In which project management process group is the detailed project budget created?
A-) Initiating
B-) Before the project management process
C-) Planning
D-) Executing
C
The BEST time to assign a project manager to a project is during:
A-) Executing
B-) Closing C-) Initiating
D-) Planning
C
A project manager gets a call from a team member notifying him that there is a variance between the speed of a system on the project and the desired or planned speed. The project manager is surprised because that performance measurement was not identified in planning. If the project manager then evaluates whether the variance warrants a response, he is in what project management process? A-) Initiating B-) Planning C-) Executing D-) Monitoring & Controlling
D
During a team meeting, a team member asks about the measurements that will be used on the project to judge performance. The team member feels that some of the measures related to activities assigned him are not valid measurements. The project is BEST considered in what part of the project management process? A-) Initiating B-) Executing C-) Monitoring & Controlling D-) Closing
B
Which of the following is a characteristic of project management processes? A-) Iterative B-) Unique C-) Unnecessary D-) Standardized
A
Which of the following is NOT an input to the initiating process group? A-) Company processes B-) Company culture C-) Historical WBSs D-) Project scope statement
D
The project sponsor has just signed the project charter. What is the NEXT thing to do? A-) Begin to complete work packages. B-) Verify Scope. C-) Start integrated change control D-) Start to create management plans
D
The high-level project risks have just been determined. What project management process group are you in? A-) Initiating B-) Planning C-) Executing D-) Monitoring & Controlling
A
A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process?
A-) Corrective action
B-) Integrated change control
C-) Monitoring and controlling D-) Project closing
C
Which process groups must be included in every project?
A-) Planning, executing, and closing
B-) Initiating, planning and executing
C-) Initiating, planning, executing, monitoring & controlling, and closing
D-) Planning, executing, and monitoring & controlling
C
Which of the following is NOT a project management process? A)Initiating B)Starting C)Planning D)Execution
B
Which of the following activities does NOT happen in Initiating Process Group? A)Select the project manager B)Divide large projects into phases C)Create activity list D)Create measurable objectives
C
You have collected processes, procedures and historical information in
your project, identified stakeholders and developed a management strategy for these stakeholders. In which process group are you in?
A)Initiating
B)Planning
C)Execution
D)Monitoring & Controlling
A
You are in planning process group in your project. All of the following are
activities you will do in this process group EXCEPT:
A)Finalize requirements
B)Create a project scope statement
C)Develop Schedule
D)Manage People
D
Activities in planning process group must be followed in a sequence. Which of the following activities is done at LAST in planning process
group?
A)Determine what to purchase
B)Estimate time and cost project activities
C)Determine critical path
D)Hold kick-off meeting
D