Process Inputs And Outputs Flashcards

1
Q

5.1.1 Define the Change

A

Inputs
- Business case
- Research
- Charter
- Strategic plan
- Success measures

Outputs
- Change definition
- Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

5.1.2 Determine Why the Change is Required

A

Inputs
- Business case
- Change definition
- Charter
- Strategic plan
- Success measures

Outputs
- Business case
- Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

5.1.3 Develop a Clear Vision for the Future State

A

Inputs
- Organization vision, mission, values
- Business case
- Change definition
- Strategic plan

Outputs
- Vision Statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

5.1.4 Identify Goals, Objectives, and Success Criteria

A

Inputs
- Business case
- Charter
- Strategic plan
- Vision statement
- Change definition

Outputs
- Change objectives and goals
- Success criteria and measures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

5.1.5 Identify Sponsors Accountable for the Change

A

Inputs
- Change definition
- Charter
- Stakeholder analysis
- Current organizational charts and profiles

Outputs
- Sponsor identification
- Sponsor assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

5.1.6 Identify Stakeholders Affected by the Change

A

Inputs
- Change definition
- Vision statement
- Current organizational charts and profiles
- Research
- Charter

Outputs
- Stakeholder analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

5.1.7 Assess the Change Impact

A

Inputs
- Change definition
- Vision statement
- Research
- Stakeholder analysis

Outputs
- Change impact assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

5.1.8 Assess Alignment of the Change with Organizational Strategic Objectives and Performance Measurement

A

Inputs
- Strategic plan
- Current vision statement
- Future state vision statement
- Case for change
- Risk plan

Outputs
- Organizational alignment assessment
- Modifications to organizational and enterprise performance targets (Goals and Objectives)
- Modifications to strategic plan
- Modification of business case
- Modification of vision statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

5.1.9 Assess External Factors that May Affect Organizational Change

A

Inputs
- Business case
- Vision statement
- Strategic plan

Outputs
- External environment impact assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

5.1.10 Assess Organization Culture(s) Related to the Change

A

Inputs
- Core values and behaviors
- Current communication channels, tools, and methods
- Opinion surveys and feedback assessments
- Vision statement

Outputs
- Culture assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

5.1.11 Assess Organizational Capacity for Change

A

Inputs
- Competency assessment
- Culture assessment
- Organization’s historical experience with change
- Stakeholder assessment
- External environment impact assessment
- Change impact assessment
- Inventory of change-related resources

Outputs
-Organizational change capacity assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

5.1.12 Assess Organizational Readiness for Change

A

Inputs
- Change objectives and goals
- Culture assessment
- Organizational change capacity assessment
- Organizational alignment assessment
- Sponsorship alignment assessment
- Vision statement
- Risk assessment

Outputs
- Organizational change readiness assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

5.1.13 Assess Communication Needs, Communication channels, and Ability to Deliver Key Messages

A

Inputs
- Change objectives and goals
- Culture assessment
- Organizational change capacity assessment
- Sponsorship alignment assessment
- Stakeholder analysis
- Current communication channels, tools, and methods
- Vision statement
- Risk assessment

Outputs
- Communication needs assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

5.1.14 Assess Learning Capabilities

A

Inputs
- Stakeholder analysis
- Change impact assessment
- Communication needs assessment
- Culture assessment
- Organizational change capacity
- Assessment
- Organizational alignment assessment

Outputs
- Learning needs assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

5.1.15 Conduct Change Risks Assessment

A

Inputs
- Stakeholder analysis
- Change impact assessment
- Culture assessment
- Organizational change capacity assessment

Outputs
- Change risks assessment
- Risk register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

5.2.1 Develop the Communication Strategy

A

Inputs
- Change definition
- Change impact assessment
- Current communication channels, tools, and methods
- Organizational change readiness assessment
- Project charter and project documentation
- Stakeholder analysis
- Vision statement

Outputs
- Communication strategy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

5.2.2 Develop the Sponsorship Strategy

A

Inputs
- Change risks
- Organizational change readiness assessment
- Sponsorship alignment assessment
- Stakeholder analysis

Outputs
- Sponsorship strategy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

5.2.3 Develop the Stakeholder Engagement Strategy

A

Inputs
- Current state analysis
- Change impact assessment
- Current communication channels, tools, and methods
- Communication strategy
- Sponsorship strategy
- Stakeholder analysis

Outputs
- Stakeholder engagement strategy

19
Q

5.2.4 Develop the Change Impact Readiness Strategy

A

Inputs
- Stakeholder engagement strategy
- Change impact assessment

Outputs
- Change impact and readiness strategy

20
Q

5.2.5. Develop the Learning and Development Strategy

A

Inputs
- Learning needs assessment
- Stakeholder analysis

Outputs
- Learning and development strategy

21
Q

5.2.6 Develop the Measurement and Benefit Realization Strategy

A

Inputs
- Strategic plan
- Case for change
- Change objectives and goals
- Project charter
- Success criteria

Outputs
- Measurement and benefit realization strategy
- Revised performance and rewards targets

22
Q

5.2.7 Develop the Sustainability Strategy

A

Inputs
- Business case
- Change objectives and goals
- Change risk assessment
- Project charter and documentation
- Strategic plan
- Success criteria and measures

Outputs
- Sustainability strategy

23
Q

5.3.1.1 Resource Plan

A

Inputs
- Change management resources, roles, and responsibilities strategy
- Communication strategy
- Learning and development strategy
- Change resources inventory
- Procurement guidelines and policies

Outputs
- Resource plan

24
Q

5.3.1.2 Sponsorship Plan

A

Inputs
- Sponsorship strategy
- Sponsorship alignment assessment
- Stakeholder analysis
- Sponsor assessment

Outputs
- Sponsorship plan

25
Q

5.3.1.3 Stakeholder Engagement Plan

A

Inputs
- Stakeholder analysis
- Stakeholder engagement strategy
- Communication strategy
- Sponsorship strategy
- Change risks

Outputs
- Stakeholder engagement plan

26
Q

5.3.1.4 Communication Plan

A

Inputs
- Communication strategy
- Current communication channels, tools, and methods
- Key messages
- Learning and development strategy
- Project charter and documentation
- Project schedule and plan
- Sponsorship strategy
- Stakeholder analysis
- Stakeholder engagement strategy
- Transition strategy

Outputs
-Communication plan

27
Q

5.3.1.5 Learning and Development Plan

A

Inputs
- Learning and development strategy
- Stakeholder analysis
- Learning needs analysis

Outputs
- Learning and development plan

28
Q

5.3.1.6 Measurement and Benefit Realization Plan

A

Inputs
- Measurement and benefit realization strategy
- Change definition
- Change objectives and goals
- Vision statement

Outputs
- Measurement and benefit realization plan

29
Q

5.3.1.7 Sustainability Plan

A

Inputs
- Status report/ Benefits gap analysis
- Resource plan

Outputs
- Sustainability plan

30
Q

5.3.2 Integrate Change Management and Project Management Plans

A

Inputs
- Change management plan
- Project charter and project documentation
- Project schedule and plan

Outputs
- Change management plan (updated)
- Project plan (updated)

31
Q

5.3.3 Review and Approve the Change Management Plan in Collaboration with Project Leadership

A

Inputs
- Change management plan
- Project plan

Outputs
- Change management plan (approved)

32
Q

5.3.4 Develop Feedback Mechanisms to Monitor Performance to Plan

A

Inputs
- Communication plan
- Learning and development plan
- Measurement and benefit realization plan
- Project schedule and plan
- Stakeholder engagement plan

Outputs
- Communication plan (updated)
- Learning and development plan (updated)
- Measurement and benefit realization plan (updated)
- Stakeholder engagement plan (updated)

33
Q

5.4.1.1 Execute Resource Plan

A

Inputs
- Change management plan
- Project schedule and plan
- Resource plan

Outputs
- Change management plan
- Financial resources update/impact reports
- Human Resources update/impact reports
- Information resources update/impact reports
- Physical resources update/impact
- Report

34
Q

5.4.1.2 Execute Communication Plan

A

Inputs
- Project plan
- Communication plan
- Stakeholder engagement plan

Outputs
- Communication delivery

35
Q

5.4.1.3 Execute Sponsorship Plan

A

Inputs
- Sponsorship plan
- Communication plan
- Stakeholder engagement plan

Outputs
- Sponsorship activities
- Sponsor competency building activities

36
Q

5.4.1.4 Execute Stakeholder Engagement Plan

A

Inputs
- Stakeholder engagement plan
- Sponsorship plan
- Communication plan

Outputs
- Stakeholder engagement activities
- Sponsor engagement activities
- Resistance management activities

37
Q

5.4.1.5 Execute Learning and Develop Plan

A

Inputs
- Learning and development plan
- Change resources, roles, and responsibilities plan
- Supporting learning and development
- Materials (e.g. job aids)

Outputs
- Learning and performance evaluation reports

38
Q

5.4.1.6 Execute Measurement and Benefit Realization

A

Inputs
- Change management plan
- Measurement and benefit realization plan

Outputs
- Measurement and benefit realization reports
- Benefits realization activities

39
Q

5.4.1.7 Execute Sustainability Plan

A

Inputs
- Sustainability plan
- Measurement baselines

Outputs
- Communication events
- Benefits reviews
- Business performance reports
- Evaluations and reviews

40
Q

5.4.2 Modify the Change Management Plan as Required

A

Inputs
- Change management plan
- Project schedule and plan

Outputs
- Change management plan (updated)

41
Q

5.5.1 Evaluate the Outcome Against the Objectives

A

Inputs
- Change objectives and goals
- Measurement and benefit realization plan
- Sustainability plan

Outputs
- Change objectives analysis outcomes and next steps

42
Q

5.5.2 Design and Conduct Lessons Learned Evaluation and Provide Results to Establish Internal Best Practices

A

Inputs
- Case for change
- Success criteria and measures
- Change management plan

Outputs
- Lessons learned evaluation
- Remediation plan

43
Q

5.5.3 Gain Approval for Completion, Transfer of Ownership, and Release of Resources

A

Inputs
- Change objectives and goals
- Measurerment and benefit realization plan
- Lessons learned report
- Future strategy plan
- Agreement on ownership transfer
- Resource release approval

Outputs
- Final summary report
- Change initiative completion