Process Group and Knowledge Area Matrix Flashcards
PMBOK Guide, Sixth Edition, Table 1-4. Project Management Process Group and Knowledge Area Mapping, p. 25
Identify the five process groups.
- Initiating
- Planning
- Executing
- Monitoring and Controlling
- Closing
Identify the ten knowledge areas.
- Integration
- Scope
- Schedule
- Cost
- Quality
- Resource
- Communications
- Risk
- Procurement
- Stakeholder
Identify the two processes in the Initiating process group.
- 4.1 Develop Project Charter
- 13.1 Identify Stakeholders
Identify the twenty-four processes in the Planning process group.
- 4.2 Develop Project Management Plan
- 5.1 Plan Scope Management
- 5.2 Collect Requirements
- 5.3 Define Scope
- 5.4 Create WBS
- 6.1 Plan Schedule Management
- 6.2 Define Activities
- 6.3 Sequence Activities
- 6.4 Estimate Activity Duration
- 6.5 Develop Schedule
- 7.1 Plan Cost Management
- 7.2 Estimate Costs
- 7.3 Determine Budget
- 8.1 Plan Quality Management
- 9.1 Plan Resource Management
- 9.2 Estimate Activity Resources
- 10.1 Plan Communications Management
- 11.1 Plan Risk Management
- 11.2 Identify Risks
- 11.3 Perform Qualitative Risk Analysis
- 11.4 Perform Quantitative Risk Analysis
- 11.5 Plan Risk Responses
- 12.1 Plan Procurement Management
- 13.2 Plan Stakeholder Engagement
Identify the ten processes in the Executing process group.
- 4.3 Manage and Direct Work
- 4.4 Manage Project Knowledge
- 8.2 Manage Quality
- 9.3 Acquire Resources
- 9.4 Develop Team
- 9.5 Manage Team
- 10.2 Manage Communications
- 11.6 Implement Risk Responses
- 12.2 Conduct Procurements
- 13.3 Manage Stakeholder Engagement
Identify the twelve processes in the Monitoring and Controlling process group.
- 4.5 Monitor and Control Project Work
- 4.6 Perform Integrated Change Control
- 5.5 Validate Scope
- 5.6 Control Scope
- 6.6 Control Schedule
- 7.4 Control Costs
- 8.4 Quality Control
- 9.6 Control Resources
- 10.3 Monitor Communications
- 11.7 Monitor Risks
- 12.3 Control Procurements
- 13.4 Monitor Stakeholder Engagement
Identify the one process in the Closing process group.
- 4.7 Close Project or Phase
Identify the seven processes in the Project Integration Management knowledge area.
Identify the six processes in the Project Scope Management knowledge area.
Identify the six processes in the Project Schedule Management knowledge area.
Identify the four processes in the Project Cost Management knowledge area.
Identify the three processes in the Project Quality Management knowledge area.
Identify the six processes in the Project Resource Management knowledge area.
Identify the three processes in the Project Communications Management knowledge area.
Identify the seven processes in the Project Risk Management knowledge area.
Identify the three processes in the Project Procurement Management knowledge area.
Identify the four processes in the Project Stakeholder Management knowledge area.
4.1
Develop Project Charter
- Initiating PG
- Integration KA
4.2
Develop Project Management Plan
- Planning PG
- Integration KA
4.3
Direct and Manage Project Work
- Executing PG
- Integration KA
4.4
Manage Project Knowledge
- Executing PG
- Integration KA
4.5
Monitor and Control Project Work
- Monitoring and Controlling PG
- Integration KA
4.6
Perform Integrated Change Control
- Monitoring and Controlling PG
- Integration KA
4.7
Close Project or Phase
- Closing PG
- Integration KA
5.1
Plan Scope Management
- Planning PG
- Scope KA
5.2
Collect Requirements
- Planning PG
- Scope KA
5.3
Define Scope
- Planning PG
- Scope KA
5.4
Create WBS
- Planning PG
- Scope KA
5.5
Validate Scope
- Monitoring and Controlling PG
- Scope KA
5.6
Control Scope
- Monitoring and Controlling PG
- Scope KA
6.1
Plan Schedule Management
- Planning PG
- Schedule KA
6.2
Define Activities
- Planning PG
- Schedule KA
6.3
Sequence Activities
- Planning PG
- Schedule KA
6.4
Estimate Activity Durations
- Planning PG
- Schedule KA
6.5
Develop Schedule
- Planning PG
- Schedule KA
6.6
Schedule Control
- Planning PG
- Schedule KA
7.1
Plan Cost Management
- Planning PG
- Cost KA
7.2
Estimate Costs
- Planning PG
- Cost KA
7.3
Determine Budget
- Planning PG
- Cost KA
7.4
Control Costs
- Monitoring and Controlling PG
- Cost KA
8.1
Plan Quality Management
- Planning PG
- Quality KA
8.2
Manage Quality
- Executing PG
- Quality KA
8.3
Quality Control
- Monitoring and Controlling PG
- Quality KA
9.1
Plan Resource Management
- Planning PG
- Resource KA
9.2
Estimate Activity Resources
- Planning PG
- Resource KA
9.3
Acquire Resources
- Executing PG
- Resource KA
9.4
Develop Team
- Executing PG
- Resource KA
9.5
Manage Team
- Executing PG
- Resource KA
9.6
Control Resources
- Monitoring and Controlling PG
- Resource KA
10.1
Plan Communications Management
- Planning PG
- Communications KA
10.2
Manage Communications
- Executing PG
- Communications KA
10.3
Monitor Communications
- Monitoring and Controlling PG
- Communications KA
11.1
Plan Risk Management
- Planning PG
- Risk KA
11.2
Identify Risks
- Planning PG
- Risk KA
11.3
Perform Qualitative Risk Analysis
- Planning PG
- Risk KA
11.4
Perform Quantitative Risk Analysis
- Planning PG
- Risk KA
11.5
Plan Risk Responses
- Planning PG
- Risk KA
11.6
Implement Risk Responses
- Executing PG
- Risk KA
11.7
Monitor Risks
- Monitoring and Controlling PG
- Risk KA
12.1
Plan Procurement Management
- Planning PG
- Procurement KA
12.2
Conduct Procurements
- Executing PG
- Procurement KA
12.3
Control Procurements
- Monitoring and Controlling PG
- Procurement KA
13.1
Identify Stakeholders
- Initiating PG
- Stakeholder KA
13.2
Plan Stakeholder Engagement
- Planning PG
- Stakeholder KA
13.3
Manage Stakeholder Engagement
- Executing PG
- Stakeholder KA
13.4
Monitor Stakeholder Engagement
- Monitoring and Controlling PG
- Stakeholder KA