What is due date of contractor invoice if LG rep must first approve?
s
25 business days from date invoice is stamped received.
s
What is due date of contractor invoice & When does Interest hit, %?
—
CONSTRUCTION:
LG need approve?
LG need not first approve?
—
NONCONSTRUCTION:
General.
s
CONSTRUCTION:
APP: 25 business days from date invoice stamped received.
NO APP: 20 bus days.
2% on due date.
———–
NON-CONSTRUCTION:
45 calendar days
1% 30 days thereafter.
s
State the due dates & interest under Prompt Payment Act for:
Construction
a) Invoice does not need approval.
b) Invoice requires approval.
Non-Construction.
s
CONSTRUCTION:
a) No approval needed = 20 BUSINESS days.
b) Approval needed = 25 BUSINESS days.
c) 2% interest on due date.
———–
NON-CONSTRUCTION:
a) 45 CALENDAR days.
b) 30 days thereafter get 1% interest.
s
What is significance of LG’s receipt of overdue notice?
s
how remember? O-W-E-D & L-A-T-E = 4 ltr words
———–
After 4 business days of delivering an overdue notice, if LG does not reject the invoice it is deemed undisputed.
s
What is LG required to do if it disputes the invoice or the overdue notice?
s
w/i 20 days of receipt, provide written rejection, specifying deficiency & stating action to rectify.
s
If LG sent contractor a written rejection of an invoice & contractor revises the invoice, what now must LG do?
s
r-e-v-i-s-e-d p-a-y
———–
Pay or notice rejection:
a) w/i 10 business days of receipt or
b) 1st business day after LG’s next meeting.
s
How long does a contractor have to pay its subs after receiving LG payment?
s
10 days.
s
How long does subcontractor have to pay the sub-subcontractors after receiving contractor’s payment?
s
7 days.
s
What are penalties for late payment?
s
2% per month (more if agreed to in K).
NEW 2021 used to be 1%,
s
What procedure must LG initiate if there is a payment dispute?
s
• w/i 45 days proper invoice was received,
commence its established dispute resolution procedure.
• w/i 60 days proper invoice was received, have final decision.
s
Re: construction
Threshold amt requiring LG to announce for pro services?
———–
BONUS - state the 5 thresholds.
1) $20k
2) $35k
3) $65k
4) $195k
5) $325k
————
*confirmed 287.017
s
Re: planning or study activity
Threshold amt requiring LG to announce for pro services?
s
Exceeds $35k.
s
What work is covered by 255.20?
s
Public Construct
Inc. bridges, roads, streets, hiways, RRs
• May req qualf
• DQ if 10% behind
• Prequl by DOT
s
What is dollar threshold for Construction?
s
Over $300k*
* Includes labor, equip + materials
s
What is dollar threshold for Electrical?
s
Over $75k