Integration Management Knowledge area Flashcards
What is integration management
Putting all pieces of project together into a cohesive whole
Processes of integration management
Develop project charter (Initiating)
Develop project management plan (Planning)
Direct and manage project work (Executing)
Manage project knowledge work (Executing)
Monitor and control project work (Monitoring and controlling)
Perform Integrated change control (M & C)
Close project or phase (Closing)
Develop project charter process (Initiating)
What is included
Project Title and Description
Project Manager and Authority level
Business Case (Reason for initiation of project)
Resources Pre-Assigned - high level
Stakeholders - high level
Stakeholder Requirements - competing requirements resolved
Product description and deliverables
Measurable project objectives
Project approval requirements
High Level project Risks (+ve and -ve risks)
Project Sponsor
Who is responsible for the distribution of project charter. Publishing project charter.
Sponsor
Benefits of Project charter
Recognizes and authorizes the project
appoints PM and authority to spending money and commit resources
High level requirements
Links project to ongoing work of the organization
Does project charter change during execution
No
What are the different project selection methods
Benefits Measurement Methods (Comparative)
Constrained optimization methods(Mathematical approach)
what are benefit measurement method
Murder board (a panel of pple who try to shoot down Peer review Scoring models Economic models
Constrained optimization methods(Mathematical approach)
Linear programming
Integer programming
Dynamic Programming
Multi-objective programming
different Economic Models - Benefit measurement method
Present Value (PV) Net Present Value (NPV) Internal rate of return Payback period Benefit cost ratio
Present value
Dollar today is worth more than a dollar tomorrow
Pv=fv/(1+r)^2
fv = future value
r = interest rate
calculate PV for project with three installments below
1st installment of 100,000 at the start of the project
2nd installment of 100,000 at the end of 1st year
3rd installment of 100,000 at the end of 2nd year
1st installment PV = 100000/(1+0.10)^0 = 100,000
2nd installment PV = 100,000/(1+0.10)^1 = 90909
3rd installment PV = 100,000/(1+0/10)^2 = 82,645
Total Cashflow = 300000
present value for project= 273554
Net present Value(economic model)
NPV > 0 project can be selected
present value of total benefits(revenue or income) minus the costs over time
Higher NPV is selected
NPV = PV of Income - PV of Cost
Internal rate of return IRR (Economic model)
project with higher IRR should be selecting
how much percent a project will give back after a certain period
Pay back period
Number of time periods to recover the investment on the project
Benefit cost ratio
Ratio of Benefit v/s cost
> 1 should be selected
Economic value added (EVA)
EVA is the amount of added value the project produces for the company’s shareholders above the cost of the project
Opportunity Cost - Cost of selecting project over another project.
NPV 1 = 200000
NPV 2 = 150000
what is the opportunity cost of selecting project 1 only
150000
Sunk cost
Cost already expended on the project. All money that has been spent until now.
Sunk cost is not considered when deciding whether to continue a troubled project.