Pool 3 Flashcards
Questions
Answers
A new project manager joins a company to work on a new. first-of-its-kind initiative. How can the project manager ensure that the project value proposition is aligned with the company’s strategic objectives?
A. Create the project management plan.
B. Refer to the company’s business plan.
C. Develop the project charter.
D. Review the business case.
Review the business case.
All the deliverables defined in a project have been completed in the final meeting to approve these deliverables. some stakeholders state that the product does not meet their needs. What should the project manager do?
A. Demonstrate that the objectives in the project charter have been achieved
B. Demonstrate that the deliverables have been verified and negotiate their approval
C. Review the list of stakeholders and determine whether the appropriate individuals attended the meeting.
D. Validate that the deliverables are as requested and close the project
Demonstrate that the deliverables have been verified and negotiate their approval
A client verbally approves the protect management plan What should the project manager do first?
A. Inform the relevant stakeholders
B. Start executing the project according to the project management plan
C. Document the approval in the decision log
D. Check organizational approval policies and processes
Check organizational approval policies and processes
A project manager in a Cross-functional organization needs to inform the department manager of the number and type of resources required. And the length of time they will be needed. What should the manager use to present this resource information?
A. Resource assignments.
B. Resource histogram
C. Responsibility assignment matrix
D. Project organization chart
Resource assignments.
Due to organizational changes, a key stakeholder is replaced by a new employee. The next status review meeting to update project progress will not take place until next month.
What should the project manager do next?
A. Schedule a separate meeting with the new stakeholder to brief them on project status.
B. Prepare and send a project status report to the new stakeholder for review.
C. Seek advice from the project sponsor on how to obtain support from the new stakeholder.
D. Wait for the next communication window to share information with the new stakeholder
Prepare and send a project status report to the new stakeholder for review
As a result of a new investor’s participation stakeholders receive status reports and project information in a language with which they are unfamiliar. This causes confusion, and lessens project support
What should the project manager do?
A. Check the communications management plan.
B. Update the organizational process assets.
C. Change the work performance information.
D. Use conflict resolution techniques.
Check the communications management plan
After a steering committee meeting, it is decided that the project will be terminated due to a lack of funds, what should the project manager do next?
A. Release the management reserve.
B. Conduct a lessons learned session.
C. Update the work breakdown structure (WBS).
D. Release the project team.
Release the project team.
A project manager invites stakeholders to a gate review meeting. What should be done at this meeting?
A. Evaluate if the protect has met its objectives and agree on phase closure
B. Evaluate protect risks and move on to the next protect phase
C. Ensue that al late changes to the project have been added
D. Ensure that the change control board (CCB) has approved me latest project changes
Evaluate if the protect has met its objectives and agree on phase closure
During project execution, a protect team identifies new risks that might affect protect success After conducting qualitative and quantitative analyses, and reviewing the risk response plan, the project manager determines that the total monetary value of the risks exceeds the project reserves.
What should the project manager do?
A. Modify the risk management plan
B. Perform a sensitivity analysis using a tornado diagram
C. Inform the project sponsor
D. Convert all reserves into revised budget costs
Inform the project sponsor
A multinational company with a cross-border project wants to implement new software that will impact several departments. The project manager needs to guarantee alignment of stakeholder expectations with the final product.
What should the project team develop?
A. Project statement of work (SOW)
B. Stakeholder engagement plan
C. stakeholders engagement assessment
D. Risk breakdown structure (RBS)
Stakeholder engagement plan
A key stakeholder misses a project kick-off meeting. The project manager arranges a separate meeting to ensure that the stakeholder understands that the project’s expected business value aligns with the organization’s strategy.
What are the key areas that should be reviewed?
A. Goals, objectives, benefits, and risks
B. Schedule, benefits, and WBS
C. Cost, schedule, risks, and work breakdown structure (WBS)
D. Benefits, effort, and resources
Goals, objectives, benefits, and risks
A project team is working on a project’s new approved scope. The regulatory team was integral in providing input that necessitated this change However, the team discovers that the regulatory department was not listed as a project stakeholder.
What should the project manager do next?
A. Gather further input from the regulatory team and update the easting change request to reflect the new information
B. Create a new change request and ensure that the regulatory team is involved in the process
C. Ensure that the regulatory learn is included in the change control board (CCB)
D. Instruct the protect team to verity the need for this change
Create a new change request and ensure that the regulatory team is involved in the process
In a control chart, three measurement points in a process are below the mean and within control limits. Four measurement points are above the mean and outside the control limits.
How is this process performing?
A. The process is out of control
B. The process is under the seven-point rule.
C. The process is writhing specification limits.
D. The process is under control
The process is out of control
A functions manager complains mat an employee is invoked in too many project meetings, wasting valuable time mat could be used for other responsibilities. To what document should the project manager refer to address this?
A. Network diagram
B. Resource calendar
C. Work breakdown structure (WBS)
D. Work performance report
Resource calendar
A vendor who historically has not had quality issues, is delivering low-quality parts. The project manager is concerned that this will cause a delay due to rework. What tool or technique should the project manager use to
address this?
A. Performance reviews
B. Procurement control system
C. Contract change control system
D. Performance reporting
Procurement control system
A project requires five tasks to complete.
? Task A begins on day 1 and will take two days to complete.
? Task B will take six days to complete and cannot begin until task A is finished.
? Task C will take four days to complete, cannot begin before task A is finished, and must be completed before task D begins.
? Task D will take eight days to complete and cannot begin until task B is finished.
? Task E will take one day to complete and cannot begin until task D is finished.
What is the duration of the critical path?
A. 15 days
B. 17 days
C. 19 days
D. 21 days
15 days
A project manager discovers that a contractor is performing additional. but necessary, work that was approved by a team member without the project manager’s knowledge What should the prefect manager do to avoid this situation in the future?
A. Meet with the team member to review how the change control process works
B. Ask the team to ensure mat work is done only on approved, in-scope items
C. Meet with the team member and the contractor to discuss the change
D. Review the requirements list and resource allocation to determine why the work was not in the scope
Ask the team to ensure mat work is done only on approved, in-scope items
A new prefect manager joins a project during us planning phase. Upon reviewing me project documents. the project manager discovers that the project management plan was me last document created. What should the project manager reference to assign resources to implement the plan?
A. Project organization chart
B. Resource management plan
C. Scope management plan
D. Resource calendars
Resource management plan
A project’s initial budget is USS200.000, but its actual cost (AC) to date is US$160,000. During an evaluation of the project’s progress, the project manager determines that the cost performance index (CPI) is 0 8, which exceeds the budget baseline.
If current performance is maintained, what is the estimate to complete (ETC)?
A. US$250,000
B. US$240,000
C. USS90.000
D. USS50.000
USS90.000
Following a company reorganization, a team member now reports to a different functional manager. What document should the project manager update to reflect Ids new reporting structure?
A. Project team assignments
B. Resource calendar
C. Resource management plan
D. Stakeholder engagement plan
Resource management plan
A project committee reviews bidder proposals Each committee member provides insights into their respective business functional areas. What tool or technique is the committee utilizing?
A. Expert judgment
B. Source selection criteria
C. Procurement negotiations
D. Data analysis
Source selection criteria
To reduce an product?s defect ratio, a corrective action is being implemented. The project manager then discovers that the corrective action is insufficient and that the team needs to resolve additional technical issues.
What should the project manager do next?
A. Issue a change request
B. Schedule a change board (CCB) meeting
C. Arrange an emergency stakeholder meeting
D. Prepare a trend analysis
Issue a change request
A project manager is working on a complex project with multiple team members and sponsors. What should the project manager do before obtaining project approval and buy-in?
A. Complete a stakeholder analysis
B. Meet with the stakeholders.
C. Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
D. Perform a risk analysis
Complete a stakeholder analysis
During the next monthly meeting, a project manager wants to show key stakeholders that the contingency reserve is insufficient to complete the entire project. What type of chart should the project manager use?
A. Bullseye
B. Correlation
C. Control
D. Burndown
Correlation
At the first team meeting, the project manager uses the risks noted in the project charter as a starting point for developing the risk register. After identifying the risks, what should the project team do next?
A. Develop contingent response strategies.
B. Perform quantitative risk analysis.
C. Populate a probability and impact matrix.
D. Calculate the management reserve.
Populate a probability and impact matrix.
Midway through a project, a subcontractor is replaced. The project sponsor asks the project manager to confirm that the new subcontractor’s deliverables meet the client’s technical specifications
What should the project manager do to confirm this?
A. Perform a quality audit
B. Perform an earned value (EV) analysis.
C. Conduct on-site inspections of the subcontractor’s deliverables
D. Establish a schedule performance index (SPI) for the subcontractor
Conduct on-site inspections of the subcontractor’s deliverables
Some project learn members claim that they failed to receive complete project information What should the project manager do to ensure proper information flow?
A. Schedule a team meeting
B. Follow the communications management plan
C. Initiate a weekly email newsletter
D. Store information in a central database
Follow the communications management plan
Due to increased price volatility a vendor asks the project manager to make a price change that will affect the project contract. What should the project manager do next?
A. Ask the change control board (CCB) for approval
B. Execute the approved change
C. Evaluate the impact, then update the risk register project management plan and budget
D. Submit a change request and analyze the impact
Submit a change request and analyze the impact
A vendor submits a high-level project schedule for a three-year project, including a detailed assign-phase schedule. what does this describe?
A. Decomposition
B. Templates
C. Rolling wave planning
D. Expert judgment
Rolling wave planning
Four months into a one project, the customer requests a change. The change control board (CCB) reviews and approves the change, but one stakeholder believes it is out of scope.
What can the project manager reference to show that the change request was appropriate?
A. Organization process assets
B. Environment enterprise factors
C. Updated project scope baseline
D. Change management plan
Change management plan
To satisfy a CEO, a project sponsor wants to reduce the project’s schedule by two weeks. What should the project manager do next?
A. Crash the schedule
B. Use change control tools
C. Create a change request
D. Apply expert judgment
Use change control tools
An unforeseen issue results in the need to procure a new piece of machinery critical for meeting quality specifications. From where may the necessary funds obtained?
A. Key stakeholders
B. Management reserve
C. Contingency reserve
D. Project sponsor
Management reserve
During the first year of a three-year project a key supplier with a long lead time stops production and closes its factory What should the project manager do first?
A. Review the risk register
B. Perform a root cause analysis
C. Meet with the change control board (CCB)
D. Baseline the project.
Review the risk register
A project manager is receiving new scope demands from multiple sources. What should the project manager use to property address these requests?
A. Project management plan updates
B. Perform integrated change control process
C. Work performance reports
D. Project document updates
Perform integrated change control process
What tool should the project manager use to demonstrate to the customer that the final production meets the business needs?
A. Work breakdown structure
B. Project scope statement
C. Requirements traceability matrix
D. project management plan
Requirements traceability matrix
A new project stakeholder is identified who has interest in, but little authority or influence on, the project.
How
should the project manager handle this stakeholder?
A. Provide information to the stakeholder as needed.
B. Work closely with the stakeholder to proactively address their concerns.
C. Keep track of the stakeholder and respond to their needs.
D. Include the stakeholder on standard updates and keep them satisfied.
Keep track of the stakeholder and respond to their needs.
A project manager identifies a new project task that will not affect the delivery date. What should the project manager do next?
A. Begin working on the new task immediately.
B. Ask the sponsor to approve the new task.
C. Create a change request.
D. Modify the schedule to include the new task.
Create a change request.
A project manager notices that work started by the project team is misaligned with an industry regulation. The project manager recalls that this topic was previously discussed during a stakeholder a stakeholder meeting.
What should the project manager review?
A. Organization process assets
B. Work performance data
C. Issue log
D. Project management plan
Organization process assets
A project manager identifies a risk that a product could endanger its users. A risk response has been proposed that will decrease the product RC4 by 10 percent, but the project will still meet financial requirements What should the project manager do?
A. Avoid the risk because endangering users will expose the company to negative publicity
B. Accept the risk and use any remaining funding from the project to deal with the sequences.
C. Mitigate the risk by adding warning labels to the product
D. Transfer the risk to the user so it does not affect the project
Avoid the risk because endangering users will expose the company to negative publicity
After completing a project schedule, the project manager learns that the sponsor wants an earlier completion data without incurring additional costs. What technique can the project manager use to meet these requirements?
A. Resource leveling
B. Fast tracking
C. Monte Carlo simulation
D. Crashing
Fast tracking
Based on the project scheduled, how much float is there for activity number 4?
A. 0 days
B. 4 days
C. 7 days
D. 9 days
4 days
A project manager is developing an organizational chart and requests the use of a specialized resource from another department. The functional manager of that department understands the value of this resource but denies the request
What should the project manager do?
A. Modify the protect management plan
B. Request sponsor approval
C. Modify the resource requirements
D. Use networking
Use networking
A new project manager assumes a project that is behind schedule. The delay is the result of a field technician’s reluctance to implement the approved design before adding a new feature.
What should the project manager do?
A. Have the field technician and design engineer meet to develop a solution.
B. Request design modification to accommodate the field technician’s new feature.
C. Insist that the field technician accept the approved design.
D. Meet with the field technician and design engineer to develop a solution
Meet with the field technician and design engineer to develop a solution
Because critical distribution needs were not identified and considered, an upcoming product is canceled one day before me announced launch. What should have been better developed to prevent this?
A. Scope management plan
B. Communications management plan
C. Stakeholder engagement plan
D. Risk management plan
Stakeholder engagement plan
Before authorizing resource assignments, a company’s project management office (PMO) requires that the project manager present the approved project charter However, the project sponsor is on vacation for the next three weeks Stakeholders want the prefect to start as soon as possible
What should the project manager do?
A. Hold the protect until the sponsor approves the protect charter
B. Find resources that can informal!/ son the project lo avoid delays
C. Obtain authorization from the steering committee.
D. Review the main project milestones to identify potential task compression to avoid delays
Obtain authorization from the steering committee.
A project manager is assign to start the charter of an IT project and review the process inputs. However, the project manager realizes that the business case does not have adequate support.
What should the project manager do to resolve this situation?
A. Notify the project sponsor
B. Hire an external subject expert (SME).
C. Request that the business analysis team perform an evaluation.
D. Propose a review of the lessons learned in similar projects
Propose a review of the lessons learned in similar projects
Two weeks into a new project, the project manager is involved in an accident. As a result another project manager must be appointed.
What should the new project manager update first?
A. Project charter
B. Resource calendars
C. Project management plan
D. Organizational process assets
Project charter
A project manager completes the requirements traceability matrix but indicates that not all requirements will be addressed. What should the project manager do to resolve this situation?
A. Define the scope by using facilitation
B. Control the scope through variance analysis.
C. Plan scope management using expert judgment.
D. Compile requirements through affinity diagrams.
Define the scope by using facilitation
The CEO of a company notifies a project manager that a bill from a vendor working on the project amounts to USS50.000 each month. The CEO questions whether the vendor is meeting the deliverables to determine if the contract should be terminated early.
What should be provided to the CEO?
A. Procurement management plan
B. Seller performance evaluation
C. Contract administration plan
Seller performance evaluation
A software development protect lot a financial institution is underway. On the software solution?s deployment date, the software produces incorrect information. What should the project manager have done to avoid this?
A. Applied agile methods, as they do not require the Manage Quality process
B. Ensured that quality assurance practices were followed by the quality team.
C. Met with stakeholders to review the software specifications
D. Requested approval of the Manage Quality process reports before project deployment
Met with stakeholders to review the software specifications
A few weeks after joining a multi-generational project learn, the project manager notices that the team is beginning to have performance issues. A key subject matter expert (SME) who is also the oldest team member, is not getting along with the younger team members
What should the project manager do before the project gets behind schedule?
A. Conduct a team-building session to demonstrate the value of all team member contributions, regardless of age or experience.
B. Review resource assignments to ensure that resources are correctly assigned based on their experience.
C. Personally speak with the SME to explain that everyone needs to work together, regardless of age.
D. Ask the project sponsor to address the issue, noting the value of the SME in obtaining project results and meeting requirements
Conduct a team-building session to demonstrate the value of all team member contributions, regardless of age or experience.
A project manager for a US$15 million construction project must meet a specific project milestone earlier than planned because a season-long pattern of extreme weather is expected soon. The project is already over budget, and the project sponsor is not prepared to provide additional funding.
Which tool or technique should the project manager use to achieve the milestone before the extreme weather begins?
A. Resource smoothing
B. Crashing
C. Simulation
D. Fast tracking
Fast tracking
The project sponsor is inappropriately requesting status reports from individual team members. The project manager plans to meet with the sponsor to discuss the issue
To what should the project manager refer prior to the meeting?
A. Communications management plan
B. Risk management plan
C. Project charter
D. Work performance reports
Communications management plan
A local supplier is unable to meet a delivery date. The project team did not anticipate this new threat to the supply of the product. Importing this product will cost the project twice the price that the local vendor charges.
What should the project manager use to fund this effort?
A. Contingency reserve.
B. Project budget reserve
C. Management reserve
D. Risk response reserve
Management reserve
A team receives outsourced deliverables and determines that they do not meet the agreed-upon acceptance criteria, what should the project manager reference to verify this with the vendor?
A. Procurement management plan
B. Request for proposal (RFP)
C. Statement of work (SOW)
D. Inspections
Statement of work (SOW)
While developing a propel schedule, the project manager identified several team activities that were critically dependent upon early customer activities. These customer activities are now significantly late What should the project manager do next?
A. Review the risk response plan
B. Meet with the customer to agree on a revised project end date.
C. Ask the change control board (CCB) to revise the scope to fit the remaining time
D. Update the project plan, and review it with the team at the next project status meeting
Review the risk response plan
While meeting with the project team, the project manager learns that the new department manager, while abroad is raising questions. What should the project manager do next?
A. Raise the issue with the project sponsor
B. Provide the kick-off meeting notes to the department manager
C. Refer the department manager to the change control board (CCB)
D. Conduct a stakeholder analysis
Conduct a stakeholder analysis
Two team managers argue about who will perform and report the status of a particular task. What source may be consulted to help resolve this?
A. Work breakdown structure (WBS)
B. Team members’ functional managers
C. Responsible, accountable, consult, and inform (RACI) matrix
D. Project sponsor
Responsible, accountable, consult, and inform (RACI) matrix
A project sponsor approves a significant change to project scope that requires additional work and new deliverables from an external provider. What should the project manager do?
A. Conduct a performance review.
B. Initiate a change request.
C. Review work performance data.
D. Employ the contract change control system
Employ the contract change control system
During a project’s execution, a modification in a data entry specification is made Due to the modification three model defects are identified for repair. What should the project manager do?
A. Escalate to the project sponsor.
B. Enter change log items.
C. Submit change requests.
D. Update the risk register
Update the risk register
A project management office (PMO) asks a project manager to calculate a project’s contingency reserves What should the project manager do”?
A. Add a percentage to the cost based on previous experiences
B. Check the total cost and add a reserve to cover quality issues
C. Ask the PMO to increase the budget according to company policies
D. Review the risk management plan
Review the risk management plan
During project implementation, the project manager reviews identified key performance indicators (KPis) and determines the project is within budget and on schedule. To what process does this activity belong?
A. Perform Integrated Change Control
B. Review Scope Baseline
C. Review Project Performance
D. Monitor and Control Project Work
Monitor and Control Project Work
Which risk analysis diagram is used to compare the relative importance and impact of variables that have a high degree of uncertainty to those that are more stable?
A. Tornado
B. Decision tree
C. Ishikawa
D. Monte Carlo
Tornado
During e protect, a business need changes and the project is canceled. The project manager meets with prefect team members to collect information learned during the project Where should this information be documented?
A. Issue log
B. Status report
C. Enterprise environmental factors
D. Organizational process assets
Organizational process assets
A project manager has two projects of equal, strategic organizational important. However, due to budget constraints only one can be chosen.
There are uncertainties and risks associated with both projects.
What tool or technique should the project manager use to decide which project to choose?
A. Simulations
B. Decision tree analysis
C. Sensitivity analysis
D. Influence diagram
Decision tree analysis
Faulty vendor supplied parts must be returned and reordered. Based on previous experience with this vendor, the project team has already identified this as a risk?
What should the project manager do to record this?
A. Issue a change request to implement the configuration plan.
B. Update the quality checklist.
C. Update the risk register.
D. Revise the vendor’s contract
Update the risk register.
A project manager wants to recruit another team member to replace an architect who resigned. what document should capture this change?
A. Ground rules
B. Project management plan
C. Organizational process assets
D. Responsibility assignment matrix (RAM)
Responsibility assignment matrix (RAM)
A project manager has been receiving enhancements to a product that will be launched in five months. What should the project manager do next to ensure that these enhancements are included in the product release?
A. Begin the Perform Integrated Change Control process.
B. Implement the Control Quality process.
C. Update the project scope statement.
D. Revise the risk management plan
Begin the Perform Integrated Change Control process.
A new smart phone is introduced Market research indicates that customer expectations for the browsing speed of certain applications are unmet. To mitigate this, the quality team reviews the design and decides to reproduce the product.
What is this cost of rework called?
A. Cost of quality assurance testing
B. Cost of quality improvement
C. Quality management cost
D. Cost of quality (COQ)
Cost of quality (COQ)
A project manager receives an approved change request related to a project’s governance framework. What should the project manager do to implement this change?
A. Revisit the plan project process and update all planning documents affected by the change.
B. Re-estimate the durations of project activities affected by the change.
C. Put the project on hold until the impact of the change can be assessed.
D. Submit the change request to the project steering committee for approval
Revisit the plan project process and update all planning documents affected by the change.
A project manager is developing a project risk register. What tool or technique should the project manager use to generate a list of all possible project risks?
A. Sensitivity analysis
B. Brainstorming
C. Tornado diagram
D. Monte Carlo simulation
Brainstorming
Due to time limitations a project manager must quickly define cross-functional requirements and reconcile stakeholder differences. What tool or technique should the project manager use?
A. Interviews
B. Benchmarking
C. Observation/conversation
D. Facilitation
Facilitation
A project in the planning stage must have a product with the following attributes:
1. Development requires a high degree of specialization
- Delivery must occur within a specific time-frame
What should the project manager do next?
A. Hire qualified staff to develop the required product.
B. Acquire the product from a supplier with many resources despite limited experience.
C. Develop the product with current staff who must learn what is required.
D. Acquire the product from a supplier who will deliver it on time
Acquire the product from a supplier who will deliver it on time
A performing organization is consulted to implement a supply chain management application for a beverage manufacturing business. During a project meeting with the customer, the performing organization mentions that the predefined budget allocation by the customer needs to be addressed
Where did the project manager find this information?
A. Project assumptions
B. Project exclusions
C. Project constraints
D. Project deliverables
Project constraints
A project manager takes over a project after its project manager resigns. At the first team meeting, the new project manager notices that team members complain and create choice.
What should the project manager do?
A. Create a rewards and recognition policy
B. Clearly observe team member performance
C. Establish ground rules with clear expectations
D. Create a new responsible accountable consult, and inform (RACI) chart to resolve issues
Establish ground rules with clear expectations
A real estate company is developing a four-building complex. The project management plan calls for completion of one building per year at a cost of USS100 million each. At the end of year three building one was completed at a cost of USS100 million, building two was completed at a cost of SUS120 million and building three was 50 percent complete at a cost of USS60 million
To meet the original project management plan, what monthly performance is needed until the end of year four?
A. 125 percent
B. 120 percent
C. 115 percent
D. 110 percent
125 percent
A project manager developed a project management plan for a team composed of members based in three countries. The project manager assumed a 40 hour work week for all team members However, during project execution, the project manager teams that one country?s team members work a 35-hour week
Where should this information have been captured?
A. Organizational process assets
B. Enterprise environmental factors
C. Legal requirements documentation
D. Response, account. consultant, and inform (RAC) chart
Enterprise environmental factors
A project’s stakeholders include business unit executives, a regional finance director, and the CEO Several stakeholders are located In different countries. What should the project manager do to obtain stakeholder approval of the project management plan?
A. Email the detailed plan 10 all stakeholders, allow a review period. and later request approval by email
B. Ask the CEO to review and approve the plan, and then communicate the approval to the other stakeholders.
C. Invite the stakeholders to a subject matter expert (SUE) workshop to review the plan, and later seek their approval via teleconference.
D. Circulate the plan among stakeholders, prepare a summary, and seek approval of the plan during a steering committee meeting
Circulate the plan among stakeholders, prepare a summary, and seek approval of the plan during a steering committee meeting
A project team is using agile methodologies 10 develop a complex system. The company does not want to
help with any preliminary reviews of product testing because they believe testing is not their responsibility
What should the prefect manager do to encourage the company to agree to preliminary reviews or testing?
Use behavior-driven development for business reviews
Explain the situation to management using a responsible, accountable. consult and inform (RACI) chart
Suggest that the technology team complete al testing
Propose that the quality control team conduct a testing workshop for the company
Explain the situation to management using a responsible, accountable. consult and inform (RACI) chart
An approved change request adds an incentive to a lump sum contract if the contractor is able to maintain the
current baseline schedule. What should now be updated?
Scope baseline
Project management plan
Cost baseline
Schedule baseline
Cost baseline
A project manager joins a project that is located in a city far from corporate headquarters. The project manager
is struggling to find the right people within the company lo relocate and design the first draft for the client
What should the project manager do?
Outsource the staffing process
Assign virtual team members
Review the resource management plan
Revisit the team charter
Review the resource management plan