Descriptions of Project Documents and Processes Created Flashcards
Activity Attributes
Detailed information about each individual activity
Process created in: Define activities
Activity list
List of all the activities on the project.
Process created in: Define activities
Assumption log
List of all project assumptions and constraints.
Process created in: Develop project charter
Basis of estimates
Describes how schedule, cost, and resource estimates were developed. Also includes their confidence level and ranges.
Process created in: Estimate activity
duration, estimate
costs, estimate
activity resources
Change log
Lists and describes the status of the change requests
that is being processed or have been processed
through the perform integrated change control process
Process created in: Perform integrated
change control
Cost estimates
Cost of each individual activity
Process created in: Estimate costs
Cost forecasts
A prediction of how much the project will cost when it completes based on the current work.
Process created in: Control costs
Duration estimates
Amount of time needed to complete each activity on
the project.
Process created in: Estimate activity
durations
Issue log
List of all issues on the project. Could include history type, description, priority, status, and resolution
Process created in: Direct and manage
project work
Lessons learned
register
List of all lessons learned throughout the project
Process created in: Manage project
knowledge
Milestone list
Description of milestones on a project.
Process created in: Define activities
Physical resource
assignments
Assignments of the physical resources to the activities or work packages
Process created in: Acquire resources
Project calendars
A calendar view of what takes place on a day-to-day basis on the project.
Process created in: Develop schedule
Project
communications
Communicate in on the project by following the
communications management plan
Process created in: Manage communications
Project schedule
A detailed breakdown of the work that needs to be
done in order to complete the project. Will include a
bar chart, milestone chart, and the project schedule network diagram.
Process created in: Develop schedule