PM3110 Chapter 8 Flashcards

1
Q

Activity-based costing

A

. a budgeting method that assigns costs first to activities and then to the projects based on each project’s use of resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Ballpark estimates

A

.typically used when either information or time is scarce. Companies often use them as preliminary estimates for resource requirements or to determine if a competitive bid can be attempted for a project contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bottom-up budgeting

A

.begins inductively from the work breakdown structure to apply direct and indirect costs to project activities. The sum of the total costs associated with each activity are then aggregated, first to the work package level, then at the deliverable level, at which point all task budgets are combined, and then higher up the chain where the sum of the work package budgets are aggregated to create the overall project budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Comparative estimates

A

.are based on the assumption that historical data can be used as a frame of reference for current estimates on similar projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Crashing costs

A

.suppose the project has fallen behind schedule and the decision is made to “_____” certain project activities in the hopes of regaining lost time. Among these costs could be: expanded use of overtime, hiring additional temporary workers, contracting with external resources or organizations for support, and incurring higher costs for transportation or logistics in speeding up materials deliveries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Definitive estimates

A

These estimates can be given only upon the completion of most design work, at a point when the scope and capabilities of the project are quite well understood.These estimates can be expected to have an accuracy of ±5%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Direct costs

A

.These are clearly assigned to the aspect of the project that generated the cost. Labor and materials may be the best examples.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Expedited costs

A

.are unplanned costs incurred when steps are taken to speed up the project’s completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Feasibility estimates

A

.based as a guideline on real numbers, or ­figures derived after the completion of the preliminary project design work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Fixed costs

A

.These are routinely used for construction projects, where there are published materials cost tables that can give reasonably accurate cost estimates for a wide range of project activities based on an estimate of the quantities involved. Because they are developed farther down the life cycle, these estimates are often expressed in terms of a degree of accuracy of+/- 10%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Function point analysis

A

.a system for estimating the size of software projects based on what the software does.The measure then relates directly to the business requirements that the software is intended to address. It can therefore be readily applied across a wide range of development environments and throughout the life of a development project, from early requirements definition to full operational use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Function points

A

.a standard unit of measure that represents the functional size of a software application. In the same way that a house is measured by the square feet it provides, the size of an application can be measured by the number of function points it delivers to the users of the application.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Indirect costs

A

.generally are linked to two features: overhead, and selling and general administration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Learning curves

A

.experience and common sense teach us that repetition of activities often leads to reduction in the time necessary to complete the activity over time. Some research, infact, supports the idea that performance improves by a fixed percentage each time production doubles.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Nonrecurring costs

A

.these costs are associated with charges applied once at the beginning or end of the project, such as preliminary marketing analysis, personnel training, or outplacement services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Normal costs

A

.those costs incurred in the routine process of working to complete the project according to the original, planned schedule agreed to by all project stakeholders at the beginning of the project.

17
Q

Parametric estimation

A

.These are detailed estimates of current projects by taking older work and inserting a multiplier to account for the impact of inflation, labor and materials increases, and other reasonable direct costs.

18
Q

Project budget

A

.a plan that identifies the allocated resources, the project’s goals, and the schedule that allows an organization to achieve those goals.

19
Q

Recurring costs

A

.these costs typically continue to operate over the project’s life cycle. Most labor, material, logistics, and sales costs are considered this because some budgetary charge is applied against them throughout significant portions of the project development cycle.

20
Q

Time-phased budget

A

.This budget allocates costs across both project activities and the anticipated time in which the budget is to be expended. It allows the project team to match its schedule baseline with a budget baseline, identifying milestones for both schedule performance and project expense.

21
Q

Top-down budgeting

A

.This budget requires the direct input from the organization’s top management; in essence, this approach seeks to first ascertain the opinions and experiences of top management regarding estimated project costs.

22
Q

Variable costs

A

.These costs accelerate or increase through usage; that is, the cost is in direct proportion to the usage level.