What is the difference between the product backlog and the iteration backlog
The product backlog contains all work needed to be completed on the project, and the iteration backlog will contain all work that will get done in the next iteration
The project manager has acquired the project team members and is starting to work with them to complete the project work. During this process, the project manager has utilized a variety of rewards and recognition theories to keep the team motivated. What is the output of this process?
The process being completed in this question is develop team. The output is team performance assessments. All other choices are tools in this process.
The project manager has noticed that a few team members are having a difficult time following the inspection process to check the quality of new software. What is the best tool to help them see the process, making it easier to follow?
A flowchart is used to visually follow the steps in a process or multiple processes. A control chart will show if a process is in “control” by illustrating the rule of 7. A histogram is a bar chart that usually shows frequency of something. A process design chart is a made-up term.
The datacenter redesign project is currently 30% complete. The project manager is not happy with the way processes are being followed by the team in ensuring that the network wiring will meet its quality requirements. What should the project manager do to improve the processes so as to meet the quality requirements with the network wiring?
Manage quality is an executing process where you will improve processes by conducting audits and process analysis. All other choices are monitoring and controlling processes that will be used to measure the work against the project management plan.
The project manager is having a very difficult time collecting the requirements from the customers. The customers are having a difficult time putting the requirements into logical groupings. What tool can best help them group the requirements?
An affinity diagram is used to group large numbers of ideas to be analyzed. A prototype is a functional model of a product given to customers for their feedback. Decomposition is a tool used to break work down into more detailed activities. The requirements documentation would be the output of the process of collect requirements, not a tool.
How long should an agile iteration last?
no more than 4 weeks