6. Project Schedule Management Flashcards
Describe the Project Scope Management knowledge area.
6.1 Define the six project management processes in the project schedule management knowledge area.
Includes the processes required to manage the timely completion of the project.
- 1 Plan Schedule Management
- 2 Define Activities
- 3 Sequence Activities
- 4 Estimate Activity Durations
- 5 Develop Schedule
- 6 Control Schedule
* PMBOK Guide, Sixth Edition, 6.0 - Project Schedule Management, p. 173*
Define the following process: Plan Schedule Management
6.1 Define the six project management processes in the project schedule management knowledge area.
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
PMBOK Guide, Sixth Edition, 6.1 - Plan Schedule Management, p. 179
Define the following process: Define Activities
6.1 Define the six project management processes in the project schedule management knowledge area.
The process of identifying and documenting the specific actions to be performed to produce the project deliverables.
PMBOK Guide, Sixth Edition, 6.2 - Define Activities, p. 183
Define the following process: Sequence Activities
6.1 Define the six project management processes in the project schedule management knowledge area.
The process of identifying and documenting relationships among the project activities.
PMBOK Guide, Sixth Edition, 6.3 - Sequence Activities, p. 187
Define the following process: Estimate Activity Durations
6.1 Define the six project management processes in the project schedule management knowledge area.
The process of estimating the number of work periods needed to complete individual activities with estimated resources.
PMBOK Guide, Sixth Edition, 6.4 - Estimate Activity Durations, p. 195
Define the following process: Develop Schedule
6.1 Define the six project management processes in the project schedule management knowledge area.
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a schedule model for project execution and monitoring and controlling.
PMBOK Guide, Sixth Edition, 6.5 - Develop Schedule, p. 205
Define the following process: Control Schedule
6.1 Define the six project management processes in the project schedule management knowledge area.
The process of monitoring the status of the project to update the proejct schedule and managing changes to the schedule baseline.
PMBOK Guide, Sixth Edition, 6.6 - Control Schedule, p. 222
Identify the inputs, tools, techniques, and outputs for the following process: Plan Schedule Management
6.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project schedule management
PMBOK Guide, Sixth Edition, Figure 6-3. Plan Scope Management: Inputs, Tools & Techniques, and Outputs, p. 179
Identify the inputs, tools, techniques, and outputs for the following process: Define Activities
6.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project schedule management
PMBOK Guide, Sixth Edition, Figure 6-5. Define Activities: Inputs, Tools & Techniques, and Outputs, p. 183
Identify the inputs, tools, techniques, and outputs for the following process: Sequence Activities
6.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project schedule management
PMBOK Guide, Sixth Edition, Figure 6-7. Sequence Activities: Inputs, Tools & Techniques, and Outputs, p. 187
Identify the inputs, tools, techniques, and outputs for the following process: Estimate Activity Durations
6.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project schedule management
PMBOK Guide, Sixth Edition, Figure 6-12. Estimate Activity Durations: Inputs, Tools & Techniques, and Outputs, p. 195
Identify the inputs, tools, techniques, and outputs for the following process: Develop Schedule
6.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project schedule management
PMBOK Guide, Sixth Edition, Figure 6-14. Develop Schedule: Inputs, Tools & Techniques, and Outputs, p. 205
Identify the inputs, tools, techniques, and outputs for the following process: Control Schedule
6.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project schedule management
PMBOK Guide, Sixth Edition, Figure 6-22. Control Schedule: Inputs, Tools & Techniques, and Outputs, p. 222
What are the four precendence relationships in Precedence Diagramming Method (PDM)?
6.3 Solve simple network diagrams problems and perform basic scheduling calculations
- Finish-to-Start (FS)
- Start-to-Start (SS)
- Finish-to-Finish (FF)
- Start-to-Finish (SF)
PMBOK Guide, Sixth Edition, 6.3.2.1 - Precendence Diagramming Method, p. 189
Define the following precedence relationship: Finish-to-Start.
6.3 Solve simple network diagrams problems and perform basic scheduling calculations
A logical relationship in which a successor activity cannot start until a predecessor activity has finished. For example, installing the operating system on a PC (successor) cannot start until the PC hardware is assembled (predecessor).
PMBOK Guide, Sixth Edition, 6.3.2.1 - Precedence Diagramming Method, p. 190
Define the following precedence relationship: finish-to-finish.
6.3 Solve simple network diagrams problems and perform basic scheduling calculations
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished. For example, writing a document (predecessor) is required to finish before editing the document (successor) can finish.
PMBOK Guide, Sixth Edition, 6.3.2.1 - Precedence Diagramming Method, p. 190