Control Costs Flashcards

Monitoring & Controlling

1
Q

What is the purpose of the Control Costs process?

A

To monitor the status of the project, to update project budget and manage changes to the cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the outputs of Control Costs Process?

A

1) Work Performance Information, 2) Change Requests, 3) Costs Forecasts, 4) Project Mgmt Plan Updates, 5) Project Document Updates, 6) OPA Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the tools and techniques to Control Costs?

A

1) Earned Value Mgmt, 2) Costs Forecasts, 3) To-complete Performance Index (TCPI), 4) Performance Reviews, 5) Project Mgmt Software, 6) Reserve Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Earned Value Management (EVM)?

A

Methodology that combines scope, schedule, and resource measurements to assess project and progress. The difference between Planned Value and Earned Value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Planned Value (PV)?

A

The authorized budget assigned to scheduled work which does not include Management Reserve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Budget at Completion (BAC)?

A

The total Plan Value for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Earned Value (EV)?

A

Measure of work performed expressed in terms of the budget authorized for that work which is used to calculate the percentage complete of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Actual Costs (AC)?

A

Costs incurred for the work performed on an activity during a specific time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Estimate of Completion (EAC)?

A

Expected total cost (forecast) at the end.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Estimate to Complete (ETC)?

A

Expected remaining costs (now until end).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Variance of Completion (VAC)?

A

Expected variance over/under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Cost Management Plan?

A

Plan that describes how costs will be planned, structured and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you calculate Cost Variance (CV)?

A

EV - AC = CV (Negative bad, Positive good)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you calculate Schedule Variance (SV)?

A

EV - PV = SV (Negative bad, Positive good)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you calculate Cost Performance Index (CPI)?

A

EV / AC = CPI (Under 1 is bad, Over 1 is good)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you calculate Schedule Performance Index (SPI)?

A

EV / PV = SPI (Under 1 is bad, Over 1 is good)

17
Q

How do you calculate Estimate to Complete (ETC)?

A

EAC - AC = ETC (Value of work remaining)

18
Q

How do you calculate Variance at Completion (VAC)?

A

BAC - EAC = VAC (Negative is bad, Positive is good)

19
Q

How do you calculate to Complete Performance Index (TCPI) within budget?

A

(BAC - EV) / (BAC - AC) = TCPI (Use 80% of time)

20
Q

How do you calculate to Complete Performance Index (TCPI) outside of budget?

A

(BAC - EV) / (EAC - AC) = TCPI (Use if original budget is not possible)

21
Q

How do you calculate Estimate at Completion (EAC) with atypical variance (not continue or budget rate)?

A

AC + (BAC - EV) = EAC (Actual cost plus work remaining, is not based on past performance)

22
Q

How do you calculate Estimate at Completion (EAC) with typical variance?

A

BAC / CPI = EAC (Use this calculation if project is on track, is based on past performance)

23
Q

How do you calculate Estimate at Completion (EAC) with assume poor performance but need to hit firm completion date?

A

AC + [(BAC - EV) / (CPI * SPI)] = EAC

24
Q

What is To Complete Performance Index (TCPI)?

A

A measure of cost performance that is acquired to be achieved with the remaining resources in order to meet a specified management goal.