Prelim 1 – Module 2 Flashcards

1
Q

Capacity

A

Output per unit time when fully busy, can refer to a single station, work area, or entire process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Throughput

A

Capacity for the entire process. This is the long-run average output per unit time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bottleneck

A

The resource that limits production. It determines the cycle time of the entire system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cycle Time (CT)

A

CT = 1/Capacity
Average time between completions of successive units for
- the entire system (think about a bell ringing upon each completion)
- an entire work area (i.e., group of workers doing same job), or
- a single work
- often convert units

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Capacity Utilization

A

actual output rate/capacity
can refer to a single station, work area, or entire process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Rush Order Flow Time

A

The minimum (i.e., completion time minus entry time) to go through the system without any waiting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Total Direct Labour Content

A

Sum of all the operation times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Direct Labour Utilization

A

What percent of the time are workers actually contributing value?
= total direct labour content/(process cycle time)(# of workers)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Throughput Time

A

How long does it take to complete a process from time of arrival to time of exit? (including wait time) aka “sojourn time”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why do bottlenecks exist?

A

Inefficient process, too few resources, excess demand, unbalanced workload

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What can we do about bottlenecks?

A

Change the process at the bottleneck, add resources, control demand, shift resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Serial

A

Customer goes to one station and then the next
Capacity λ1 -> Capacity λ2
Has the same throughput as capacity min(λ1, λ2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Parallel

A

Customer is “served” by both simultaneously, and needs both to be done before moving on; e.g., body screening and luggage screening in airport security line
Has the same throughput as Capacity min(λ1, λ2)
Diagram: Capacity λ1 over Capacity λ2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Multiple Servers

A

Customers can go to either
Has the same throughput as Capacity λ1+2λ
Diagram: Capacity 1λ over Capacity 2λ with a box around both

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Strategy to solve

A

Convert everything to a rate = completions/unit of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does the process capacity calculation tell us?

A

Average completion rate with - a “fully loaded” system (i.e., infinite customers)
- note that the completion rate may vary over the short term

17
Q

What does the process capacity not necessarily tell us?

A
  • throughput time
  • average number of customers in the system
18
Q

Theory of Constraints

A

Core idea: every process has a single constraint that limits total process throughput.
Corollary: improving non-constraints will not provide significant benefits.

19
Q

5 focusing steps and meaning

A
  1. Identify: determine the current constraint
  2. Exploit: make quick improvements to that constraint’s capacity
  3. Subordinate: review other activities and re-align to support the constraint
  4. Elevate: invest in more substantial improvements to the constraint
  5. Repeat: go back to step 1 once previous constraint is no longer a constraint
20
Q

Fix the Mix to Improve Throughput

A

Some processes have customers of different “classes”.
If we don’t have the right mix of servers, throughput could suffer.
We need to know: customer mix, total resource budget ($, SF, # seats), and amount of resources needed for each type of server