Procedures and processes relevant to costs in dispute resolution Flashcards
General rule is that:
the unsuccessful party is ordered to pay the costs of the successful party.
The court, however, has discretion and can order otherwise.
Costs include:
Solicitor’s fees
Disbursements such as expenses, court, counsel, and expert fees.
Court can control costs under?
case management powers.
Overriding objective that litigation be conducted justly and at?
proportionate cost.
Parties’ conduct before and during litigation is relevant to costs orders and to?
assessment of costs.
Unreasonable conduct CAN be penalised by?
costs sanctions
Where the court orders a party to pay costs it can be either:
Make a summary assessment of the costs
OR order a detailed assessment of the costs by a costs officer.
Summary assessment – fast track cases:
*Procedure by which the court, having made an order for a party to pay costs of a case or application, then goes on to decide the amount of money to be paid, instead of ordering fixed costs or detailed assessment.
*This is the normal practice on fast-track cases.
*Consideration of costs and summary assessment of costs takes place immediately following the end of the substantive aspects of the hearing.
*Conducted by the judge dealing with the hearing and is intended to be brief.
*Doesn’t involve the lengthy consideration of each item of cost claimed
(detailed assessment, which is a longer assessment process at the end of the proceedings).
*Costs determined in summary assessment are normally to be paid within 14 days of the date of the order UNLESS the court states otherwise.
Detailed assessment – multi-track cases:
*Multi-track cases the court normally orders detailed assessment.
*Occurs where parties CAN’T agree costs.
*Procedure for detailed assessment:
Receiving party MUST serve notice of commencement, a copy of the bill of costs, fees of counsel/experts and any other disbursements on the paying party within 3 months of date of judgment or order.
Paying party can dispute any points in bill within 21 days.
If no points in dispute, receiving party can file a request for a default costs certificate entitling them to payment.
But if no agreement as to costs, receiving party MUST serve a reply within 21 days.
Paying party must then file a request for assessment hearing within 3 months.
Costs less than £75K, court will carry out provisional assessment.
Costs more than £75K, hearing with a costs judge.
Small track cases are dealt with by?
fixed costs (fixed and assessed costs).
End of a trial a party awarded costs by a costs management order:
Standard basis – recover the last approved or agreed budgeted costs UNLESS court directs otherwise.
Indemnity basis – costs are assessed in the normal way by the court, UNLESS agreed.
Standard basis – court will consider every item of costs claimed and decide:
*Item was proportionately and reasonably incurred.
*Item was proportionate and reasonable in amount.
Any doubts are resolved in favour of paying party.
Indemnity basis – court will decide if the costs were:
*Reasonably incurred
*Reasonable in amount
Any doubts are resolved in favour of receiving party.
No test for proportionality on the indemnity basis.
Costs awards made on an indemnity basis work out higher than those made?
on a standard basis.
Inter-partes cost orders - Interim:
These are cost orders in connection with interim matters.
Costs are summarily assessed at the end of the interim hearing.
Interim hearings include summary judgment, setting aside a default judgment OR striking out a party’s statement of case.
Inter-partes cost orders - final:
Costs order at the end of the trial.
Costs order will be made on a standard basis or indemnity basis.
Court will consider the following factors in assessing the amount of costs:
Conduct of the parties (before and during proceedings).
Efforts made to try and resolve the dispute.
Value of any property involved.
Importance of the matter to the parties.
Complexity of the matter.
Skill, effort, specialised knowledge, and responsibility involved.
Time spent on case.
Place and circumstances in which the work was done.
Receiving party’s last approved or agreed budget.