Control Costs Flashcards
Monitoring & Controlling
What is the purpose of the Control Costs process?
To monitor the status of the project, to update project budget and manage changes to the cost baseline.
What are the outputs of Control Costs Process?
1) Work Performance Information, 2) Change Requests, 3) Costs Forecasts, 4) Project Mgmt Plan Updates, 5) Project Document Updates, 6) OPA Updates
What are the tools and techniques to Control Costs?
1) Earned Value Mgmt, 2) Costs Forecasts, 3) To-complete Performance Index (TCPI), 4) Performance Reviews, 5) Project Mgmt Software, 6) Reserve Analysis
What is Earned Value Management (EVM)?
Methodology that combines scope, schedule, and resource measurements to assess project and progress. The difference between Planned Value and Earned Value.
What is Planned Value (PV)?
The authorized budget assigned to scheduled work which does not include Management Reserve.
What is Budget at Completion (BAC)?
The total Plan Value for the project.
What is Earned Value (EV)?
Measure of work performed expressed in terms of the budget authorized for that work which is used to calculate the percentage complete of a project.
What is Actual Costs (AC)?
Costs incurred for the work performed on an activity during a specific time period.
What is Estimate of Completion (EAC)?
Expected total cost (forecast) at the end.
What is Estimate to Complete (ETC)?
Expected remaining costs (now until end).
What is Variance of Completion (VAC)?
Expected variance over/under budget.
What is Cost Management Plan?
Plan that describes how costs will be planned, structured and controlled.
How do you calculate Cost Variance (CV)?
EV - AC = CV (Negative bad, Positive good)
How do you calculate Schedule Variance (SV)?
EV - PV = SV (Negative bad, Positive good)
How do you calculate Cost Performance Index (CPI)?
EV / AC = CPI (Under 1 is bad, Over 1 is good)