Planning Sequence Before Flashcards
What comes before estimate time and cost?
estimate resource requirements
What comes before gain formal approval of the plan?
develop realistic and final PM plan and performance measurement baseline
What comes before create network diagram?
create activity list
What comes before determine all roles and responsibilities?
create process improvement plan
What comes before develop budget?
develop schedule
What comes before develop schedule?
determine critical path
What comes before hold kickoff meeting?
gain formal approval of the plan
What comes before create change management plan?
finalize procurement documents
What comes before create WBS and WBS dictionary?
determine planning team
What comes before create process improvement plan?
determine quality standards, processes, and metrics
What comes before assess what to purchase and create procurement documents?
create project scope statement
What comes before finalize the “how to execute and control” parts of all management plans?
create change management plan
What comes before create project scope statement?
determine detailed requirements
What comes before determine detailed requirements?
determine how you will plan for each knowledge area
What comes before develop realistic and final PM plan and performance measurement baseline?
finalize the “how to execute and control” parts of all management plans
What comes before estimate resource requirements?
create network diagram
What comes before determine planning team?
assess what to purchase and create procurement documents
What comes before determine critical path?
estimate time and cost
What comes before determine quality standards, processes, and metrics?
develop budget
What comes before perform risk identification, qualitative and quantitative risk analysis, and risk response planning?
plan communications and stakeholder engagements
What comes before determine how you will plan for each knowledge area?
initiating phase
What comes before plan communications and stakeholder engagements?
determine all roles and responsibilities
What comes before go back - iterations?
perform risk identification, qualitative and quantitative risk analysis, and risk response planning
What comes before create activity list?
create WBS and WBS dictionary
What comes before finalize procurement documents?
go back - iterations