Procurement and Tendering Flashcards
What is procurement?
The overall act of obtaining goods and services from external sources (for example a building contractor) and includes decision making with regards to how the goods are to be acquired by reviewing a client’s requirements (i.e time, quality and cost). and their attitude to risk.
What is tendering?
Tendering forms part of the procurement strategy and involves:
- The bidding process to obtain a cost for the works; and
- How a contractor is appointed.
What is the difference between procurement and tendering?
- Procurement is the overall act of obtaining goods and services from external sources (for example a building contractor) and includes decision making with regards to how the goods are to be acquired by reviewing a client’s requirements (i.e time, quality and cost). and their attitude to risk.
- Tendering forms part of the procurement strategy and involves the bidding process to obtain a cost for the works and how a contractor is appointed.
What is two-stage tendering?
- The first stage of the process involves first-stage tender enquiry documentation being issued to preselected bidding contractors at RIBA stage 2 / 3. At this stage the works are still being designed.
- The contractors then submit their bids which do not give a lump cost for the entirety of the works but confirm their preliminaries costs, proposed sub letting of the works (sub contractors) and their overhead and profit allowances.
- The preferred contractor then joins the design team on a consultant basis using a pre-construction services agreement.
- The preferred contractor then works with the design team to complete the design before presenting a bid for the works.
What is negotiated tender?
- A single contractor is provided with the tender documentation by the client and then submits their initial cost to carry out the entirety of the works.
- The client’s professional team then negotiates the cost of the works with the contractor to achieve a final cost.
What are the advantages and disadvantages of single-stage tendering? When would you utilise single stage tendering?
Advantages:
- Ensures that only capable and approved firms submit tenders (as they are preselected from an approved list).
- Client gets cost certainty as they are provided with a lump sum for the works.
Disadvantages:
- The full design has to be prepared before the works can be tendered which is not suitable whereby total programme length is important.
What are the advantages and disadvantages of two-stage tendering? When would you use two-stage tendering?
- *Advantages:**
- Allows the contractor to contribute to the design and early planning of the work (so increases buildability).
- Allow the contractor to commence works on sections before the entirety of the design is complete.
- *Disadvantages:**
- Hard to replace the contractor is second stage negotiations break down.
- Risk of increased cost for retendering works if second stage negotiations have broken down.
- The second stage is not a competitive process so the contractors cost may not be competitive.
- *Two-stage tendering is suitable for:**
- Projects that are complex (require contractor’s input on design).
- When programme length is important.
- Projects whereby the magnitude of the works are yet unknown.
What are the advantages and disadvantages of negotiated tendering? When would you utilise negotiated tendering?
- *Advantages:**
- The contractor is usually approached because they have carried out similar works and to the required standard before so there is greater certainty of cost and quality.
- Time and cost savings by reducing input into the tendering process because only a single tender needs to be analysed.
- Time saving on tender process allows earlier commencement of the works.
- *Disadvantages:**
- Lack of competitive tendering may increase the cost for the works.
- Negotiation process needs to be structured and controlled otherwise there could be adversity between the parties before works have even commenced.
- You would usually utilise negotiated tendering when overall programme length is a priority over cost and whereby the client wants to replicate the quality of a project that the contractor has delivered before.
What are the main procurement routes?
- Traditional.
- Design and build (single and two stage).
- Management Contracting.
- Construction Management.
- Framework agreements.
- Partnering.
What is design and build procurement? When would you utilise design and build procurement? What contract would you use?
Design and build is whereby the contractor is responsible for the design, planning organisation, control and construction of the works to the employer’s requirements.
I would utilise design and build when…
- The client has a need to make an early start on site as the design can be developed during the construction phase.
- The client wishes to minimise their risk in relation to the design of the works, this may be due to risky nature of the works for example replacement of combustible cladding.
- The design is complex and contractor input is needed to ensure buildability.
- The client does not want to or is not bothered about retaining control over the development of the design.
- The JCT Design and Build, 2016 contract would be used.
What is management contracting? When would you utilise management contracting? What contract would you use?
- A procurement option whereby a client employs a management contractor to contribute to design and manage the works.
- The management contractor has direct contractual links with all of the works contractors and has the responsibility for the works without carrying them out.
- The management contractor breaks down the project into suitable works packages and selects works contractors through competitive open book tenders.
- The client then then reimburses the cost of the works packages to the management contractor in addition to their fee.
- I would utilise this procurement route when:
1. The client values an early start and overall project length over cost.
2. The works are extensive.
3. The works are complicated. - I would use the JCT Management Contract, 2016.
What are the advantages and disadvantages of design and build?
Advantages:
- There is a single point of responsibility for the design and construction of the works.
- Works can commence earlier on site as the design and construction process can overlap.
- Contractor involvement with the design ensures buildability and expertise are incorporated into the design. It also promotes innovation in design (contractor’s not constrained by detailed design) which leads to cheaper and faster construction.
Disadvantages:
- It may be hard for a client to prepare a sufficiently comprehensive brief.
- Harder to compare tenders as the contractors each have their own designs rather than pricing for fully defined and designed works.
- Designs submitted may also be uninspiring as contractors may emphasise quickness of construction over quality.
What is construction management? When would you utilise construction management? What contract would you use?
- A procurement strategy whereby the client engages directly with specialists for the design of the works via individual contracts. A construction manager is then employed on a consultant basis to plan, coordinate and monitor the works.
- The construction manager coordinates the design team and has no contractual links with the specialist contractors or the design team. They prepare the programme, determine prelims and then break down the project into suitable works packages and obtain and evaluate tenders.
- I would utilise construction management when:
1. The client is uncertain of the extent of works to be carried out.
2. Those clients that want to commence works on site quickly and is less concerned about cost certainty.
3. The client is an ‘expert’ and would benefit from the simple and direct legal relationships as they allow for effective redress of latent defects should they arise. - JCT Management Contract, 2016.
What are the advantages and disadvantages of the construction management procurement route?
Advantages:
- The construction manager can be appointed early on and can contribute to the design and planning process.
- Project duration is shortened as there is an overlap between the design and planning.
- Offers flexibility in design and the works as specialist contractors are let in stages.
- The simple and direct contractual link between the client and expert contractors allow easy redress regarding latent defects.
- Cost for the works packages may be lower due to direct contracts between the client and expert contractors.
Disadvantages:
- Client needs to be an ‘expert’ to manage the various contracts between them and specialist contractors and consultants.
- Can be difficult to select a suitable construction manager as selection is based on skill and not cost of a tender submission.
- Puts risks of the performance of specialist contractors largely on the employer as the construction manager has little responsibility.
- There is little incentive for the construction manager to reduce costs associated with the works as their payment is fee based.
- The price of the works is not confirmed until the last package of works has been let.
What are the advantages and disadvantages of the management contracting procurement route?
Advantages:
- Overall project duration is shorter due to overlapping design and construction
- There is contractor contribution to the design and planning process
- Changes can be accommodated in packages not yet let if they have no further
impact - The works are let competitively at current market prices on a firm price basis
Disadvantages:
- Can be difficult to select a suitable construction manager as selection is based on skill and not cost of a tender submission.
- Puts risks of the performance of specialist contractors largely on the employer as the construction manager has little responsibility.
- There is little incentive for the construction manager to reduce costs associated with the works as their payment is fee based.
- The price of the works is not confirmed until the last package of works has been let.
What are framework agreements? When would you utilise them? What contract would you use?
- Framework agreements allow client’s that are consistently instructing construction work to invite tenders from contractors to be carried out over a prolonged period of time on a call off basis as and when required.
- Could use JCT FA, 2016.