Procurement and Tendering Flashcards

1
Q

What is procurement?

A

The overall act of obtaining goods and services for a construction project.

There are several routes by which the design and construction of a building can be procured. The selected procurement route should follow a strategy which fits the project criteria and objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the main factors which typically govern procurement route selection?

A

The key is to identify the client’s objectives and key drivers in terms of time, cost and quality. Other factors such as risk allocation should also be considered.

It’s unusual to satisfy all these elements with one procurement route. Consideration must be given to the client’s list of priorities to identify the most appropriate procurement route.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What procurement options are you familiar with?

A

Traditional procurement
Design & Build
Management Contracting
Construction Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is traditional procurement?

A

Design, bid, build.

Traditional procurement involves separating design from construction. The employer first appoints consultants to design the project in detail, contractors are then invited to submit tenders based on a fully developed scheme.

Key points:
- The design is completed by the employer’s design team before competitive tenders are invited. The contractor is then appointed to build what the designers have specified.
- The contractors tender based on a complete design produced by the employer’s consultants (with exception to CDP).
- Assuming no significant design changes arise, construction costs can be determined with reasonable certainty before work begins.
- The employer retains the design consultants during construction. The consultants prepare any additional design information and review CDP designs prepared by the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the key advantages of traditional procurement?

A
  • The employer retains control over the design
  • The design is largely finalised before the contractors tender for the build, this means the employer knows exactly what they are getting
  • All tenderers produce a submission based on the same information and tender returns are much easier to compare
  • Assuming the design is robust, reasonable price certainty is achieved at contract award
    Minimal built in contractor risk premium (unlike design and build)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key disadvantages of traditional procurement?

A
  • The overall project duration may be longer than design and build (limited opportunity to overlap design and construction phases).
  • Zero or limited contractor buildability input
  • Design risk is retained by the employer, any changes post contract will be a variation or compensation event
  • Dual point of responsibility (employer for design and contractor for construction)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When might traditional procurement be appropriate?

A
  • The employer may have specific or detailed design requirements
  • Cost certainty is important (traditional has significant advantages over construction management or management contracting procurement routes)
  • The shortest overall programme is not the employers main priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is design and build?

A

The contractor is responsible for completing the design and executing the construction phase of the project. This is a completely different approach to delivering a project via traditional procurement, where the client appoints consultants to undertake the design and then a contractor is appointed to construct the works.

Key points:
- Under JCT contracts, the employer’s team produce a set of Employer’s Requirements (ERs), the contractor then responds to the ERs with their Contractor’s Proposals (CPs).
- The original employer’s design team may be novated to the contractor for continuity, or the contractor may appoint their own team.
- The contractor is responsible for the design, planning, organisation, control and construction of the works.
- Design risk is transferred to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the key advantages of design and build procurement?

A
  • Single point of responsibility for design and construction (contractor)
  • Earlier commencement on site is possible (if design and construction can be overlapped)
  • Benefit of contractor’s experience harnessed during design period (buildability input)
  • Design and construction risk rest with the contractor
  • Provides more cost certainty than traditional procurement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the key disadvantages of design and build procurement?

A
  • The design is only as good as the employer requirements (the employer may find it difficult to prepare a sufficiently comprehensive brief)
  • More complex to compare tender returns
  • Employer changes can be difficult to value and expensive
  • The employer may have less control over aesthetics and quality
  • The contractor will build in risk premiums into their tender return
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When might design and build be appropriate?

A
  • Where there is a need to make an early start on site
  • Where the employer wishes to minimise their risk profile
  • For technically complex projects, the design will benefit from the contractor’s buildability input.
  • Where retaining control of the design is not a priority.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What additional insurances might be needed under a D&B contract?

A

The contractor and their design team will have design responsibility, therefore, it is likely additional professional indemnity insurance (PI) will be required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are Employer’s Requirements?

A

The expression ‘ Employers Requirements’ are used to describe the document(s) produced by the employer to set out its requirements in relation to the project (including performance specifications, drawings, initial designs etc.) and this is what the design and construction of the works will be based on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are Contractor’s Proposals?

A

CPs are prepared by the contractor which responds to the employers requirements. In this document, the contractor will set out more detailed design (based on the ERs) which will require further development throughout the course of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which procurement route poses the least risk to the employer?

A

Design and Build because the design risk is transferred to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why does the employer usually pay a premium for design and build at tender stage?

A

The contractor will usually factor in an allowance within their tender return in exchange for taking on the design risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Under design and build, who executes the design for the contractor?

A

The contractor may use their own in house designers or they can appoint external consultants. The employers original design team can also be novated to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is construction management?

A

The employer directly appoints multiple subcontractors (referred to as trade contractors) instead of employing a single main contractor. The single feature that makes construction management unique, particularly from management contracting, is that the employer places individual contracts with separate trade contractors themselves.

Key points:
- The employer places a direct contract with each trade contractor and utilizes the expertise of the construction manger to coordinate the works.
- The construction manger coordinates and programmes the works.
- The construction manager has no contractual links with the trade contractors.
- The construction manager has no vested interest in the financial outcome of the project and , barring professional negligence, carries no risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the key advantages of construction management procurement?

A
  • Speed to get to site
  • Overall project duration reduced by overlapping design and construction
  • The construction manager can contribute to the design and project planning processes
  • Changes in design can be accommodated without paying a premium
  • Prices may be lower due to direct contracts with trade contractors
  • The employer has no means of redress with trade contractors through direct contractual links
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the key disadvantages of construction management procurement?

A
  • Price certainty not achieved until the last trade package is let
  • The procurement route requires an informed, experienced and proactive employer to work
    The employer has a lot of consultants and contractors to manage
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

When might construction management be appropriate?

A
  • The employer is experienced in construction and has the suitable resources to manage the project
  • The employer wants to achieve an early start on site
  • The employer wants the flexibility to make minor changes to the design/specification throughout the process with minimal impact on time or finances
  • The project is technically complex and requires detailed engagement of specialist consultants and trade contractors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the riskiest procurement route for the employer?

A

Construction management. This is because the employer places individual contracts direct with each trade contractor and the construction manager carries no risk (barring professional negligence)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is management contracting?

A
  • The employer appoints a management contractor to manage the entire building process who in turn appoints trade contractors to carry out the construction works.
  • The management contractor is usually paid a fee percentage based on construction costs.
  • The management contractor has a direct contractual link with the trade contractors and is responsible for the overall construction works.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are the key advantages of management contracting?

A
  • Overall project duration can be reduced by overlapping design and construction
  • The management contractor will provide buildability input
    Single point of responsibility (management contractor)
    Trade packages are let competitively and transparently
  • There can be considerable flexibility in the design, with changes being made throughout the construction process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are the key disadvantages of Management Contracting?

A
  • Price certainty not achieved until the last trade package is let
  • Requires an informed and proactive employer to be successful
  • Depending on how the construction manager is remunerated, there may be a built in disincentive for the construction manager to minimise costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

When might management contracting be appropriate?

A
  • When an early start on site is a priority
  • Flexibility in design is required
  • Buildability input from the management contractor is required
    Where cost certainty is not a priority for the employer
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is the key difference between management contracting and construction management?

A

Construction management - The employer directly appoints multiple trade contractors to execute the works
Management contracting - The employer appoints a management contractor who in turn appoints the works contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What is a framework agreement?

A

A framework agreement is an umbrella agreement that a party enters with one or more suppliers (who may be contractors, subcontractors, suppliers or consultants) to establish governing terms.

A framework usually sets a strategic partnering relationship for the procurement of goods, works or services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

How long can a framework be?

A

Typically a framework agreement lasts for 4 years. However, this is determined by the buyer and they may range between 2-10 years.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What are the key advantages of a framework?

A
  • Framework agreements can help to develop stringer relationships between the parties involved and encourage long term collaboration and co-operation
  • Time saving (can speed up the procurement of goods and services)
  • Repeat work and continuity of delivery
  • Rates and prices are usually agreed upfront
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What are the key disadvantages of a framework?

A
  • The contractors, suppliers or consultants can become complacent
  • Bidders will invest time and money to be awarded onto a framework and then potentially not receive any work through them
  • May be restrictive to new suppliers who offer innovative, new solutions with the changing and evolving nature of technologies for example
32
Q

Why might the employer choose a framework agreement to procure goods and services?

A
  • Employers that are continuously commissioning construction work might want to reduce procurement timescales, learning curves and other risks by using framework agreements.
  • A framework allows the employer to invite tenders from suppliers of goods and services on a call-off basis as and when required
33
Q

What is the difference between a framework agreement and a contract?

A
  • A framework agreement rarely provides any specific commitment in terms of project and value of works. It is more focused around being an approved supplier.
  • A contract is usually a specific fee, with project scope and timelines allowing you to quote and tailor your product/service for the specific job at hand
34
Q

What is project partnering?

A
  • Partnering is a broad term used to describe a collaborative management approach that encourages openness and trust between the contracting parties.
  • There is more opportunity for building working relationships, finding improvements and planning investment.
  • Ownership of risk is spread between the parties and a collaborative approach is encouraged to delivering the solution and overcoming problems.
35
Q

What are the key advantages of partnering?

A
  • The overall construction and design programme can be shortened
  • The likelihood of conflict is reduced
  • Improved communication and mutual objectives
  • Improved customer satisfaction
  • Improved value for the employer
  • Improved buildability
  • Better predictability of time and cost
36
Q

What are the key disadvantages of partnering?

A
  • Less opportunity to understand what other contractors / potential partners have to offer
  • Difficult to find a strong partner which have the same objectives, ethics, attitude etc.
37
Q

What is tendering?

A

Tendering is the process by which the employer invites contractors to place a bid for work on a construction project. The overall objective is to obtain a price for the works.

38
Q

What is the difference between procurement and tendering?

A

Procurement is the overall act of obtaining goods and services from external sources and deciding the strategy on how these goods are to be acquired.

Tendering is a phase in the procurement strategy and deals with obtaining a price through a bidding process and deciding how a contractor is appointed.

39
Q

What are the 3 main tendering options for construction projects?

A

Single Stage
Two Stage
Negotiated

40
Q

What documents were included within your tender pack?

A
  • Invitation to Tender (ITT), including cover letter with tender return information.
  • Form of tender.
  • Contract conditions and employer’s amendments.
  • Instructions to tenders with information how errors will be dealt with.
  • Tender scoring matrix
  • Project information, drawings, specifications, surveys, planning conditions
  • Pricing document
  • PCI (Pre-Construction Information)
  • Quality questions (such as experience and methodology)
  • Receipt of tender
41
Q

What is a bona fide tender?

A

A bid submitted in good faith, complete and in prescribed form which meets the conditions of the bidding requirements.

Confirmation that the supplier has not colluded with another party when compiling the tender.

42
Q

What is OJEU?

A

The Official Journal of the European Union.

An online portal that houses public sector contracts that are over the stated procurement threshold - now use Find A Tender Service.

43
Q

What happens to OJEU now the UK has left the EU?

A

From 1st January 2021, the UK is not subject to EU procurement regulations, therefore, no longer follows the rules outlined for OJEU tenders.

Tenders will now be published on a new e-tendering portal, called Find a Tender Service (FTS)

44
Q

What is a Pre-Qualification Questionnaire (PQQ)

A

A pre-qualification questionnaire sets out a series of questions for potential tenderers to answer regarding their level of experience, capacity and financial standing etc. prior to being invited to tender.

45
Q

What is the purpose of a PQQ?

A

The pre-qualification questionnaire has the effect of reducing the number of potential tenderers to those that are genuinely appropriate for the project. This saves a great deal of time for potential tenderers who would not have had any realistic chance of winning the project.

46
Q

What might the PQQ ask for?

A
  • Company details
  • Details of insurance cover
  • Financial information
  • Relevant experience
  • Information about technical and professional ability
  • Information about capability and capacity
  • Health and Safety policy and records
  • Quality assurance policy
  • Environmental management policy
  • Equal Opportunities policy
  • References
47
Q

A credit check is usually part of the PQQ process, where could you get a credit check from?

A
  • Dun & Bradsheet Report
  • Credit Agency such as Experian
48
Q

What is single stage tendering?

A

Invitation to tender documents are issued to a number of competing contractors who are all given the chance to bid for the project based on identical tender documentation. This is usually done at RIBA Stage 4 so that the tendering contractors receive the most detailed information to base their bid on.

49
Q

What are the key advantages of single stage tendering?

A
  • The employer benefits from a competitive tendering process which can lead to more competitive pricing.
  • The employer can benefit from a fixed price through this tendering process.
50
Q

What are the key disadvantages of single stage tendering?

A
  • No buildability input from contractor (at stage of tender)
  • The price is only as good as the design information
  • Contractors may be unwilling to tender in a good economic climate (too much competition)
51
Q

If you had a £25m new build project under design and build procurement (single stage tender), how long would you allow for the tender period?

A

The tender period is largely dependent on the complexity of the project, however, 10-12 weeks would be reasonable as it will take some time to interpret the employer’s requirements.

52
Q

What is two stage tendering?

A

Stage 1:
The employer provides an outline project design and contractors then compete for preferred contractor status. The preferred contractor is usually chosen based on the quality of their bid, the quality of their team, preliminaries and OH&P allowances. They then join the design team on a consultancy basis using a pre-construction services agreement (PCSA).

Stage 2:
Once the design has sufficiently progressed, the contractor enters a detailed contract negotiation with the employer to agree the final price, contract conditions and programme.

53
Q

What are the key advantages of two stage tendering?

A
  • Early appointment of the contractor to work in parallel with the design team
  • Early involvement of the contractor to benefit from buildability input
  • Earlier start on site is possible
  • Employer involvement in subcontractor selection
  • Increase opportunity to value engineer with contractor input
  • Improved opportunity to identify project risk
54
Q

What are the key disadvantages of two stage tendering?

A
  • The contractor has less incentive to price the second stage competitively, negotiations may therefore be difficult.
  • Additional cost of the contractors pre-construction fee.
  • Potential for the negotiation stage to fail (contract sum not agreed).
55
Q

What is a negotiated tender?

A

A negotiated tender is effectively a single stage tender carried out between the client employer and just one contractor. Negotiated tenders are obtained by the client, inviting one contractor of their choice to submit a tender response fort he project.

56
Q

What are the key advantages of negotiated tender?

A
  • Simplicity
  • Speed, a negotiated process can have programme advantages if undertaken in good faith
  • The employer has flexibility in terms of choosing their preferred contractor
  • Time and cost savings involved in comparing and analyzing multiple tender submissions
  • The process can allow early contractor involvement
57
Q

What are the key disadvantages of negotiated tender?

A
  • Possibility of delay if contract negotiations are protracted
  • Potential cost premium due to the lack of competition
  • There is a heavy reliance on trust between the parties
  • It can be seen as anti-competitive and exclusive
58
Q

How could you justify value for money in a negotiated tender?

A

Insist on an open book approach when agreeing subcontract packages and a minimum of 3 quotes to be provided for each element of the works (this would need to be agreed upfront with the contractor).

59
Q

What is a form of tender?

A
  • The contractor usually signs and returns with their proposed tender submission
  • It is formal acknowledgement that the tenderer understands and accepts the terms of the conditions of the tender documents and any other requirements that are stipulated. The document also includes the contractor’s price and programme.
60
Q

What information is typically included in the form of tender?

A
  • Tender sum
  • The date until which the price remains valid
  • Construction period
  • Confirmation of the tender being a bona fide tender
  • Tenderer details and signature
  • Acceptance of terms and conditions
61
Q

When seeking tenders for construction work, in addition to the actual price for the work, what additional information might be requested from the contractor?

A
  • Track record of previous experience, e.g. case studies.
  • Proposed team and hierarchy
  • Methodology or approach
  • References
  • Programme
  • H&S information
  • Value engineering proposals
  • Logistics plans
  • Social value strategy
  • Diversity and Inclusion policy
62
Q

Once tenders have been submitted, what should be examined for compliance with the invitation to tender and tender instructions?

A
  • Arithmetical errors
  • Pricing errors (items not priced)
  • Pricing methods (front loading)
  • Compare the Contractor’s Proposals against the Employer’s Requirements for compliance (if D&B)
  • Check the form of tender is complete and signed
  • Resolve any qualifications
63
Q

What happens if a tender is submitted late?

A

Public Sector - documents should not be accepted
Private Sector - the matter should be discussed with the employer to understand if they would like to accept. The safest option is not to consider (potential fraud, collusion risk etc.)

64
Q

What is the danger of accepting a very low tender submission?

A
  • The contractor may be trying to ‘buy’ the project with a view to recover their costs with variations and/or claims
  • It could indicate the contractor is in poor financial or cash flow position and they are eager to win the work at any cost
  • Areas of the project may not be priced accurately, potential for an adversarial relationship to develop post contract
65
Q

How do you deal with qualifications within the tender submission?

A
  • Procedures associated with qualifications should be outlined in the tender instructions.
  • If the qualifications are unauthorised, it might invalidate the tender (leading to disqualification)
  • The employer and contractor team should look to resolve the qualifications prior to signing the contract. Any outstanding matters should be clearly documented in the contract to avoid future disputes.
66
Q

How would you deal with errors identified in the tender submissions?

A

JCT have produced a tendering practice note where two options are suggested to deal with errors, one of these options is usually drafted into the tender pack.

Alternative 1:
- The tenderer should be given the details of the errors and afforded the opportunity of confirming or withdrawing their tender
- If they withdraw, the next lowest bid is considered

Alternative 2:
- The tenderer should be given the opportunity of confirming their offer or amending it to correct genuine errors

67
Q

What would you do if you considered a contractor submitting the lowest tender to be in financial difficulty?

A
  • As part of the evaluation process, the company accounts would be reviewed to assess the financial stability of the contractor (if not already completed at PQQ stage). This could lead to disqualification if the contractor is in financial difficulty.
  • Consider a performance bond. In the event the contractor fell insolvent, the employer would be able to call on the bond and appoint another contractor to complete the project.
  • Consider a parent company guarantee
68
Q

On what grounds would you advise the client to re-tender?

A

Not enough tenderers returned tenders
The tendering procedure is compromised for some reason
- If tenders were not at the cost levels required and it was believed re-tendering to different tenderers would provide a different result
- Design changes or VE has been carried out that has significantly changed the design that was originally tendered on

69
Q

How would you deal with a front loaded tender?

A
  • Front loading is generally not a pricing error
  • Request contractor removes front loading, if the contractor refuses, this may be grounds for disqualification
70
Q

How could you reduce the risk of contractors pulling out during the tender process?

A
  • Ensuring the tender information is as accurate as possible
  • Ensure the tender period is long enough
  • Go through the PQQ to ensure the correct contractors are selected
  • Check the contractor has time and capacity to complete the tender
71
Q

What is the contract sum analysis under design and build procurement?

A

A contract sum analysis is an alternative pricing document to a schedule of works or bill of quantities. It’s often prepared in a standard format by the employer’s team to support the tender analysis. The employer’s team usually request that all tenders are returned on the same CSA format.

72
Q

What information is typically included within a tender analysis report?

A
  • List of tenders received
  • Initial tender return totals
  • Any qualifications identified
  • Post-tender adjustments
  • Revised tender sum
  • Issues to be resolved
  • Comparison of tender returns
  • Comparisons with pre-tender estimate
    -Recommendation
73
Q

If the tender was received on time, but the works were delayed and did not commence until a few months later, what would you need to check?

A

Check the form of tender, this would show how long the price (the offer) was valid for, (for example, 60 or 90 days after the tender return date).

74
Q

If the contractor (in their tender return) put a cost against an item and marked it provisional, what would you do?

A

I would seek further information from the contractor and request this to be removed, subject to the tender instructions, this may invalidate the submission.

75
Q

If you think the programme delivery is tight, how can you give comfort to the contractor regarding liquidated damages (to avoid them excessively pricing in their tender sum)?

A

The contract can be amended to include a liquidated damage free period. For example, damages would not be levied for the first 3 weeks or levied at 50% for a defined period.

76
Q

What is the purpose of a pre-tender estimate?

A

A PTE is the last cost check of the project before it is issued to tender. The design should be sufficiently developed at this stage, therefore, the PTE should be an accurate reflection of the works.

The estimate can then be used to compare against other tender submissions.

77
Q

What happens if the tender prices are higher than the pre-tender estimate?

A
  • This could be down to market conditions or some other external factor such as Covid or Brexit
  • The employers team should reconcile the tenders against the PTE to identify where the major differences are
    The team could look to value engineer the project if the prices are over budget