PMP - Free for All Questions Flashcards
Random Nuggets of Test Information
Gulf of Evaluation
- The way I describe it may not be how you hear it ( Telephone Game)
- Misunderstanding can breed conflict, rework
Where are the team ground rules defined?
Team Charter
- Define expectations and ground rules as early as possible
- Confirm approaches for Knowledge Transfer (lessons learned registry, osmosis learning, etc.)
- Violations to ground rules must be addresses
What is emotional intelligence and how is it best used?
- Assessing of behavior through the use of personality indicators (know you own feelings and how they will impact others)
- Promote team performance through the use of emotional intelligence
-Adjust emotional intelligence and how you communicate to stakeholders
What is MVP
Minimal Viable Product -
Functional, viable, minimal level of functionality while focusing on breaking project down into smaller deliverables/increments
- Quick way to obtain feedback and confirm understanding from Stakeholders
Communication Channels Formula
n * (n -1) / 2
What is the Risk Register
Where risks are captured and identified
How prioritizes the Product Backlog
The Product Owner prioritizes the backlog based on perceived value
- In Agile iterations, the most valuable work is done first
Define the (2) Types of Risk
1 - Negative Risk == Threat/Issues
2 - Positive Risk == Opportunities
- Engage team and stakeholders to remediate issues
Name several external business environmental impacts to a project
- Regulations
- Politics
- Technology
- Market
- Assess and prioritize the impact on project scope / product backlog based on changes in the external business environment
What must happen before a traditional project can be formally closed?
- all bills and paid off, the lessons learned register updated, and the resources released
- This holds true for projects terminated early
When selecting a contract to use on a project with a potential seller it is important to do what?
Always use a contract that is mutually beneficial to both the seller and the buyer and satisfies the overall project value and business objectives
What is being a servant leader?
- Be a servant leader to the team at all times.
- Impower the team and remove impediments
- Providing the tools for the team to succeed while staying out of their way
What is PERT (Project Evaluation and Review Technique)?
- A scheduling tools that uses a weighted average formula to predict length of a project
What is Analogous Estimating
- Top-Down Estimating
- Using historical Information to predict estimates
- Used when limited information is available; not very accurate
What is Bottom-Up Estimation ?
- A detailed estimation based on the separate estimate / break-down of each task from the WBS and aggregated up to a summary mode
- Very detailed & accurate; extremely time consuming & labor intensive / costly
What is Parametric Estimation
- An estimate based on statistical relationship between historical data and other variables (always includes a divisor)
What is 3-Point Estimation
An estimate that calculates an expected duration using a weighted average of 3: Optimistic, Pessimistic, Most Likely
What is the formula for Beta Distribution in 3-Point Estimation?
(Optimistic Estimate + (4 x Realistic Estimate) + Pessimistic Estimate) / 6
What is the formula for Standard Deviation in 3-Point Estimation?
(Pessimistic Estimate - Optimistic Estimate) / 6
What is the formula for Triangular Distribution in 3-Point Estimation?
(Optimistic Estimate + Realistic Estimate + Pessimistic Estimate) / 3
What is Reserve Analysis?
- Money set aside for risks
- Slack Time, Contingency Reserves, or Time Reserves
What is Critical Path Method (CPM)?
- Calculated the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) dates to help determine leads/lags, activity relationships and schedule constraints
What does the relationship of “Start to Start” mean in CPM (Critical Path Method)
- Relationship of “Start to Start” is when a successor activity cannot start until the predecessor activity has started
- This means that they both generally start at the same time, but may not finish at the same time
What is “crashing” in project scheduling?
- Schedule compression by adding more resources to a project activity
- always adds more cost
- may add additional risk