255.20 (public works/roads) Road Builders Flashcards
At what threshold amount may LG require its road contractor to be qualified?
If over $250k.
———–
Same as County roads in 336
When presumed qualified?
DOT prequalified ktor presumed to be qualified.
When is road contractor not eligible to be qualified?
If behind by 10% ON A GOVT JOB at the time of advertising LG’s project.
———–
Similar to County roads in 336
What procedure must be in place for a contractor who is not prequalified by FDOT to ?
Step 1: LG creates criteria & procedure.
Step 2: LG holds a public hearing for comment.
Step 3: LG includes prequalification criteria in advertisement.
———–
Same as County roads in 336
What if potential contractor disputes the criteria or procedure adopted by LG?
De novo to circuit.
———–
Same as County roads in 336
What is a mandatory part of any procedure LG adopts, regarding prequalification?
Appeal process within LG w/ de novo review by circuit based on record below w/in 30 days.
How do 336 & 255.20 differ?
336:
Bid only, no award.
County qualifies Ktor.
10% behind on job for County.
No timeline for Circuit review.
———–
255.20:
Award
FDOT (if already preq) & County prequalify.
10% on any govt job.
30 day review by Circuit.
State how 336 & 255.20 are the same, re:
— COMP BID (1 way)
———— HIRE (2 ways)
———————PROCEDURE (3 ways)
HIRE:
1) Optional qualification. Focus on method of hiring.
2) 10% behind = ineligible.
———–
PROCEDURE:
1) Procedure + criteria require public hearing.
2) Mandatory appeal.
3) 336 + 255.20 + 287.55 = All short list