Planning and Legal & Regulatory Compliance Flashcards
What is development?
Defined in Section 55 of the Town and Country Planning Act 1990 as the carrying out of building or other operations in, on, over or under land, or the making of any material change of use of any buildings or other land.
What is planning?
The control of development by a local authority.
What is the key legislation?
Town and Country Planning Act 1990
Planning and Compulsory Purchase Act 2004 – states that proposals should be assessed against adopted strategic plans
Localism Act 2011 - places emphasis on planning at a local level or ‘bottom up’ planning, and gives neighbourhood groups the right to create Neighbourhood Plans
What planning policy framework do we work under?
The National Planning Policy Framework was adopted in 2019. This is supported by the NPPG, an online guidance tool.
What does the NPPF define sustainable development as?
Positive growth which makes economic, environmental and social progress for this and future generations.
Does demolition require planning consent?
No unless its in a conservation area or is a listed building.
What are permitted development rights?
Permitted development rights allows certain development to be carried out without the need to acquire formal planning consent, subject to certain conditions and the requirements being met.
What are the requirements of office to residential PD rights?
Office to residential PD rights are detailed under Class O of the General Permitted Development Order as amended 2015. These apply only if:
• The building is used as B1(a) offices as of 29th May 2013
• The site is not in a safety hazard area
• Isn’t a listed building
What does prior approval mean?
You have to apply to the LA for determination as to whether prior approval from the Local Authority is required in regards to transport and highways impacts, contamination risks and flood risk.
How do you apply for prior approval?
For Carnwath Road, I submitted a Prior Notification form, a site location plan, existing plans, proposed plans and a planning statement to H&F with the application fee of £80. I also submitted a transport impact assessment, flood risk assessment and contamination assessment. H&F assessed the application to determine whether prior approval was required, and then whether prior approval was given or refused.
If the site is within Flood Risk Zone 2 or 3, will prior approval always be refused?
No but the site would require a flood risk assessment. If the risks were found to be unacceptable than prior approval would be refused.
How long does the LA have to determine whether prior approval is required?
8 weeks. 13 weeks for larger application and 16 weeks if there is an EIA
What can you do to a listed building without listed building consent?
I would always advise my client to seek specialist advice before undertaking any works to a listed building, however they may be able to undertake minor repair works on a like for like basis without consent
What weight would you give to an emerging policy?
Any emerging policy would be a material consideration when considering a development proposal, however the weight I would give to it would depend on the stage of its preparation. For example, if a draft local plan was in the examination stages I would give it more weight than if it was just at the preferred options stage of consultation.
What is the importance and relevance of SHLAAs?
SHLAAs identify the borough’s capacity to meet identified housing need. If a borough can not demonstrate that it has a sufficient five year land supply then developer’s have a stronger case for bringing forward sites that would otherwise not be considered for development.
How do LA’s produce a SHLAA?
- Desktop review of existing information
- Determine which areas and site should be surveyed
- Carry out a survey of potential sites
- Estimate the housing potential of each site and when and whether sites are likely to be developed
- Review the assessment
- Identify the housing potential of windfall
- Use this assessment to inform the five year land supply of deliverable sites
- Should be monitored and updated annually
What is the definition of a greenbelt?
Land which is safeguarded in order to prevent urban sprawl by keeping the land permanently open.
What could you do if a LA did not determine your application?
I would advise my client to appeal after the statutory period of 8 weeks, but within 6 months.
What is a S106 agreement?
A legal agreement setting out the contributions a developer will provide in order to offset the negative impacts caused by their development. Obligations must be necessary, directly related and reasonable.