Procurement Management Flashcards

1
Q

Alternative Dispute Resolution

A

Alternative Dispute Resolution

When there is an issue or claim that must be settled before the contract can be closed, the parties involved in the issue or claim will try to reach a settlement through mediation or arbitration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Bid Documents

A

Bid Documents

All documents used to solicit information, quotations, or proposals from perspective sellers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bidder Conference

A

Bidder Conference

The meetings with prospective sellers prior to the preparation of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement. Also known as contractor conferences, vendor conferences, or pre-bid conferences.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Claims

A

Claims

These are disagreements between the buyer and the seller, usually centering on a change, who did the change, and even whether a change has occurred.

Claims are also called disputes and appeals, and are monitored and controlled through the project in accordance with the contract terms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contract

A

Contract

A contract is a mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contract Change Control System

A

Contract Change Control System

The system used to collect, track, adjudicate, and communicate changes to a contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contract statement of work (SOW also CSOW)

A

Contract statement of work (SOW also CSOW)

This document requires that the seller fully describe the work to be completed and/or the product to be supplied. The SOW becomes part of the contract between the buyer and the seller.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost plus award fee contract

A

Cost plus award fee contract

A contract that pays the vendor all costs for the project, but also includes a buyer-determined award fee for the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost plus fixed fee contract

A

Cost plus fixed fee contract

A contract that requires the buyer to pay for the cost of the goods and services procured plus a fixed fee for the contracted work.

The buyer assumes the risk of a cost overrun.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost plus incentive fee

A

Cost plus incentive fee

A contract type that requires the buyer to pay a cost for the procured work, plus an incentive fee, or a bonus, for the work if terms and conditions are met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cost plus percentage of costs

A

Cost plus percentage of costs

A contract that requires the buyer to pay for the costs of the goods and services procured plus a percentage of the costs.

The buyer assumes all of the risks for cost overruns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Direct costs

A

Direct costs

These are costs incurred by the project in order for the project to exist.

Examples include the equipment needed to complete the project work, salaries of the project team, and other expenses tied directly to the project’s existence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Fixed-price contracts

A

Fixed-price contracts

Also known as firm fixed-price and lump-sum contracts, these are agreements that define a total price for the product the seller is to provide.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fixed-price incentive fee

A

Fixed-price incentive fee

A fixed-price contract with opportunities for bonuses for meeting goals on costs, schedule, and other objectives.

These contracts usually have a price ceiling for costs and associated bonuses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Fixed-price with economic price adjustments

A

Fixed-price with economic price adjustments

A fixed-price contract with a special allowance for price increases based on economic reasons such as inflation or the cost of raw materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Force majeure

A

Force majeure

An “act of God” that may have a negative impact on the project. Examples include fire, hurricanes, tornadoes, and earthquakes.

17
Q

Independent estimates

A

Independent estimates

These estimates are often referred to as “should cost” estimates.

They are created by the performing organization or outside experts to predict what the cost of the procured product should be.

18
Q

Indirect costs

A

Indirect costs

These are costs attributed to the cost of doing business.

Examples include utilities, office space, and other overhead costs.

19
Q

Invitation for Bid (IFB)

A

Invitation for Bid (IFB)

From buyer to seller. Requests the seller to provide a price for the procured product or service.

20
Q

Letter contract

A

Letter contract

A letter contract allows the vendor to begin working on the project immediately. It is often used as a stopgap solution.

21
Q

Letter of intent

A

Letter of intent

A letter of intent is not a contract, but a letter stating that the buyer is intending to create a contractual relationship with the seller.

22
Q

Make-or-buy decision

A

Make-or-buy decision

A process in which the project management team determines the cost-effectiveness, benefits, and feasibility of making a product or buying it from a vendor.

23
Q

Privity

A

Privity

The contractual relationship between the buyer and the seller is often considered confidential and secret.

24
Q

Procurement management plan

A

Procurement management plan

A project management subsidiary plan that documents the decisions made in the procurement planning processes.

25
Q

Procurement planning

A

Procurement planning

A process to identify which parts of the project warrant procurement from a vendor by the buyer.

26
Q

Proposal

A

Proposal

A document the seller provides to the buyer. The proposal includes more than just a fee for the proposed work. It also includes information on the vendor’s skills, the vendor’s reputation, and ideas on how the vendor can complete the contracted work for the buyer.

27
Q

Purchase order (PO)

A

Purchase order (PO)

A purchase order is a form of unilateral contract that the buyer provides to the vendor showing that the purchase has been approved by the buyer’s organization.

28
Q

Quotation

A

Quotation

From seller to buyer. Price is the determining factor in the decision-making process.

29
Q

Request for Proposal (RFP)

A

Request for Proposal (RFP)

From buyer to seller. Requests the seller to provide a proposal to complete the procured work or to provide the procured product.

30
Q

Request for Quote (RFQ)

A

Request for Quote (RFQ)

From buyer to seller. Requests the seller to provide a price for the procured product or service.

31
Q

Risk-related contractual agreements

A

Risk-related contractual agreements

When the project management team decides to use transference to respond to a risk, a risk-related contractual agreement is created between the buyer and the seller.

32
Q

Screening system

A

Screening system

A tool that filters or screens out vendors that don’t qualify for the contract.

33
Q

Seller rating systems

A

Seller rating systems

These are used by organizations to rate prior experience with each vendor that they have worked with in the past. The seller rating system can track performance, quality ratings, delivery, and even contract compliance.

34
Q

Terms of Reference

A

Terms of Reference

Defines the obligations for the seller, what the seller will provide, and all of the particulars of the contracted work. Terms of reference is similar to the statement of work.

35
Q

Time and materials contract

A

Time and materials contract

A contract type in which the buyer pays for the time and materials for the procured work. This is a simple contract, usually for smaller procurement conditions. These contract types require a not-to-exceed clause, or the buyer assumes the risk for cost overruns.

36
Q

Weighting system

A

Weighting system

This takes out the personal preferences of the decision maker in the organization to ensure that the best seller is awarded the contract. Weights are assigned to the values of the proposals, and each proposal is scored.