Pool 2 Flashcards
Questions
Answers
A complex project is closing and many project team members report negative experiences The project stakeholders from various areas of” the organization may never work together again As part of the project’s requirements the project manager must provide lessons learned
How should the project manager ensure this requirement is met?
A. Document only the negative experiences so that alternative approaches can be developed for future projects
B. Facilitate a session with the project team to review only positive experiences
C. Reach out to each project stakeholder to capture their feedback on experiences from each phase of the project
D. Initiate documentation of both the positive and negative experiences using the issue log and record of escalation
Reach out to each project stakeholder to capture their feedback on experiences from each phase of the project
During a project steering committee meeting, the project manager reports that a formerly supportive key ream member has become resistant to and negative about changes. Where should this information be captured?
A. Responsible, accountable, consult, and inform (RACI) matrix
B. Stakeholders engagement assessment matrix
C. Risk register and issue log
D. Work performance reports
Stakeholders engagement assessment matrix
During the execution of a project, a key stakeholder asks the project manager why one high-level requirement was unmet. The project manager informs the stakeholder that they were unaware of the requirement.
What artifact should the project manager have referenced to capture this high-level requirement?
A. Statement of work (SOW)
B. Scope statement El
C. Project charter
D. Resource management plan
Project charter
While preparing for a product launch, the project manager conducts a review and identifies a potential blocker to the launch. What should the project manager do?
A. Conduct a risk workshop
B. Update the risk register
C. Identify project risks k
D. Perform a risk analysis
Update the risk register
In a project with a multigenerational team, some resources are underperforming due to differing viewpoints. This may cause project delays.
What should the project manager do?
A. Use the collaborate/problem solve technique.
B. Find new, more cooperate team members.
C. Define the communions management plan for the team
D. Use the force/direct technique
Use the collaborate/problem solve technique.
While preparing a project charter for a new project, a project manager reviews lessons learned from previous projects the lessons learned documents show frequent issues with low engagement levels and stakeholder misalignment on project objectives.
What should the project manager do to avoid repetition of this issue in the new project?
A. Gather all the requirements provided by every individual stakeholder and include in the work breakdown structure (WBS).
B. Allow any stakeholder to join the change control board (CCB) at any time in the project.
C. Include all stakeholders in the responsibility assignment matrix (RAM) for acceptance of the deliverables.
D. Build a common understanding among stakeholders about key deliverables described in the approved project charter
Build a common understanding among stakeholders about key deliverables described in the approved project charter
A project manager assumes a new project. As part of the initiation process, what should the project manager do prior to the planning stage?
A. Define the project sign-off criteria and create a risk register
B. Start gathering requirements and plan the kick-off meeting.
C. Develop the project charter and identify the stakeholders
D. Acquire the resources and determine the budget
Develop the project charter and identify the stakeholders
While reviewing a status report a project manager notices that over a period of six months the coding quality tor one developer is statistically lower than another developer assigned the same task. Which tool should the project manager use to trace the problem’s source back to its actionable root cause?
A. Scatter diagram
B. Histogram
C. ishikawa diagram
D. Control chart
ishikawa diagram
After identifying a new risk, a project manager wants to determine its impact on project objectives What should the project manager use to accomplish this?
A. Risk register
B. Risk breakdown structure (RBS)
C. Probability and impact matrix
D. Lessons learned repository
Risk register
A project manager assumes a three-year, multiphase project with tight timelines. stakeholder schedules permit time for addressing only essential activities.
How should the project manager handle updating the lessons learned?
A. Schedule lessons learned meetings at the end of each phase.
B. Periodically seek feedback on lessons learned.
C. Wait to gather lessons learned until the end of each year.
D. Fast track the project by gathering lessons learned only at the end of the project
Periodically seek feedback on lessons learned.
A project manager must track schedule variances over time. What tool or technique should be used to determine whether or not the variances are within acceptable limits?
A. Scatter diagram
B. Cause-and-effect diagram
C. Control chart
D. Control panel diagram
Control chart
While managing a project for a multinational company, a project manager continues to accept changes from
the client to maintain a good relationship and secure new business. Three quarters of the way through the project, the budget is depleted.
What should the project manager have developed to prevent this?
A. Statement of work (SOW)
B. Change management plan
C. Cost management plan
D. Project scope statement
Change management plan
A key project decision requires the support of all stakeholders. The project manager now teams that one key stakeholder was not previously identified. What should the project manager do to prevent this from being an obstacle to the project’s progress and success?
A. Review the stakeholder register.
B. Meet with the project sponsor.
C. Update the stakeholders engagement assessment matrix.
D. Conduct regular and timely reviews of the communications strategy.
Update the stakeholders engagement assessment matrix
A company has a longstanding client who is often late with payment. The company now has a new project with this client. What document should the project manager use to ensure that payment delay information is documented for this project?
A. Risk management plan
B. Historical information and lessons learned repository
C. Assumption log
D. Project charter
Assumption log
A project manager in a matrix organization notices that a resource is working a significant amount of overtime to complete project assignments. What should the project manager do next?
A. Update the risk register with this information.
B. Update the issue log with this information.
C. Discuss the situation with the resource’s manager.
D. Escalate the issue to the project sponsor
Escalate the issue to the project sponsor
New members join a project during its execution phase. What process should the project manager use to integrate the new members?
A. Manage Team
B. Plan Communications Management
C. Plan Resource Management
D. Manage Communications
Plan Resource Management
A project is using multiple vendors. What document should the project manager use to classify the various project documents in order to protect a vendor’s proprietary information?
A. Communications management plan
B. Procurement management plan
C. Project management information system (PMIS)
D. Statement of work (SOW)
Procurement management plan
A project manager is conducting a project benefits analysis with key stakeholders of an IT project. An engineer from another department informs the project manager that there are systems impacted by the solution that have not yet been identified.
What should the project manager do?
A. Document this information in the risk register
B. Review the project benefits analysis to consider the additional impact
C. Note the engineer’s issue in the issue log
D. Work with the team to identify all stakeholders
Document this information in the risk register
A project manager plans the agenda for a kick-off meeting As one of the first agenda items the project manager wants to set the strategic direction of the project Who should present this topic?
A. Customer
B. Project sponsor
C. Project manager
D. Functional manager
Project sponsor
During risk analysis for a building renovation project, it is discovered that the building contains toxic materials that must be removed. What should the project manager do to mitigate this risk using the risk transference strategy?
A. Ask the client to remove the toxic materials and exclude this work from the contract.
B. Train personnel how to remove the toxic materials and then perform the work.
C. Increase the management reserves to address the potential impact of additional time and cost.
D. Hire a contractor to perform the work
Hire a contractor to perform the work
After preparation of the project management plan, the project manager schedules a meeting with Key stakeholders. What part of the project will this complete?
A. Planning
B. Evaluation
C. Execution
D. Initiation
Planning
A supplier continuously delays submitting status reports to the project management team. What should the project manager do?
A. Submit a request to change the supplier’s scope.
B. Send the supplier a warning letter and withhold payments to them.
C. Modify the inspections and procurement management plan
D. Develop a risk response plan
Develop a risk response plan
During project execution, a project team develops a new response for an existing risk that will reduce the schedule by 30 days. What document should the project manager update?
A. Work breakdown structure (WBS)
B. Risk breakdown structure (RBS)
C. Mitigation plan
D. Risk register
Risk register
An IT group rejects a project deliverable citing noncompliance with existing processes. The project team believes that reworking the deliverable would delay project delivery by three weeks. What should the project manager do?
A. Document the rejection in the risk register and issue log.
B. Communicate the impact of the rework to the IT group.
C. Escalate the issue to the project sponsor
D. Ask the IT manager to conduct a root cause analysis of the issue.
Document the rejection in the risk register and issue log.
During project execution, several concerned stakeholders confront the project manager with concerns The project manager discovers that these stakeholders’ expectation^ were unrecorded and hence unmet
What should the project manager have consulted to avoid this?
A. Stakeholder analysis
B. Project charter
C. Stakeholder engagement plan
D. Communications management plan
Stakeholder analysis
Phase two of a complex, multi-phase project is completed, and the customer accepts the deliverables What should the project team do to benefit from this phase?
A. Measure customer satisfaction.
B. Document and share lessons learned
C. Obtain additional resources
D. Perform a risk analysis
Document and share lessons learned
A new warehouse facility is under construction. The project manager knows that increasing the team?s training
will result in a lower defect ratio.
What should the project manager do next?
A. Introduce a training program.
B. Update the resource management plan.
C. Increase quality control reviews.
D. Add training costs to the budget.
Update the resource management plan.
Company A wants to subcontract the installation of a factory’s building management system to company B. After some adjustments and a review of key stakeholder feedback, company B’s project manager needs to develop the project charter for approval.
What should company B’s project manager consider as an input when developing the project charter?
A. Submission of project management plan
B. Letter of intent
C. Letter of enquiry
D. Subcontractor submittal approval
Subcontractor submittal approval
A project manager is convinced that a contractor is requesting work outside of the project’s scope. What should the project manager do?
A. Create a change request
B. Review the scope statement with the contractor
C. Inform the sponsor of the issue
D. Hold a project review meeting to address the issue with the project team
Review the scope statement with the contractor
A project is three weeks behind schedule and the baseline finish date is two months away. The management team states there is no budget overtime pay.
What Should the project manager do to complete the propel on schedule?
A. Over-allocate resources
B. Male a scope change request
C. Crash the project schedule
D. Fast track the project schedule
Fast track the project schedule
While developing the project charter stakeholders disagree about the project’s most important objectives. What should the project ranger to resolve this?
A. Ask a subject matter expert (SME)
B. Escalate the issue to senior management
C. Use interpersonal skills to resolve conflicts
D. Defer the disagreement and conversation to a later project phase
Use interpersonal skills to resolve conflicts
Two team members argue about who will perform and report the status of a particular task. what source may be consulted to help resolve this?
A. Work breakdown structure (WBS)
B. Project sponsor
C. Team members’ functional managers
D. Responsible, accountable, consult, and inform (RACI) matrix
Responsible, accountable, consult, and inform (RACI) matrix
An overseas project has a budget of US$4 million. Due to a decrease in the currency exchange rate, the project’s cost performance index (CPI) is 0.91. What should the project manager do to address this issue’?
A. Update the risk register
B. Update the project management plan
C. Request sponsor approval of the change
D. Create a change request
Update the risk register
A project manager realizes that an issue that occurred several weeks ago has negatively impacting the schedule. When the mitigation plan is initiated, it fails because the required resources are now unavailable.
What should the project manager have done to avoid this?
A. Updated the resource management plan
B. Sent out status reports to stakeholders
C. Conducted stand-up meetings to communicate project status
D. Reviewed and updated the risk mitigation plan
Updated the resource management plan
A project manager conducts an inquiry into the increase of scrapped material over the past quarter. The project manager assembles a team and proposes a project business case to overhaul the system.
What should the project manager use to justify and establish boundaries for validating the viability of this project1?
A. Benchmarking
B. Questionnaires and surveys
C. Cost-benefit analysis
D. Cost of quality (COQ) method
Cost-benefit analysis
An external audit concludes that a project is six to 12 months behind schedule. The project manager and the project team agree. What should the project manager do next?
A. Initiate the change request process
B. Update the risk register
C. Set a new project schedule baseline
D. Revise the work breakdown structure (WBS)
Update the risk register
A demanding project stakeholder insists that an additional feature be added to a project product without changing the scope, budget or schedule. The project manager allows this feature to be included since it adds great value to the end product. However, this lengthens the project schedule and increases project cost.
Which process should the project manager have following before including the additional product feature?
A. Change management
B. Schedule and cost management
C. Product scoping
D. Requirements definition
Change management
During a project’s execution phase. the project manager receives notice from environment authorities to stop work. What should the project manager have done to avoid this?
A. Defined a detailed scope of work
B. Developed a comprehensive project management plan
C. Identified project risks
D. Identified stakeholders
Identified stakeholders
After preparing the work breakdown structure (WBS), the project manager is ready to assign task areas to project team members. Subsequently, the project sponsor asks to add requirements that the team feels are unachievable.
What should the project manager do next?
A. Evaluate the impact of the request on the project scope, schedule, and budget.
B. Use expert judgment to adjust the WBS based on the new requirements.
C. Review the project scope and resources to assess the feasibility of satisfying the request.
D. Collect requirements, and conduct a team brainstorming session.
Evaluate the impact of the request on the project scope, schedule, and budget.
An organization is completing a critical milestone during the construction of residential properties. The project is fully sponsored by the government. Ten days prior to completion of this key project phase: affected community members begin a four-day protest causing the project to be put on hold.
What should the project manager do?
A. Increase effort on the project.
B. Mitigate the risk.
C. Review the timeline
D. Escalate the issue to the project sponsor
Escalate the issue to the project sponsor
Upon approval, a new project manager immediately begins a project. Three points into me project, the project manager identifies numerous obstacle. What should the project manager have done?
A. Performed a quantitative risk analysis
B. Performed a qualitative risk analysis
C. Identified risks
D. Planned risk responses
Identified risks