Descriptions of Project Documents and Processes Created Flashcards

1
Q

Activity Attributes

A

Detailed information about each individual activity

Process created in: Define activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Activity list

A

List of all the activities on the project.

Process created in: Define activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Assumption log

A

List of all project assumptions and constraints.

Process created in: Develop project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Basis of estimates

A

Describes how schedule, cost, and resource estimates were developed. Also includes their confidence level and ranges.

Process created in: Estimate activity
duration, estimate
costs, estimate
activity resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Change log

A

Lists and describes the status of the change requests
that is being processed or have been processed
through the perform integrated change control process

Process created in: Perform integrated
change control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost estimates

A

Cost of each individual activity

Process created in: Estimate costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost forecasts

A

A prediction of how much the project will cost when it completes based on the current work.

Process created in: Control costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Duration estimates

A

Amount of time needed to complete each activity on
the project.

Process created in: Estimate activity
durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Issue log

A

List of all issues on the project. Could include history type, description, priority, status, and resolution

Process created in: Direct and manage
project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Lessons learned
register

A

List of all lessons learned throughout the project

Process created in: Manage project
knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Milestone list

A

Description of milestones on a project.

Process created in: Define activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Physical resource
assignments

A

Assignments of the physical resources to the activities or work packages

Process created in: Acquire resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project calendars

A

A calendar view of what takes place on a day-to-day basis on the project.

Process created in: Develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Project
communications

A

Communicate in on the project by following the
communications management plan

Process created in: Manage communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project schedule

A

A detailed breakdown of the work that needs to be
done in order to complete the project. Will include a
bar chart, milestone chart, and the project schedule network diagram.

Process created in: Develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project schedule
network diagram

A

A sequencing diagram that shows the relationships
amongst the activities and the sequence they will be
performed. But also show the critical path.

Process created in: Sequence activities

17
Q

Project scope
statement

A

A detailed description of the project or phase deliverables

Process created in: Define scope

18
Q

Project team
assignments

A

Assignment of the project team members to the work
packages or activities

Process created in: Acquire resources

19
Q

Quality control
measurements

A

Results of the activities done in the “control quality”
processes to determine if the quality standards or
policies were met.

Process created in: Control quality

20
Q

Quality metrics

A

An attribute that will be used to measure the project or to deliverable to verify that it has met the quality requirements and/or standards

Process created in: Plan quality
management

21
Q

Quality report

A

A report which generally includes information about
quality issues on the project and
recommendations
on how to improve the processes on the project

Process created in: Manage quality

22
Q

Requirements
documentation

A

Description of all requirements from project
stakeholders

Process created in: Collect requirements

23
Q

Requirements
traceability matrix

A

A table that traces the origin of the requirements.

Process created in: Collect requirements

24
Q

Resource breakdown
structure

A

Categorization and type of the project resources.

Process created in: Estimate activity
resources

25
Q

Resource calendars

A

Shows the availability of resources on the project both physical and HR.

Process created in: Acquire resources

26
Q

Resource
requirements

A

Description of the number and type of resources
needed to complete each work package or activity.

Process created in: Estimate activity
resources

27
Q

Risk register

A

A list of all positive and negative risks on a project, along with responses.

Process created in: Identify risks

28
Q

Risk report

A

A description of the overall project risks. I

Process created in: Identify risks

29
Q

Schedule data

A

The information that is used to create the schedule such as who made it, assumptions, and constraints.

Process created in: Develop schedule

30
Q

Schedule forecasts

A

A prediction of when the project may be completed
based on the current progress of the work.

Process created in: Control schedule

31
Q

Stakeholder register

A

A list of all stakeholders, which can include
categorization, impact, and communication
requirements

Process created in: Identify stakeholders

32
Q

Team charter

A

Guidelines team should follow on a project. Includes
values, decision-making process, acceptable
behavior, code of conduct, and etiquette.

Process created in: Plan resource
management

33
Q

Test and evaluation
documents

A

Used to help evaluate the project deliverables when
completed.

Process created in:
Manage quality