PMI Lexicon Flashcards

1
Q

A set of conditions that are met before deliverables are accepted.

A

Acceptance Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A distinct, scheduled position of work performed during the course of a project.

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

An alphanumeric value assigned to each activity the enables classifying, sorting, and filtering.

A

Activity Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A unique alphanumeric value assigned to an activity and used to differentiate that activity from other activities.

A

Activity Identifier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A phrase that names and describes an activity.

A

Activity Label

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The realized cost incurred for the work performed on an activity during a specific time period.

A

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.

A

Analogous Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

An activity where effort is allotted proportionality across certain discrete efforts and not divisible into discrete efforts.

A

Apportioned Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A factor in the planning process considered to be true, real, or certain, without proof or demonstration.

A

Assumption

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.

A

Backward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The approved version of a work product that can be changed using formal change control procedures and is used as the basis for comparison to actual results.

A

Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure.

A

Bottom-Up Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The sum of all budgets established for the work to be performed.

A

Budget at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected.

A

Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.

A

Change Control Board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.

A

Change Control System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A formal proposal to modify a document, deliverable, or baseline.

A

Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A numbering system used to uniquely identify each component of the work breakdown structure.

A

Code of Accounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A component of the project, program, or portfolio management plan that describes how, when, and by whom information will be administered and disseminated.

A

Communications Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.

A

Configuration Management System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A factor that limits the options for managing a project, program, portfolio, or process.

A

Constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A document describing actions that the project team can take if predetermined trigger conditions occur.

A

Contingency Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Time or money allocated in the schedule or cost baseline for known risks with active response strategies.

A

Contingency Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.

A

Control Account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

An intentional activity that realigns the performance of the project work with the project management plan.

A

Corrective Active

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

The approved version of work page cost estimates and contingency reserve that can be changed using formal change control procedures and is used as the basis for comparison to actual results.

A

Cost Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

A component of a project or program management plan that describes how costs will be planned, structured, and controlled.

A

Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.

A

Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.

A

Cost Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

A schedule compression technique used to shorten the schedule duration for the last incremental cost by adding resources.

A

Crashing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

A schedule method that allowed the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.

A

Critical Chain Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.

A

Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Any activity on the critical path in a project schedule.

A

Critical Path Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.

A

Critical Path Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

A point in time when the status of the project is recorded.

A

Data Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.

A

Decision Tree Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.

A

Decomposition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

An intentional activity to modify a nonconforming product or product component.

A

Defect Repair

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Any unique and verifiable product, result, or capability to perform a service that is produced to complete a process, phase, or project.

A

Deliverable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

An activity that can be planned and measured and that yields a specific output.

A

Discrete Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks.

A

Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints.

A

Early Finish Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints.

A

Early Start Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

The measure of work performed expressed in terms of the budget authorized for that work.

A

Earned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

A methodology that combines scope, schedule, and resource measurements to asses project performance and progress.

A

Earned Value Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks.

A

Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program, or portfolio.

A

Enterprise Environmental Factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

A

Estimation at Completion (EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

The expected cost to finish all the remaining project work.

A

Estimate to Complete (ETC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.

A

Fast Tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.

A

Finish-to-Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

A logical relationship in which a successor activity cannot start until a predecessor activity has finished.

A

Finish-to-Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

method of estimating earned value in which a specific percentage of the budget value of a work package is assigned to the start milestone and the remaining percentage is assigned when the work package is complete.

A

Fixed Formula Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

A critical path method technique for calculating the early start and finish dates by working forward through the schedule model from the project start date or a given point in time.

A

Forward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.

A

Free Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work and apply resources.

A

Functional Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates.

A

Gantt Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

The amount of time whereby a successor will be delayed with respect to a predecessor activity.

A

Lag

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.

A

Late Finish Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints.

A

Late Start Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.

A

Lead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

The knowledge gained during a project which shows how project events were addressed or schedule be addressed in the future for the purpose of improving future performance.

A

Lessons Learned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

An activity that does not produce definitive end products and is measured by the passage of time.

A

Level of Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

A dependency between two activities or between an activity and a milestone.

A

Logical Relationship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Time or money that management sets aside in additional to the schedule or cost baseline and releases for unforeseen work that is within the scope of project.

A

Management Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

An organizational structure in which the project manager shares authority with the functional manager temporarily to assign work and apply resources.

A

Matrix Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

A significant point or event in a project, program, or portfolio.

A

Milestone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

A type of schedule that presents milestones with planned dates.

A

Milestone Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

An estimate of the most probably activity duration that takes into account all of the known variables that could affect performance.

A

Most Likely Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

An activity with a total float that is deemed to be low based on expert judgment.

A

Near-Critical Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

A sequence of activities with low float which, if exhausted, becomes a critical path sequence for the project.

A

Near-Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

All activity dependencies in a project schedule network diagram.

A

Network Logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

A sequence of activities connected by logical relationships in a project schedule network diagram.

A

Network Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

A point at which dependency lines connect on a schedule network diagram.

A

Node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

A risk that would have a positive effect on one or more project objective.

A

Opportunity

76
Q

An estimate of the shortest activity duration that takes into account all of the known variables that count affect performance.

A

Optimistic Duration

77
Q

A hierarchical representation of the project organization, which illustrates the relationship between project activities and the organizational units that will perform those activities.

A

Organizational Breakdown Structure

78
Q

A structural, cultural, technological, or human-resource practice that the performing organization can use to achieve strategic objectives.

A

Organizational Enabler

79
Q

Plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization.

A

Organizational Process Assets

80
Q

A framework in which portfolio, program, and project management are integrated with organizational enablers in order to achieve strategic objectives.

A

Organizational Project Management

81
Q

The level of an organization’s ability to deliver the desired strategic outcomes in a predictable, controllable, and reliable manner.

A

Organizational Project Management Maturity

82
Q

An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.

A

Parametric Estimating

83
Q

A relationship in which a schedule activity has more than one predecessor.

A

Path Convergence

84
Q

A relationship in which a schedule activity has more than one successor.

A

Path Divergence

85
Q

An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.

A

Percent Complete

86
Q

Integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project execution.

A

Performance Measurement Baseline

87
Q

An enterprise whose personnel are the most directly involved in doing the work of the project or program.

A

Performing Organization

88
Q

An estimate of the longest activity duration that takes into account all of the known variables that count affect performance.

A

Pessimistic Duration

89
Q

A review at the end of a phase in which a decision is made to continue to the next phase, to continue with medication, or to end a project or program.

A

Phase Gate

90
Q

The authorized budget assigned to scheduled work.

A

Planned Value

91
Q

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.

A

Portfolio

92
Q

The process of optimizing the mix of portfolio component to further the strategic objectives of the organization.

A

Portfolio Balancing

93
Q

A document issued by a sponsor that authorizes and specifies the portfolio structure and links the portfolio to the organization’s strategic objectives.

A

Portfolio Charter

94
Q

The centralized management of one or more portfolios to achieve strategic objectives.

A

Portfolio Management

95
Q

A document that specifies how a portfolio will be organized, monitored, and controlled.

A

Portfolio Management Plan

96
Q

The person or group assigned by the performing organization to establish, balance, monitor, and control portfolio components in order to achieve strategic business objectives.

A

Portfolio Manager

97
Q

A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.

A

Precedence Diagramming Method

98
Q

An activity that logically comes before a dependent activity in a schedule.

A

Predecessor Activity

99
Q

An intentional activity that ensures the future performance of the project work is aligned with the project management plan.

A

Preventive Action

100
Q

A grid for mapping the probability of occurrence of each risk and its impact on the project objectives if that risk occurs.

A

Probability and Impact Matrix

101
Q

A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.

A

Procurement Management Plan

102
Q

The series of phases that represent the evolution of a product, from concept through delivery, growth, maturity, and to retirement.

A

Product Life Cycle

103
Q

Related project, subsidiary programs, and program activities managed in a coordinated manner to obtain benefits not available from managing them individually.

A

Program

104
Q

A document issued by a sponsor that authorizes the program management team to use organizational resources to execute the program and links the program to the organization’s strategic objectives.

A

Program Charter

105
Q

A technique used to estimate project duration through a weighted average of optimistic, pessimistic, and most likely activity durations when there is uncertainty with the individual activity estimates.

A

Program Evaluation and Review Technique (PERT)

106
Q

The application of knowledge, skills, and principles to a program to achieve the program objectives and to obtain the benefits and control not available by managing program components individually.

A

Program Management

107
Q

A management structure that standardizes the program-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.

A

Program Management Office

108
Q

A document that integrates the program’s subsidiary plans and established the management controls and overall plan for integrating and managing the program’s individual components.

A

Program Management Plan

109
Q

The person authorized by the performing organization to lead the team or teams responsible for achieving program objectives.

A

Program Manager

110
Q

The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.

A

Progressive Elaboration

111
Q

A temporary endeavor undertaken to create a unique project, service, or result.

A

Project

112
Q

The sum of work package cost estimates, contingency reserve, and management reserve.

A

Project Budget

113
Q

A calendar that identifies working days and shifts that are available for scheduled activities.

A

Project Calendar

114
Q

A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

A

Project Charter

115
Q

An organizational structure in which the project manager has full authority to assign work and apply resources.

A

Projectized Organization

116
Q

The series of phases that a project passes through from its start to completion.

A

Project Life Cycle

117
Q

The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

A

Project Management

118
Q

A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.

A

Project Management Office

119
Q

The document that describes how the project will be executed, monitored and controlled, and closed.

A

Project Management Plan

120
Q

The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.

A

Project Manager

121
Q

A collection of logically related project activities that culminates in the completion of one or more deliverables.

A

Project Phase

122
Q

An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.

A

Project Schedule

123
Q

A graphical representation of the logical relationships among the project schedule activities.

A

Project Schedule Network Diagram

124
Q

The work performed to deliver a product, service, or result with the specified features and functions.

A

Project Scope

125
Q

The description of the project scope, major deliverables, assumptions, and constraints.

A

Project Scope Statement

126
Q

A component of the project or program management plan that describes how an organization’s policies, procedures, and guidelines will be implemented to achieve the quality objectives.

A

Quality Management Plan

127
Q

A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed.

A

Requirements Management Plan

128
Q

A grid that links product requirements from their origin to the deliverables that satisfy them.

A

Requirements Traceability Matrix

129
Q

The risk that remains after risk responses have been implemented.

A

Residual Risk

130
Q

A hierarchical representation of resources by category and type.

A

Resource Breakdown Structure

131
Q

A calendar that identifies the working days and shifts upon which each specific resource is available.

A

Resource Calendar

132
Q

A resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path.

A

Resource Leveling

133
Q

A component of the project management plan that describes how project resources are acquired, allocated, and controlled.

A

Resource Management Plan

134
Q

A technique in which activity start and finish dates are adjusted to balance demand for resources with the available supply.

A

Resource Optimization Technique

135
Q

A resource optimization technique in which free and total float are used without affecting the critical path.

A

Resource Smoothing

136
Q

A grid that shows the project resources assigned to each work package.

A

Responsibility Assignment Matrix

137
Q

An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.

A

Risk

138
Q

A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.

A

Risk Acceptance

139
Q

The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward.

A

Risk Appetite

140
Q

A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.

A

Risk Avoidance

141
Q

A hierarchical representation of potential sources of risk.

A

Risk Breakdown Structure

142
Q

A group of potential causes of risk.

A

Risk Category

143
Q

A risk response strategy whereby the project team acts to increase the probability of occurrence or impact of an opportunity.

A

Risk Enhancement

144
Q

A risk response strategy whereby the project team acts to ensure that an opportunity occurs.

A

Risk Exploiting

145
Q

An aggregate measure of the potential impact of al risks at any given point in time in a project, program, or portfolio.

A

Risk Exposure

146
Q

A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed.

A

Risk Management Plan

147
Q

A risk response strategy whereby the project team acts to decrease the probability of occurrence or impact of a threat.

A

Risk Mitigation

148
Q

The person responsible for monitoring the risk and for selecting and implementing an appropriate risk response strategy.

A

Risk Owner

149
Q

A repository in which outputs of risk management processes are recorded.

A

Risk Register

150
Q

A risk response strategy whereby the project team allocates ownership of an opportunity to a third party who is best able to capture the benefit of that opportunity.

A

Risk Sharing

151
Q

The measure of acceptable variation around an objective that reflects the risk appetite of the organization and stakeholders.

A

Risk Threshold

152
Q

A risk response strategy whereby the project team shifts the impact of a threat to a third party, together with the ownership of the response.

A

Risk Transference

153
Q

An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future if planned at a higher level.

A

Rolling Wave Planning

154
Q

The approved version of a schedule model that can be changed using formal change control procedures and is used as the basis for comparison to actual results.

A

Schedule Baseline

155
Q

A technique used to shorten the schedule duration whiteout reducing the project scope.

A

Schedule Compression

156
Q

A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring and controlling the schedule.

A

Schedule Management Plan

157
Q

A representation of the plan for executing the project’s activities, including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts.

A

Schedule Model

158
Q

A process used to investigate or analyze the output of the schedule model in order to optimize the schedule.

A

Schedule Model Analysis

159
Q

A technique to identify early and late start dates, as well as early and late finish dates, for the uncompleted portions of project activities.

A

Schedule Network Analysis

160
Q

A measure of schedule efficiency expressed as the ratio of earned value to planned value.

A

Schedule Performance Index (SPI)

161
Q

A measure of schedule performance expressed as the difference between the earned value and planned value.

A

Schedule Variance (SV)

162
Q

The approved version of a scope statement, work breakdown structure, and its associated WBS dictionary that can be changed using formal change control procedures and is used as the basis for comparison to actual results.

A

Scope Baseline

163
Q

The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.

A

Scope Creep

164
Q

A component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and validated.

A

Scope Management Plan

165
Q

A technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.

A

S-Curve Analysis

166
Q

A risk that arises as a direct result of implementing a risk response.

A

Secondary Risk

167
Q

An individual or a group that provides resources and support for the project, program, or portfolio, and is accountable for enabling success.

A

Sponsor

168
Q

A component of the resource management plan that describes when and how team members will be acquired and how long they will be needed.

A

Staffing Management Plan

169
Q

An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio.

A

Stakeholder

170
Q

A component of the project or project management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in project or program decision making and execution.

A

Stakeholder Engagement Plan

171
Q

A logical relationship in which a successor activity cannot finish until a predecessor activity has started.

A

Start-to-Finish

172
Q

A logical relationship in which a successor activity cannot start until a predecessor activity has started.

A

Start-to-Start

173
Q

A dependent activity that logically comes after another activity in a schedule.

A

Successor Activity

174
Q

A group of related schedule activities aggregated and displayed as a single activity.

A

Summary Activity

175
Q

A risk that would have a negative effect on one or more project objectives.

A

Threat

176
Q

A technique used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.

A

Three-Point Estimating

177
Q

A measure of the cost performance that is achieved with the remaining resources in order to met a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.

A

To-Complete Performance Index (TCPI)

178
Q

The amount of time that a schedule activity can be delayed or extended from its early start date without dealing the project finish date or violating a schedule constraint.

A

Total Float

179
Q

An event or situation that indicates that a risk is about to occur.

A

Trigger Condition

180
Q

A technique for determining the. cause and degree of difference between the baseline and actual performance.

A

Variance Analysis

181
Q

A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.

A

Variance at Completion (VAC)

182
Q

A document that provides detailed deliverable, activity, and schedule information about each component in the work breakdown structure.

A

WBS Dictionary

183
Q

A method of estimating earned value in which the budget value of a work package is divided into measurable segments, each ending with a milestone that is assigned a weighted budget value.

A

Weighted Milestone Method

184
Q

The process of evaluating scenarios in order to predict their effect on project objectives.

A

What-If Scenario Analysis

185
Q

An immediate and temporary response to an issue for which a prior response had not been planned or was not effective.

A

Workaround

186
Q

A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.

A

Work Breakdown Structure (WBS)

187
Q

The work defined at the lowest level of the work breakdown structure for which cost and duration as estimated and managed.

A

Work Package