Planning Sequence Before Flashcards

1
Q

What comes before estimate time and cost?

A

estimate resource requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What comes before gain formal approval of the plan?

A

develop realistic and final PM plan and performance measurement baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What comes before create network diagram?

A

create activity list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What comes before determine all roles and responsibilities?

A

create process improvement plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What comes before develop budget?

A

develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What comes before develop schedule?

A

determine critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What comes before hold kickoff meeting?

A

gain formal approval of the plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What comes before create change management plan?

A

finalize procurement documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What comes before create WBS and WBS dictionary?

A

determine planning team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What comes before create process improvement plan?

A

determine quality standards, processes, and metrics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What comes before assess what to purchase and create procurement documents?

A

create project scope statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What comes before finalize the “how to execute and control” parts of all management plans?

A

create change management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What comes before create project scope statement?

A

determine detailed requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What comes before determine detailed requirements?

A

determine how you will plan for each knowledge area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What comes before develop realistic and final PM plan and performance measurement baseline?

A

finalize the “how to execute and control” parts of all management plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What comes before estimate resource requirements?

A

create network diagram

17
Q

What comes before determine planning team?

A

assess what to purchase and create procurement documents

18
Q

What comes before determine critical path?

A

estimate time and cost

19
Q

What comes before determine quality standards, processes, and metrics?

A

develop budget

20
Q

What comes before perform risk identification, qualitative and quantitative risk analysis, and risk response planning?

A

plan communications and stakeholder engagements

21
Q

What comes before determine how you will plan for each knowledge area?

A

initiating phase

22
Q

What comes before plan communications and stakeholder engagements?

A

determine all roles and responsibilities

23
Q

What comes before go back - iterations?

A

perform risk identification, qualitative and quantitative risk analysis, and risk response planning

24
Q

What comes before create activity list?

A

create WBS and WBS dictionary

25
Q

What comes before finalize procurement documents?

A

go back - iterations