Determine Budget Flashcards

Planning

1
Q

What is the purpose of the Determine Budget process?

A

To aggregate the estimated costs of individual activities or Work Packages to establish an authorized Cost Baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which document would best assist you in performing Cost Aggregation?

A

Cost estimates are aggregated by Work Packages in accordance with the WBS, then aggregated for the higher component levels of the WBS and ultimately for the entire project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Where are Contingency Reserves and Management Reserves added?

A

Contingency Reserves are added to Work Package cost estimates whereas Management Reserves are added to the Cost Baseline to produce the project budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are aggregated in the Control Accounts?

A

The Work Package costs estimates, along with any Contingency Reserves estimated for Work Packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the Cost Baseline?

A

The approved version of the budget, excluding Management Reserves.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Funding Limit Reconciliation?

A

Variances between funding limits and planned expenditures may necessitate re-scheduling work. i.e. Quarterly budgets.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly