivery details.

The difference between a purchase requisition and a purchase order is that the latter acts as a contract between the buyer and the seller. By submitting an order, the buyer is committing to purchasing goods or services for the agreed upon amount. Because the order is filled before the buyer receives their bill, a purchase order gives the seller insurance against non-payment.