Formulas Flashcards

1
Q

BAC

A

Budget at completion: Original budget of the project.

no formula

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV

A

Planned Value: Amount of money worth of work we that should have been done on the project.

PV= Planned %
Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

EV

A

Earned Value: Amount of money worth of work you actually did on the project.

EV= Actual %
Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AC

A

Actual Cost: Amount of money you already spent on the project

no formula

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A

Cost Variance (CV): The difference between the work done and money
spent. This value should be positive for under budget. Negative values indicate over budget

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CPI

A

Cost Performance
Index (CPI): The rate of how we are spending to actually earning on the project. This value should be 1 and over
for projects under budget.

CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SV

A

Schedule Variance
(SV): The difference between the amount of work we
should have done vs. the amount actually done. This value should be positive for ahead of
schedule. Negative values indicate behind
schedule

SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI

A

Schedule Performance
Index (SPI): The rate of how we are meeting the project
schedule. This value should be 1 and over for a project to be ahead of the schedule.

SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC

A

Estimate at
Completion (EAC):

Forecasting the total cost of the project at the end
based on the current spending rate of the project.

EAC = BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC

A

Estimate to
Completion (ETC)

Forecasting the amount that will be needed to complete the current project based on the current performance.

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC

A

Variance at
Completion (VAC)

The difference between the original budget and new forecasted budget. This value should be
positive for projects that may end at or under budget

VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI

A

To-Complete
Performance Index
(TCPI)

The performance that needs to be met to finish the project within the budget.

TCPI = (BAC – EV) /
(BAC – AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly