PMP - EVM Formulas Flashcards

1
Q

BAC - Budget at Completion

A

Definition:
Original Budget of the Project

Formula:
None, it’s just the original budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV - Planned Value

A

Definition:
Amount of money worth of work that we should have done on the project

Formula:
PV = Planned % Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

EV - Earned Value

A

Definition:
Amount of money worth of work you actually did on the project

Formula:
EV = Actual % Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AC - Actual Cost

A

Definition:
Amount of money you already spent on the project

Formula:
None, it’s simply the amount of money already spent on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV - Cost Variance

A

Definition:
The difference between the work done and the money spent. This value should be positive for under budget (negative values indicate over budget)

Formula:
CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CPI - Cost Performance Index

A

Definition:
The rate of how we are spending to actually earning on the project. This value should be 1 and over for project under budget

Formula:
CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SV - Schedule Variance

A

Definition:
The difference between the amount of work we should have done vs. the amount of work actually done. Negative values indicate behind schedule

Formula:
SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI - Schedule Performance Index

A

Definition: The rate of how we are meeting the project schedule. This value should be 1 and over for a project ahead of schedule

Formula:
SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC - Estimate at Completion

A

Definition:
Forecasting the total cost of the project at the end based on the current spending rate of the project

Formula:
EAC = BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC - Estimate to Completion

A

Definition:
Forecasting the amount that will be needed to complete the current project based on the current performance

Formula:
ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC - Variance at Completion

A

Definition:
The difference between the original budget and the new forecasted budget. This value should be positive for projects that may end under budget

Formula:
VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI - To-Complete Performance Index

A

Definition:
The performance that needs to be met to finish the project within the budget

Formula:
TCPI = (BAC - EV) / (BAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly