PMP formulas Flashcards
1
Q
earned value EV
A
EV=should %complete * BAC
2
Q
Planned value
A
actual %complete * BAC
3
Q
Cost Varience
A
CV=EV-AC
4
Q
Scheduled Variance
A
SV=EV-PV
5
Q
cost performance index
A
CPI=EV/AC
6
Q
schedule performance index
A
SPI=EV/PV
7
Q
estimate at completion
A
EAC=BAC/CPI
8
Q
estimate to completion
A
ETC=EAC-AC
9
Q
to complete performance index (using BAC)
A
(BAC-EV)/(BAC-AC)
10
Q
to complete performance index (using EAC)
A
(BAC-EV)/(EAC-AC)
11
Q
variance at completion
A
VAC=BAC-EAC