Plan Cost Management Flashcards

Planning

1
Q

What is the purpose of the Plan Cost Management process?

A

To establish policies, procedures, and documentation for planning, managing, expending, and controlling project costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is contained the Cost Management Plan?

A

Units of Measure, Level of Precision, Level of Accuracy, Organizational Procedures Links, Control Thresholds, Rules of Performance Measurements, Reporting Formats, Process Descriptions, Additional Details

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the inputs to Plan Cost Management?

A

Project Mgmt Plan, Project Charter, EEOs, OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who should create the Cost Management Plan?

A

Project Team, in consultation with company financial experts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly