PjM_PPI Flashcards

1
Q

labor and materials bond payment bond

A

A bond carried by the contractor and the contractor’s surety promising that payment will be provided to the subcontractors and suppliers for labor and materials used in the project. A means to prevent a mechanic’s lien from being placed on the project property.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

elemental method

A

Systems and assemblies cost estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

bidding documents

A

Documents produced by the design team—including documents required by the owner for the construction contract—that allow contractors to produce cost estimations and bid their fee for construction. The bidding documents include, for example,

bid form
contract form
contract conditions
bond requirements
general and supplementary conditions
specifications
construction drawings
addenda

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

bid bond bid security

A

A type of insurance that the bidding contractor provides ensuring they will enter into contract with the owner. This protects the owner from selecting a winning bid that will not be executed, putting them at risk for wasted time or increased bids in a second round of bidding. Also protects owner from a contractor placing low, unrealistic bids to successfully execute the project, and against contractors bidding on too many projects at once, winning more than they can execute, and not accepting the project after winning the bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

supplementary conditions

A

A portion of the contract documents that may add to, modify, or change the general conditions of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

unit rate method

A

Pricing of a project or portion of a project by providing a cost per area, volume, or other single-unit rate method, such as a hotel project being priced on cost per room.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

unit price contract

A

A contract based on the acceptance of the unit price quote given for various portions of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

general conditions

A

The portion of the contract documents where the rights, responsibilities, and relationships of the parties are outlined, as well as the overall expectation of the execution and delivery of the work. Often includes boilerplate terms that are common to most construction projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

project manual

A

A collection of documents required for the construction work, often including (drawings are not included)

‐ bidding requirements, (instructions to bidders)
- contract forms,
- general and supplementary conditions
- specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

progress payments

A

In response to the contractor’s application for payment, the architect approves portions of the work completed to allow payment to the contractor for materials and work performed to date. The contract specifies the period for which “progress” will be addressed for payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

labor and materials bond payment bond

A

A bond carried by the contractor and the contractor’s surety promising that payment will be provided to the subcontractors and suppliers for labor and materials used in the project. A means to prevent a mechanic’s lien from being placed on the project property.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

procurement documents

A

The documents used to obtain pricing from prospective contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

procurement

A

The transition from the design stage to the construction stage of a project. Involves the bidding, negotiating, and purchasing phases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

bid shopping

A

The practice of revealing the sub-bid of one subcontractor to obtain a lower price from another subcontractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

design negotiate build

A

The owner and contractor negotiate a construction contract in order to achieve mutual benefit and avoid the inherent risks of competitive bidding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

supplementary conditions

A

A portion of the contract documents that may add to, modify, or change the general conditions of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

basic service

A

The architectural services normally required for a building project, usually consisting of

schematic design,
design development,
construction documents,
bidding or negotiation,
construction contract administration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What two types of services does AIA Document B101allow the architect and owner to agree on and contract for?

A

The architect’s basic services, and additional services such as programming and land-use studies can be contracted by these two parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What four methods are commonly used to determine the compensation for the architect?

A

These four methods are
- stipulated sum
- cost plus fee
- hourly billing rates
- percentage of construction cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Who does the legal concept of agency involve?

A

This legal relationship involves three parties.
- principal
- agent, who has been authorized by the principal to act on the principal’s behalf
- third party, who enters into a contract with the principal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is a stipulated or lump-sum contract?

A

This kind of contract calls for a project to be delivered for a set price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are liquidated damages?

A

This is money paid to the owner by the contractor for every day the project is late, as stipulated in the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What type of bonds must contractor purchase as stated in AIA Document A101-2017?

A

This party must carry surety bonds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Who is protected against third-party claims in the standard owner-architect agreement?

A

Both parties are protected against third-party claims in this agreement, AIA Document B101–2017, to the extent damages are covered by property insurance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

If the owner fails to make progress payments to the contractor, what remedies may the contractor seek?

A

The contractor may request in writing that the owner show reasonable evidence that financial arrangements have been made to fulfill this obligation if this event happens.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

If liquidated damages are asked for in the contract, what
provision must also be added?

A

A bonus provision must be added to make this provision enforceable in the courts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Why does a sustainable project require a special owner-architect agreement?

A

This type of contract includes a sustainable objective set by the owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What documents and services must the owner provide to the architect?

A

The owner must provide to this person the project program, schedule, and budget, and furnish a property survey, a geotechnical report, tests and inspections, and required insurance, legal, and accounting services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

With what phase of an owner-architect agreement would closeout documents be associated?

A

These documents are reviewed by the architect at the end of the project, before final payment is made by the owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Who pays for permits after the construction contract is executed?

A

The contractor must pay for the permits after this document is signed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What two responsibilities does the owner assume if he or she elects to perform some of the work with his or her own forces?

A

The owner must coordinate the work of his or her forces with the contractor’s work, and must act with the same rights and responsibilities as any other contractor in this situation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What are two reasons a change order may be executed?

A

This is executed by the architect when unforeseen site conditions arise or the owner changes the scope of the work. Other reasons include time extensions due to weather or omissions of the architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Name the phases included in the owner-architect basic services agreement for a design-bid-build project.

A

The phases listed in this agreement are

schematic design,
design development,
construction documents,
bidding,
construction administration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

scope creep

A

The gradual inclusion of work into the project that exceeds the contracted work agreement and the original project requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

punch list

A

A list typically generated by the architect during a field survey at the end of the project, including items or work that does not conform to the contract documents or quality expectation as specified in the contract documents. Per the AIA Document B101, Owner-Architect Agreement, this is a basic service of the architect. Work must be completed or corrected by the contractor by the date issued in the architect’s certificate of substantial completion, or final payment is withheld.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

building permit

A

Document of permission by the government authority having jurisdiction to conduct construction, as approved in the construction documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

phasing

A

Portions of work are set aside to commence after other portions of work have been completed. Among other reasons, this allows for building use during construction or for the owner to secure funding in portions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

design development

A

The third phase of design work after programming and schematic design. Design development shows the integration of preliminary building systems designs and fully develops the design of floor plans and elevations. Owner final approval of design is often achieved at the end of design development.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

schematic design

A
  • A preliminary level of design; the second phase of design work, after programming, that gives form, shape, and itinerary to the project program.
  • Schematic level design should suggest overall building dimensions, footprint and profile, locations of building core items, egress, and preliminary floor plans.
  • Preliminary coordination regarding code compliance strategies should take place between the architect and consultants during the schematic design phase of a design-bid-build or design-build project.
  • Communicating during this phase gives the engineer enough information about the proposed layout of the building, the construction type, anticipated occupant loads, exit paths, and fire ratings so that the engineer can evaluate options, suggest an appropriate system, and begin to incorporate the elements of that system into the initial design
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

shop drawings

A

Drawings issued by a vendor to the contractor demonstrating the details and connections of components they will be fabricating for a project. The architect should review these drawings for conflicts and design consistency, but ultimately, the contractor signs as approved or rejected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

construction drawings

A

The set of drawings produced, signed, and sealed by the architect and consultant team that serve as the graphical component to the project’s contract documents. Also, the design phase following design development, where specifications and details are added to the work to produce a design capable of construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

direct liability (vicarious liability) vs contingent liability

A
  • direct liability / Vicarious liability : an architect’s liability for their own acts is known as direct liability for their employee’s’ acts is known as vicarious liability.
  • contingent liability : refers to the architect’s liability for the acts of independent consultants who are retained to perform professional services such as consulting engineers.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

RFI

A

A formal request by the contractor to the architect for more information or clarification to the contract drawings. The response from the architect may add more work or cost to the project or may require a design change, all of which may warrant a proposal request and construction change directive from the architect, and eventually, a change order from the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

submittals

A

A formal request by a material or labor provider for the contractor or professional consultant to review the proposed material or equipment for the project, according to the corresponding written specification. The architect must indicate his acceptance of the submittal as conforming to the contract documents for use in the project. All submittals must be responded to as approved, rejected, or revised and resubmitted. The contractor is responsible for this, but seeks confirmation from the design team prior to doing so.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

payment bond

A

A bond carried by the contractor and the contractor’s surety promising that payment will be provided to the subcontractors and suppliers for labor and materials used in the project. A means to prevent a mechanic’s lien from being placed on the project property.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

final payment

A

Payment made to the contractor once the architect has issued the final certificate for payment of the entire unpaid balance of the project, including adjustments for change orders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

final completion

A

The completion of work based on the requirements and procedures specified in the contract and in the general conditions of the contract. Unlike substantial completion, there is not typically a given date for final completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

substantial completion

A

The required date by which the building or project must be able to be used for its intended purpose.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

abatement

A

The containment and removal of existing contaminants in the built environment, often during demolition for renovation. The owner must coordinate these services outside of the construction contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

to ensure quality

A
  • self-checking (check-list) by team members (producer)
  • in-house third party review : by experienced collogues which occurs every after major project phase
  • peer reviews : by independent outside consultant sometimes required by states for building permit
  • BIM
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

post-construction services

A
  • post-occupancy evaluations (basic)
  • building commissioning (basic)
  • energy analysis and monitoring
  • space scheduling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Project manager

A

Term used to describe the professional responsible for the oversight and delivery of their discipline of professional work or services, typically having administrative and technical responsibilities to the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

specifications

A

A portion of the contract documents that formally list the written requirements for equipment, performance, quality, standard of workmanship, building materials, and construction systems. Are included in the project manual.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Partnering

A

The concept of teamwork or team-building to help ensure cooperative efforts and proactive solutions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

milestone dates

A

Significant dates involving the establishment of starting and finishing time frames for activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Lead time

A

The amount of time required from receipt of purchase order by a seller to the time the product is delivered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

FOB

A

Free on board: factory, freight, prepaid to the job site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

commissioning authority

A

An independent entity engaged to verify the quality of the project in relation to the owner’s project requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

commissioning

A

Documented confirmation that building systems function according to criteria set forth in the project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

facility management

A

The phase in the life cycle of a facility when the completed facility is placed into service. Includes operations and maintenance procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

facility life cycle

A

The sequence of activities, from project concept and construction, to use and eventual demolition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

life cycle costing

A

The process of evaluating a building or product based on the total costs attributed to that object during its lifetime. These costs include the initial costs, operating costs, maintenance costs, demolition costs, and credit for any residual or salvage value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

payback period

A

The amount of time required to recover the cost of a purchase through increased performance and efficiencies or reduced operating costs and expenses. Payback periods are commonly used to evaluate the potentially higher initial costs of high-efficiency energy systems. The shorter the payback period, the more economical the purchase would be.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

contingency allowance

A

An amount included in a construction budget—normally 5%–10%—to provide for unforeseen or unpredictable costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

value engineering

A

The systematic review of a project design to obtain the best value for the money spent, considering first costs, operating costs, and replacement costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

critical path method (CPM)

A

A system of planning and scheduling construction operations that analyzes sequences and durations of time using network diagrams.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

fast-track

A

A construction procedure in which construction on each phase of a project begins as its design is completed, without waiting for the completed project design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

construction drawings (CDs)

A

The set of drawings produced, signed, and sealed by the architect and consultant team that serve as the graphical component to the project’s contract documents. Also, the design phase following design development, where specifications and details are added to the work to produce a design capable of construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

lump sum agreement (stipulated sum agreement)

A

A specific amount is initially specified in the contract as the total fee for the project work, including materials, labor, and profit. Cost savings go directly to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

observation report

A

Documentation of an architect’s survey of work progress and quality and affirming work is being conducted in accordance with the contract documents. Often supports the architect’s understanding of acceptable work progress for approval of the contractor’s application for payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

warranty

A

An assurance of quality for a duration or period of time after project completion or substantial completion, and legally enforceable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

associations, societies, councils, and institutes

A

Organizations that have a vested interest in the existence of a common language, understanding, beliefs, and standards of care within their respective industries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Spearin doctrine

A

A 1918 court decision stating that a contractor is entitled to rely on the construction documents provided by the owner to be sufficient for their intended purpose and is not responsible for the consequences of defects in the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

What are the four treatment categories cited in “Standards for the Treatment of Historic Properties,” published by the Secretary of the Interior in 1992?

A

These categories are

preservation
rehabilitation
restoration
reconstruction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Name three documents from the closeout phase that should be incorporated into project files.

A

Three key documents from this phase are
- the punch list,
- the certificate of substantial completion, and
- the final application and certificate for payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

How is corporate knowledge documented?

A

Standards details,
general notes, and
checklists are three examples of this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

What is a quality circle?

A

This is a small group of employees who meet regularly to identify, analyze, and solve problems for the quality control (QC) program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

What aspect of the firm should be considered before establishing a quality control program?

A

The type of services offered by the firm is critical to this program. An architectural engineering firm will have different needs than an architecture or interiors firm.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

What is the role of top firm management in a quality control program?

A

These firm members must publicly support and encourage a quality control program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Name three appropriate methods for communicating project information.

A

-Telephone conversations,
- a project website, and emails
- paper documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

What method of communication should not be used for project information?

A

This aspect of quality control should not use social media.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

What is the reason project files are created and stored after a project is completed?

A

These are kept by the firm to reduce risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

What are the two types of project documentation used in a project?

A

These types are

  • construction documents
  • contracts, change orders, and shop drawing logs based on standard forms
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

At what point is a project reviewed against the requirements of the building code?

A

This review takes place at every phase during the planning, design, and construction of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

Name two ways an architect can maintain a professional standard of practice.

A

This practice includes using
- accepted details of trade associations
- specification standards
.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

What is quality control?

A

This is an organized set of procedures, systems, and tools to meet the expectations of the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

Name two elements of a high-quality control program?

A
  • Checklists
  • adherence to the approved program
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

tax abatement

A

A reduction of taxes granted by a government to encourage economic development.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

field survey

A

An evaluation of the conditions at the site, either before, during, or after work is performed, to assess work progress, analyze existing conditions, or review the work for a punch list. An observation report is typically generated after the survey to document observations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

bulletin

A

Changes to the documents after bidding and before a construction contract is awarded; changes to the documents are referred to as post-bid bulletins.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

program management

A

The process of managing large private and public projects—most specifically, the criteria of the project’s needs regarding spaces, accommodations, and adjacencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

clash detection

A

The utilization of computer programs that coordinate project BIM to detect conflicts in the design between buildings systems, for resolution prior to issuing construction drawings. Often performed later in design development or construction drawings design phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

value-enhanced design value engineering

A

The process of reviewing the design components and evaluating options for cost savings or value substitutions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

cost plus fee

A

The project has a budget of actual cost of materials and labor plus a set fee, often a percentage of the overall cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

construction manager

A

A contractor consultant who offers technical guidance and cost-estimating advice and direction for the project early in the design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

construction schedule

A

A timeline for construction, which includes estimated start dates and end dates for construction processes, as well as lead times and deadlines for major milestones. Often represented in a Gantt chart.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

pull planning session card session

A

A charette of project delivery where all teams and professionals involved in the effective delivery of a project coordinate the timeline for project deliverables based on the anticipated project completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

BIM execution plan

A

A formal document specifying the policies and procedures for managing the building information modeling for the project, including level of detail or level of design for the model, and processing each subconsultant in coordinating models together. May be generated by an owner on a large project or by the design team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

architect’s supplemental instruction (ASI)

A
  • Architect’s supplemental instructions (ASI): a formal issuance of additional information to clarify the construction drawings, made independent of a request from the contractor.
  • this is when there is no change for time and cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

turnkey

A

A real estate development project that is fully complete, ready for intended use, or already in operation upon delivery to a future owner. A method for allowing designer, developer, or contractor to have total control over the design, as well as construction methods and materials, without obligation to an owner or users’ preferences. Often allows for greater profits to the design, development, or construction team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

integrated project delivery

A

A project delivery approach to optimize project results and improve efficiency that integrates people, systems, business structures, and practices into a collaborative process that maximizes the talents, insights, and strengths of all participants.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

NIOSH

A

National Institute for Occupational Safety and Health

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

program manager

A

A consultant representing the owner in developing and coordinating the criteria for a project regarding spaces, accommodations, and adjacencies throughout a project. Best to be included on the project team at the beginning of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

EJCDC

A

Engineers Joint Contract Documents Committee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

AGC

A

Associated General Contractors of America.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

ASHRAE 90.1

A

A standard that provides minimum requirements for the energy-efficient design of buildings, except for low-rise residential buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

SMACNA

A

Sheet Metal & Air Conditioning Contractors’ National Association.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

NFPA

A

National Fire Protection Association

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

NEC

A

National Electrical Code.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

IPC

A

International Plumbing Code.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

IMC

A

International Mechanical Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

IFC

A

International Fire Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

IECC

A

International Energy Conservation Code.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

IEBC

A

International Existing Building Code.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

ICC

A

International Code Council

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

ASTM

A

American Society for Testing and Materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Contemporaneous documentation

A

Contemporaneous documentation is a written record of verbal or informal communications which is kept in real time and is generally not issued to other project participants in a standard form

This type of documentation could include the project manager’s daily journal, notes from telephone conversations or conversations on site, or email and text messages. Along with providing a record of the project’s progress and the project manager’s day-to-day activities,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

A hierarchical view of different types of work plans

A
  • Strategic, tactical, and operational plans can be used to organize and schedule a design project.
  • A contingency plan allows the project team to address unforeseen issues that may arise during the course of a project.
  • The firm principal or project architect takes the information from a strategic plan and uses it to develop a tactical plan, which is a list and schedule of the activities that must occur to accomplish the goals defined in the strategic plan.
  • What architects generally call a project work plan is a type of tactical plan. This plan includes assigning responsibility for each task (i.e., to in-house staff or consultants), determining how much time and money is allocated for each task, and charting when tasks must be completed to keep the project on schedule, including deadlines or submission requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

tactical plan

A
  • A tactical plan has a level of detail that falls in between a strategic plan and an operational plan. For example, a tactical plan lists “structural design by consultant” and may list review milestones or submission dates, but it does not break this topic into very specific tasks.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

operational plan

A
  • An operational plan is used by a designer or project manager who is responsible for a smaller part of the project. In a design project, an operational plan may be implemented through a responsibilities matrix or a task checklist. For example, a structural engineer may develop an operational plan that includes a list of the activities that the firm must complete to develop the design of the structural systems. The structural engineer begins by analyzing and applying the requirements and schedule defined in the architect’s work plan. The engineer then lists the required engineering tasks, which may include receiving and reviewing the geotechnical report, choosing and designing the foundation system, completing wind and seismic loading analysis, selecting a material and calculating reactions for the structural frame, coordinating with the architect and other building systems engineers as their portions of the design are developed, and preparing the final documents and specifications.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

contingency plan

A
  • A contingency plan is a way to rescue a troubled project, proposed in advance of a project being in trouble. Issues may arise for a variety of reasons but are usually attributable to a lack of time, money, or resources. A project may also encounter unforeseen issues or conditions related to the site, a delay in the approvals process, a change in the owner’s direction or available resources, or a delay caused by a natural disaster. A contingency plan helps the architect respond to these issues quickly and thoughtfully. For example, a zoning approval board meeting is canceled because of a snowstorm, and the project does not receive land development plan approval until the next month. The design and construction schedules for the project may be adjusted to factor in this extra time. The architect may allow for these types of unforeseen conditions by including a design contingency in the project budget (e.g., usually 5−10%, determined by the architect), encouraging the owner to include a contingency in the construction budget (e.g., usually 5−10%, determined by the owner), and building extra time into the design and construction schedule.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

strategic plan

A
  • A strategic plan is a high-level plan that outlines broadscope project objectives. One example of a strategic plan is the program for an architectural project. The owner, with the assistance of a programmer or the architect, prepares the program. The architect becomes familiar with the requirements and determines both the design approach and the production plan to satisfy the program.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

American Institute of Architects (AIA) Document A305, Contractor’s Qualification Statement, includes

A
  • This document contains sections on organization, licensing, experience, references, financing, and signature. The section on financing requires that the contractor
  • “attach a financial statement, preferably audited, including your organization’s latest balance sheet and income statement.” Nowhere in these sections does it provide for a personal narrative, a list of potential subcontractors, or a list of materials on hand.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

Two major issues should be addressed in every agreement between an architect and a consultant:

A
  • passing through rights and responsibilities of the architect to the consultant,
  • and sharing risks and rewards.
  • The agreement should also establish responsibilities such as compensation, internal coordination, revisions on request of the architect, cost estimating, assistance with the bidding process, review of shop drawings, and site visits.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

A101 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
article 1 : The Contract Documents

A
  • This agreement
  • Conditions of the contract (general, supplementary, and others)
  • Drawings
  • Specifications
  • Addenda issued prior to this agreement
  • Other documents listed in this agreement
  • Modifications issued after this agreement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

A101 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
article 2 : The Work of this Contract

A
  • The contractor shall fully execute the work as described in the contract documents
    : Exception is if the documents specifically call out another entity to perform any work described
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

A101 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
article 3 : Date of Commencement and Substantial Completion

A
  • Defines date of commencement of the work
    — If no date is selected or called out, the date of commencement is the date of the contract
    — Contract time is measured from the date of commencement
  • Substantial completion date is defined
    — Can also define portions of the work to be substantially complete before overall
    substantial completion
128
Q

A10 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
article 4 : Contract Sum

A
  • Defines contract sum for the contractor to be paid
    – Subject to additions and deductions based on the contract documents
  • Defines any alternates, unit prices, allowances, and liquidated damages
  • Defines any bonuses or other special incentives for the contractor
129
Q

A101 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
article 5 : payments

A
  • Progress Payments
    — Contractor submits application for payments to the architect
    — Progress payment based on schedule of values and percentage of work completed
    — Owner can withhold retainage in each progress payment as defined in the contract
  • Final Payment
    — Contractor has fully performed the work of the contract
    — Final certificate for payment has been issued to the architect
  • Interest can be applied to payments due but unpaid
130
Q

A101 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
article 6 : Dispute Resolution

A
  • Initial decision maker is generally the architect unless otherwise defined in the agreement
  • Method of binding resolution if decision cannot be made by mediation is defined
    Arbitration
    Litigation
    Other
131
Q

A101 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
article 7 : Termination or Suspension

A
  • Contract may be terminated by the owner or contractor as provided in A201
  • Termination fees are defined if the owner terminates for convenience based on A201
  • Contract may be suspended by the owner based on A201
132
Q

A101 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
article 8 : Miscellaneous Provisions

A
  • Defines owner’s representative
  • Defines contractor’s representative
  • Defines any insurance and bonds based on A 101 Exhibit A
  • Defines any other provisions not defined elsewhere in the agreement
133
Q

A101 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
article 9 : Enumeration of Contract Documents

A
  • Agreement is compromised of the following documents
    — AIA Document AIOI
    — A 101 Exhibit A, Insurance and Bonds
    — AIA Document A201, General Conditions
    — AIA Document E203, BIM and Digital Data Exhibit
    — Drawings
    — Specifications
    — Addenda (if any)
    — Any other exhibits or documents listed
134
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery

When do you use it?
Who is the contract between?

A

— Integrated Project Delivery
— Owner/Architect agreement

135
Q

A101 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

When do you use it?
Who is the contract between?

A

—Project price based on a fixed sum
—Suitable for large or complex commercial projects

—Owner/Contractor agreement

136
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery

A

Article I-Architect’s Servcies and Responsibilities
Article 2-0wner’s Responsibilities
Article 3-Copyright and Licenses
Article 4-Compensation
Article 5-Dispute Resolution
Article 6-Termination or Suspension
Article 7-Miscellaneous Provisions
Article 8-Special Terms and Conditions
Article 9-Scope of the Agreement

137
Q

A101 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

A

Article I-The Contract Documents
Article 2-The Work of the Contract
Article 3-Date of Commencement and Substantial Completion
Article 4-Contract Sum
Article 5-Payments
Article 6-Dispute Resolution
Article 7-Termination or Suspension
Article 8-Miscellaneous Provisions
Article 9-Enumeration of Contract Documents

138
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery
article 1 : Architect’s Services and Responsibilities

A
  • Architect’s Services and Responsibilities
  • Provide professional services set forth in A295
  • Standard of care
  • Architect Insurance
    — General liability
    — Automobile liability
    — Worker’s compensation
    — Professional liability
  • Additional services
139
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery
article 2 : Owner’s Responsibilities

A

Owner’s Responsibilities
* Set forth in A295

140
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery
article 3 : Copyrights and Licenses

A
  • Transmitting party of instruments of service either owns copyright or has permission from
  • owner of instruments of service to transmit them
    Architects and Architect’s consultants are deemed the owners of their instruments of service
  • Owner has a nonexclusive license to use Architect’s Instruments of Service for the project
141
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery
article 4 : Compensation

A
  • Sets forth how the Architect will be compensated
  • Sets forth what additional services are required and how additional services will be
    compensated for
  • Outlines reimbursable expenses
  • Outlines how and when architect will be paid
142
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery
article 5 : Dispute Resolution

A
  • Refer to A295 for dispute resokltion protocol
    — Mediation
    — Arbitration
  • Owner and Arctütect wil commence any claims rising from the contract within legal limits or 10 years of substantial completion of the project
  • If damages are covered by property insurance, all rights are waived except to the
    proceeds provided by that insurance
  • Owner and architect waive consequential damages
143
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery
article 6 : Termination or Suspension

A
  • If the owner does not pay the architect. the architect can suspend work with seven days
  • If the owner suspends the project. the architect shall be paid for all services performed
    prior to the suspension
  • If the owner suspends the project for more than 90 cumulative days at no fault of the
    architect, the architect may terminate with seven days written notice
  • Either party can terminate with seven days notice if the other party is not fulfilling their
    side of the contract
  • Owners right to use instrument of service upon termination are laid out in A295
144
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery
article 7 : Miscellaneous Provisions

A
  • Contract is governed by the law of the place the project is located
  • Terms the agreement have the same meaning as those set forth in A29S
  • All agents, successors assigns. and legal representatives are abound to this agreement
  • unless otherwise required in the agreement. the Architect will have no responsibility for the discovery. presence. removal, handling, or exposure of people on site of hazardous material
  • The architect has the right to take photos of the project and use them for their own
    promotion
145
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery
article 8 : Special Terms Conditions

A

Special Terms Conditions
* Any special terms and conditions that modify the agreement go here

146
Q

AIA Document B195 Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery
article 9 : Scope of Agreement

A
  • The document represents the entire and integrated agreement between the owner and architect and supersedes any and all previous agreements
  • The agreement is compromised of documents more than just B195 and includes
    — A295
    — E201. if required
    — Any other documents also incorporated into the agreement
147
Q

A133 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

A
  • Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum price
    — Owner and construction manager agreement
    — Construction manager as constructor
    — Payment is cost plus with a GMP
  • Types of projects
    Large scale projects
148
Q

A133 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

Document Content

A

Article 1 -Initial Information
Article 2-General Provisions
Article 3-Consturction Manager’s Responsibilities
Article 4-0wner’s Responsibilities
Article 5-Compensation and Payments for Preconstruction Phase Services
Article 6-Compensation for Construction Phase Services
Article 7 -Cost of Work for Construction Phase
Article 8-Discounts, Rebates, and Refunds
Article 9-Subcontractors and Other Agreements
Article 10-Accounting Records
Article 11-Payments for Construction Phase Services
Article 12-Dispute Resolution
Article 13-Terminaton or Suspension
Article 14-Miscellaneous Provisions
Article 1 5-Scope of the Agreement

149
Q

A133 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

Content Highlights

A
  • Two phases of responsibility for Construction Manager
    — Preconstruction phase
    — Construction phase
  • Architect’s Responsibilities
    — Lots of reviewing
    — Procurement schedule, GMP proposal, application for payment, etc.
    — Dispute resolution
    — Initial decision maker, unless otherwise noted
150
Q

A195, Standard Form of Agreement Between Owner and Contractor for Integrated Project Delivery

A

AIA Document A195
* Standard Form Of Agreement Between Owner and Contractor for Integrated Project
Delivery
— Owner and contractor agreement
— Incorporates AIA Document A295 for contractors duties and responsibilities
— Contractor provides Guaranteed Maximum price exhibit
* Types of projects
— Large scale projects
— Integrated project Design delivery

151
Q

A195, Standard Form of Agreement Between Owner and Contractor for Integrated Project Delivery

Document Content

A

Article 1 -The Work of this Contract
Article 2-0wner*s Responsibilities
Article 3-Copyrights and Licenses
Article 4-Compenstation
Article 5-Payments
Article 6-Dispute Resolution
Article 7-Termination or Suspension
Article 8-MisceIIaneous Provisions
Article 9-Special Terms and Conditions
Article 10-Scope of Agreement

152
Q

A195, Standard Form of Agreement Between Owner and Contractor for Integrated Project Delivery

Content Highlights

A
  • Many references to A295-General Conditions for IPD projects
  • Services before and after GMP is established
  • Architect’s Responsibilities
    — Review of applications for payment
    — Dispute resolution
    — Initial decision maker, unless otherwise noted
153
Q

A295, General Conditions of the Contract for Integrated Project Delivery

A
  • General Conditions of the Contract for Integrated Project Delivery
    — General conditions of the contract
    — A195-Standard Form of Agreement Between Owner and
    contractor for IPD
    — B195-Standard Form of Agreement Between Owner and Architect for IPD
    — Referenced and incorporated by other IPD agreements
  • Types of projects
    — Large scale projects
    — Integrated project delivery
154
Q

A295, General Conditions of the Contract for Integrated Project Delivery

Document Content

A

Article 1 -General Provisions
Article 2-0wner
Article 3-Architect
Article 4 -Contracor
Article 5-Conceptualization Phase
Article 6-Criteria Phase
Article 7-Detailed Design Phase
Article 8-lmplementation Documents Phase
Article 9-Construction Phase
Article 10-Closeout Phase
Article Il-Insurance and Bonds
Article 12-Miscellaneous Provisions
Article 13-Claims and Disputes

155
Q

A295, General Conditions of the Contract for Integrated Project Delivery

Content Highlights

A
  • Architect’s Responsibilities
    — Lays out general responsibilities of the Architect
    — Responsibilities for each phase are laid in each phase’s article
    — Must still understand full responsibilities of all parties referenced
  • Phases
    — Criteria Design
    — Detailed Design Phase
    — Implementation Documents Phase
    — Construction Phase
    — Closeout Phase
156
Q

A701, Instructions to Bidders

A

AIA Document A701
- Instructions to Bidders
- When to Use
— Competitive bids are being solicited for the project
— Establishes project needs for the contractor to actually submit a bid

157
Q

A701, Instructions to Bidders

Document Content

A

Article 1 -Definitions
Article 2-Bidder’s Representations
Article 3-Bidding Documents
Article 4-Bidding Procedures
Article 5-Consideration of Bids
Article 6-Post-Bid Information
Article 7-Performance Bond and Payment Bond
Article 8-Enumeration of the Proposed Contract Documents

158
Q

A701, Instructions to Bidders

Content Highlights

A
  • Lays out what is necessary for bidders to submit a potentially successful bid for a project
  • Architect’s Responsibilities
    — Answer requests for clarification or interpretation-7 days prior to bid cutoff
    — Any modifications made by addendum
    — Review any requests for substitutions 10 days prior to bid cutoff
    — Any substitutions issued by addendum
    — Addenda will be issued no later than 4 days prior to submission date of bids
    — Review sub contractors
159
Q

A201, General Conditions of the Contract for Construction

articles

A
  • General provisions
  • Expectations of the Owner, Contractor, Architect, and Subcontractors
  • Construction by Owner or by separate Contractors
    Changes in the work
  • Time, payments & completion
  • Requirements (protection of persons & property, insurance & bonds)
  • Uncovering & correction of work
  • Miscellaneous provisions
  • Legal matters (termination or suspension of the contract, claims & disputes)
160
Q

A201, General Conditions of the Contract for Construction

provisions

A
  • Components of the Contract Documents
  • Applicable definitions and relevant information for interpreting the agreement
  • Intent of the Contract Documents
  • Ownership of drawings, specifications, and other instruments of service
  • Data use, reproduction, and transmission
  • Building Information Modeling (BIM) use and reliance
161
Q

A201, General Conditions of the Contract for Construction

The next article outlines the expectations of the Owner. This section includes information regarding the
following matters:

A
  • Evidence of the Owner’s financial arrangements
  • Project expenses that are the Owner’s direct responsibility
  • Requirements of the Owner to hire a lawfully practicing architect or architecture firm
  • The Owner’s obligation to provide Contract Documents, a site survey, and other relevant information to the Contractor
  • The Owner’s right to stop the work
  • The Owner’s right to carry out the work
162
Q

A201, General Conditions of the Contract for Construction

The next article outlines the expectations of the Architect. This section includes information regarding the
following matters:

A
  • The responsibility of the Architect to provide administration of the contract
  • Expectations of the Architect to make regular site visits
  • The extent of the Architect’s role in the construction process
  • The responsibility of the Architect to keep the Owner reasonably informed
  • Standards for communication among the project team
  • The process of approving the Contractor’s applications for payment
  • The Architect’s authority to reject non-conforming work
  • The review and approval process for submittals
  • The Architect’s responsibility to handle change orders and construction change directives
  • Conflict resolution processes
  • The Architect’s obligation to respond to requests for information (RFI) regarding the Contract Documents
163
Q

A201, General Conditions of the Contract for Construction

The next article outlines the expectations of the Subcontractors. This section includes information regarding the following matters:

A
  • The process for awarding subcontracts and other contracts for portions of the work
  • Sub contractual relations
  • The contingent assignment of subcontracts
164
Q

A201, General Conditions of the Contract for Construction

The remaining articles outline processes and standards involving the project. These sections include
information pertaining the following matters:

A
  • The Owner’s right to perform construction and award separate contracts
  • Changes in the work, such as change orders, construction change directives, or minor changes
  • Time, in relation to progress and completion as well as delays and extensions
  • Payments and completion, including the contract sum, schedule of values, applications for payment,
    certificates for payment, decisions to withhold certification, progress payments, failure of payment, substantial
    completion, partial occupancy or use, and final completion & payment
  • Protection of persons and property, in relation to site safety, injury, and hazardous materials
  • Insurance and bond regulations
  • The uncovering and correction of work, both before ond after substantial completion
  • Termination or suspension of the contract
  • Claims & disputes and conflict resolution processes, including the Architect’s role as the initial decision maker
165
Q

cost estimate method per phase

A
  • During pre-planning phase or proposal writing, estimates are based on unit costs (cost per person, per bed, etc.)
  • During programming, estimates are based on cost per square foot of recently constructed comparable spaces.
  • During schematic design, estimates are based on building systems (budgets for the scopes of mechanical, electrical, plumbing, etc.)
  • During design development, estimates are based on components (estimated allotment for storefront, furniture, etc.).
  • During construction documentation, estimates are based on cost per unit for selections and complete assemblies (500 square feet of tile at $3/square feet, installed),
166
Q

Why Quality Control?

A

Reduces risk
Reduces liability
Likely will save time and energy later in the project

167
Q

Establish a Quality Control Program

A
  • Must have buy in from top to bottom of firm/office
  • Name one person or a small committee as heads of the program to maintain daily or weekly requirements
  • Involve everyone in the office
  • Review past problem areas
  • Must be maintained and used continually to be effective
168
Q

Other Approaches and Techniques to maintain quality control

A
  • Follow any and all laws and regulations
  • Maintain good programming from the project onset
  • Use checklists
  • Hold quality management meetings
  • Staff projects appropriately
  • Hold quality circles
  • Use corporate knowledge
  • Don’t be afraid to ask for help
169
Q

Evaluate Management of Design Process
Factors to consider:

A
  • Confirm project goals
  • Confirm project budget
  • Confirm project timeline
170
Q

Ensure Design Objectives are Met and Monitored
Factors to consider:

A
  • Continually circle back and confirm design and project objectives
  • Check in at given points throughout the project and design process
  • Confirm you are meeting programming requirements as the project progresses
  • Staff project appropriately throughout the design process
  • When in doubt, get a second set of eyes
171
Q

B101 overview

A
  • AIA Document BIOI is the standard form of agreement between an owner and an architect. You can access a sample of this document through the AIA website to review for your ARE exams.
    The beginning of the document contains the Table of Articles outlining all subjects addressed in the contract. While order or wording may be vary based on updates, the general contents are as follows:
  • Initial project information
  • The Architect’s responsibilities, scope of basic services, & additional services
  • The Owner’s responsibilities
  • Cost of the work
  • Legal matters (copyrights & licenses, claims & disputes, termination or suspension, & miscellaneous provisions)
  • Compensation
  • Special terms & conditions
  • Scope of the agreement
172
Q

B101 :Initial Information is the section of the document where general details of the project are recorded. This section includes the following information:

A
  • The Owner’s program
  • The project’s physical characteristics
  • The Owner’s budget
  • Scheduling milestones
  • Selected procurement and project delivery method
  • Sustainability objectives, if applicable
  • The Owner’s and Architect’s representatives, if either party elects to employ one
  • Consultants and contractors hired by the Owner and Architect, individually
173
Q

B101 : The following sections relate to the roles and responsibilities of the Architect. These sections include the
following information:

A
  • The Architect’s responsibilities regarding professional services
  • Insurance requirements for the Architect
  • What is and is not included in the scope of the Architect’s basic services
  • The Architect’s roles and obligations for each phase of design
  • The Architect’s responsibilities evaluating the work and approving payments to the contractor
  • The process for reviewing and approving submittals
  • Expectations for project completion and follow-up
  • Supplemental and additional services offered by the Architect, if applicable
174
Q

B101 : The next section relates to the roles and responsibilities of the Owner. This section includes the following
information:

A
  • The Owner’s responsibility to provide requested information in a timely manner
  • Breakdown of items that should be included in the overall project costs for the Owner’s budget
  • The Owner’s obligations regarding hiring and scheduling consultants and testing
  • The Owner’s insurance requirements
  • Guidelines for communications within the project team
175
Q

B101 : The remaining sections cover all other applicable matters. These sections address the terms and legal limitations of the contract, as well as the cost of work and agreed upon compensation for professional services. The sections include the following information:

A
  • Cost of work
  • Copyrights and licenses
  • Claims and disputes
  • Termination or suspension
  • Miscellaneous provisions
  • Compensation
  • Special terms and conditions
  • The scope of the agreement
176
Q

Authority Having Jurisdiction

A
  • Permit is the term typically used to indicate approval of a proposed project concept, design, or execution by the Authority Having Jurisdiction (AH)). AHJ refers to the individual, agency, or office responsible for enforcing the requirements of codes and regulations. They exist on the federal, state, and local levels.
    The following are examples of Authorities Having Jurisdiction:

– State fire marshal
– State education department
– State transportation deportment
– County building department
– County health department
– Local zoning department
– Utility companies
– Elevator inspectors

177
Q

Regulatory Codes

A
  • The codes and requlations enforced by Authorities Having Jurisdiction also exist on the federal, state, and local levels. The following are a few examples of regulatory provisions:
  • Building code- International Building Code (IBC) or other
  • National Fire Protection Association (NFPA) codes
    • NFPA 7: Fire code
    • NFPA 707: National Life Safety Code
    • NFPA 70: Notional Electrical Code
  • Energy codes
  • Housing codes
  • Department of Health codes and standards
  • Local zoning codes
  • Americans with Disabilities Act (ADA) guidelines
  • Historic preservation regulations
178
Q

Permits and Restrictions

A
  • Permits exist in many different forms. A few examples of approvals that may be awarded over the course of a project are a plan review, building permit, fire inspection, and a certificate of occupancy.
  • Restrictions that may apply to a project include deed restrictions, planning review board rules, restrictive covenants, zoning requirements, easements, and right-of-way.
  • Often, a special type of approval is required when a proposed project will violate a restriction. This circumstance will typically require an application and explanation of the proposal and violation, a presentation to a committee, and the issuance of approval, if the proposal is deemed appropriate. Examples include a variance or a special use permit.
179
Q

Permitting Design Process

A
  • Permitting is relevant throughout the design process and may involve many authorities, agencies, boards, or review committees.
  • An application and review for a zoning variance would necessitate an approval during the concept stage. An owner or developer will not want to invest time and money into a design until they have
    permission to locate the specific project on the given site.
  • A plan review and award of building permit occur after the design is completed but before the project moves into construction. A review of this type is intended to ensure the proposed design meets the code requirements enforced by the AH), allowing any necessary charges to be made before the commencement of construction.
  • A certificate of occupancy is granted at the end of construction if a project has been constructed in accordance to code and safety standards.
  • The requirement of incremental permits and approval can help ensure a project does not progress too far without first resolving any problems of compliance to the regulations of the AH]
180
Q

augment

A

make (something) greater by adding to it; increase

181
Q

Balanced scorecard

A

Balanced scorecard is a system established to provide performance goals and metrics that take intangibles into account (in addition to strictly monetary measures).

182
Q

Lean production

A

Lean production is a system of quality control management based on eliminating waste

183
Q

Project work plans

A

Project work plans help with quality control

184
Q

Six Sigma

A

Six Sigma is a system of quality control management based on eliminating variation.

185
Q

Methods of Reviewing Project Documentation for Quality Control
How is quality control maintained?

A
  • Review and confirm any and all code and other regulatory requirements
  • When possible, stick with industry standards or corporate knowledge
  • Engage quality circles, quality teams, or other qualified people in your office
  • Use checklists
186
Q

Code and Regulatory Requirements
Factors to consider:

A
  • Confirm basic code requirements
  • Confirm hot button issues that go along with specific project type
  • Let the code or other regulatory requirements guide you
  • Check your project drawings against code or other regulatory requirements
187
Q

Corporate Knowledge and Industry Standards
Factors to consider:

A
  • Use any corporate knowledge or past details when applicable
  • Stick to industry standards whenever possible
188
Q

Quality Circles, Teams, and Outside Help
Factors to consider:

A
  • Quality circles and teams should always review documents if available
  • A fresh set of eyes that are qualified can go be very effective
189
Q

Checklists
Factors to consider:

A
  • Easy and effective
  • Check things off as you complete them
  • Easy to show what’s left and still need completing
190
Q

A planned unit development

A

A planned unit development is an area set aside for a specific use, such as a residential subdivision or a mix of commercial and residential uses.

191
Q

Cluster zoning

A

Cluster zoning allows structures to be grouped on one part of a site to preserve open space on other parts.

192
Q

overlay zoning

A

A historic preservation district is an example of overlay zoning. The primary zoning designation for the properties in the historic district might be commercial, residential, or some other category, but all
improvements to the properties in this area are subject to the approval of the architectural review board. The board’s goal is to protect areas of architectural or cultural distinction from decay due to demolition or neglect or to encourage development complementary to the area’s existing character.

193
Q

joint use easement

A

A joint use easement allows two or more property owners to share a common feature, such as a driveway.

194
Q

Restrictive covenants

A

Restrictive covenants are provisions that restrict the use of the property by the buyer.

195
Q

zoning variance

A

is deviation from the zoning regulations

196
Q

conditional use permit (CUP)

A

A conditional use permit (CUP) is a permit issued by the zoning jurisdiction for a proposed use that is not otherwise allowed in a particular zoning district. Of the options listed, only a CUP allows a commercial building to be built in a residential neighborhood.

197
Q

AHJ requires correction for the architect’s work. what should the architect do?

A
  • It is the architect’s contractual responsibility to provide a set of documents that can be permitted by the authority having jurisdiction (AHJ). Making these changes would not be additional services. Therefore, the architect can not charge the owner for making these necessary changes to obtain a permit from the AHJ.
  • If the AHJS review had required a change that would greatly affect the scope of the project, then a meeting with the AH] (option D) might be appropriate, but this is not the case here.
198
Q

C401 Overview

A
  • outlining all subjects addressed in the contract. While order or wording may vary based on updates, the general contents are as follows:
  • General provisions
  • The Consultant’s responsibilities, scope of basic services, & additional services
  • The Architect’s responsibilities
  • Cost of the work
  • Legal matters (copyrights & licenses, claims & disputes, termination or suspension, & miscellaneous provisions)
  • Compensation
  • Special terms & conditions
  • Scope of the agreement
199
Q

C401 Overview
General Provisions

A
  • The requirement to include the Owner-Architect Agreement as “Exhibit A” for the consultant’s reference
  • Explanation of terminology used in the contract
  • The Consultant’s ownership of the means and methods of their scope of work
  • The limitations of liability that falls on the Architect
  • *(Communication guidelines among the project team**
  • Shared costs between the two parties, if applicable
  • The agreed upon guidelines for sharing professional credit, if applicable
  • Other Consultants to be retained by the Architect
  • Subconsultants to be retained by the Consultant
200
Q

C401 Overview
the roles and responsibilities of the Consultant.

A
  • The responsibility of the Consultant to provide work consistent with the professional standard of care
  • The Consultant’s representative, if provided
  • The recommendation of relevant surveys, tests, reports, and services
  • Coordination of work and services
  • Responsibilities regarding errors and omissions of work
  • Insurance requirements
  • The services to be supplied by the Consultant per the agreement
    Supplemental and additional services offered by the Consultant, if applicable
201
Q

C401 Overview
the roles and responsibilities of the Architect.

A

The following sections relate to the roles and responsibilities of the Architect. This section includes the following information:

  • The responsibility of the Architect to provide timely information to the Consultant
  • The Architect’s representative, if provided
  • The expectation for the Architect to assist in the coordination of work among Consultants
  • The actions required of the Architect upon receiving a Request for Information (RFI) regarding work performed by the Consultant
  • Information sharing among project team members regarding budget estimates and scopes of services
  • Methods for requesting outside surveys, tests, reports, or services from the Owner
  • The responsibility of errors and omissions in the Consultant’s work
  • Requests relevant to evaluate, give notice of, or enforce lien rights by the Consultant
202
Q

C401 Overview
The remaining sections
cover all other applicable matters.

A
  • Cost of work
  • Copyrights and licenses
  • Claims and disputes
  • Termination or suspension
  • Miscellaneous provisions
  • Compensation
  • Special terms and conditions
  • The scope of the agreement
203
Q

Fee percentage for each phase

A

schematic design: 15%
design development: 20%
construction documents: 40–45%
bidding and negotiation: 5%
contract administration: 15-20%

204
Q

historic structures, as defined in the Secretary of the Interior’s Standards for the Treatment of Historic Properties.

A
  • Preservation is the most historically accurate and requires keeping existing elements in situ.
  • Restoration returns a building to its appearance at a particular point in time.
  • Reconstruction is building based on documentation (e.g., photographs and historical records) that recreates elements of the building that have been demolished or lost to time.
  • Rehabilitation emphasizes the retention and repair of historic materials but gives some latitude for replacement of damaged materials.
205
Q
  • Net service revenue (NSR)
  • Estimate-at-completion (EAC)
  • job-to-date (JTD)
  • Earned-not-billed (ENB)
A
  • Net service revenue (NSR) is the net fee determined by subtracting consultant fees from the gross fee for the project.
  • Estimate-at-completion (EAC) is job-to-date (JTD) plus estimate-to-complete (ETC) : labor hours and dollar amounts estimated at project completion.
  • JTD is labor hours and dollar amounts spent as of the current date.
  • Earned-not-billed (ENB) refers to amounts recognized in the accrual accounting system as revenue that is earned but not billed to clients.
206
Q

Proposal request

A

A Proposal Request notifies the contractor of an anticipated change and requests a proposal from the contractor stating the cost and/or time impact of the change

207
Q

The Architect’s Supplemental Instructions

A

The Architect’s Supplemental Instructions would be the appropriate document only if there is no change in the cost or time

208
Q

performance specification

A
  • they make the architect responsible for identifying the performance needs of the specified items.
209
Q

descriptive specification

A
  • they describe general product needs.
  • they explain all components of the specified items in detail.
  • they describe the arrangement and assembly of the components of the specified items.
210
Q

A statute of limitations

A
  • the period during which an architect can be subject to legal action resulting from injury or damage caused by deficient design.
  • A statute of limitations is a law that imposes time limits upon the right of action by one party against another for alleged damage or injury.
211
Q

Contractor bid price includes

A
  • Potential liquidated damages
  • Competitive conditions
  • Special insurance requirements
  • The weather
  • general overhead
  • fee
  • material cost
212
Q
  • Quality circle
  • steering committee
A
  • A quality circle is a participatory management technique that brings employees who do the same, or similar, work into formal, small groups in order to identify and address work-related problems. Solutions to problems are then presented to management. The quality circle identifies those problems that affect day-to-day work.
  • A steering committee may be appointed to coordinate the efforts of multiple quality circles focusing on various issues. The steering committee then vets ideas to be passed along to the firm’s management. Management issues such as developing strategic and financial plans are outside of the scope of work performed by a quality circle
213
Q

Wall schedule

A

The full wall schedule technique requires everyone on the project to work on developing the project schedule. This facilitates discussion about work tasks, responsibilities, and project deadlines. Participation of all team members is encouraged, and as a result, everyone has a vested interest in the final schedule.

214
Q

Consultant responsibilities

A

I. providing a preliminary estimate for the cost of the work
II. performing with professional care and skill
III. submitting a schedule for approval
IV. recommending needed tests, surveys, or investigations

215
Q
  • Life safety code
  • building and fire code
A
  • Life safety codes primarily address egress.
  • Building and fire codes are intended to protect buildings from fire damage.
216
Q

project-related documents how long it should be properly stored

A
  • Until the expiration day of statute of repose.
  • documents should be suitably identified and properly stored in accordance with the firm’s document retention policy.
  • Unless required for a longer period by the services contract, documents are typically retained for a period of approximately the same length of time as the period specified by the state statutes governing claims. Although some states have no statute of limitation on claims,
  • a popular period for maintaining project files in storage is 15 years. Documents on projects for repeat clients are often kept longer, especially if the project has future phases yet to be constructed
217
Q

What is this definition for?
- running a practice professionally

A

Practice management

218
Q

What is this definition for?
- finding ways to meet the requirements, constraints, and opportunities of a project

A

Programming and analysis

219
Q

What is this definition for?
- performing tasks related to building the design of a project

A

Construction and evaluation

220
Q

What is this definition for?
competently delivering architectural services

A

Project management

221
Q

Partnering

A
  • The owner initiates a project partnering agreement. The owner hires the architect and contractor and might also hire other consultants. The owner has a separate contract with each professional. In these contracts, the consultants agree to be a part of the partnering process, which means that they agree to participate in partnering activities and meetings and adhere to the dispute resolution terms defined by the team.
  • The participants do not have a contractual relationship with each other (i.e., their contracts are with the owner) but they agree to cooperate and work together in good faith throughout the course of the project.
  • At the beginning of the project, the team members choose a third-party facilitator who leads a kick-off workshop in which the project goals are discussed, a work plan and schedule is developed, potential conflicts are identified, and the team determines the means of dispute resolution that will be used if required. The participants also develop an issue resolution ladder, which is a strategy for anticipating potential problems and a method for dealing with them.
222
Q

Architect can reject the work.
True or false?

A

True
Architect can reject the work but can’t stop the work.
Only the Owner can stop the work.

223
Q

eminent domain.

A
  • The government has the right to take private property for public use if it is for the greater good. The government must pay the property owner fair market value for the property, but the owner does not get a choice.
  • It is granted by the Fifth Amendment to the U.S. Constitution, which states, “…nor shall private property be taken for public use, without just compensation.
  • Eminent domain laws are intended to allow public projects to move forward while fairly compensating private property owners for their property and any other damages, such as relocation expenses. This process is sometimes referred to as condemnation.
  • condemnor must be authorized by statute or ordinance to use the power of eminent domain for a specific purpose. The condemnor must first make an offer to buy the property from the property owner. If they cannot agree, eminent domain proceedings may be initiated, where the condemnor will be required to prove that the property is to be acquired for a public purpose.
  • If the judge agrees that use of eminent domain is appropriate, hearings begin to determine the fair market value of the property. The judge may appoint a panel of “condemnation commissioners” who determine the fair market value or, if this is not satisfactory to either party, he or she may appoint a jury to determine the award. The property owner is then paid the determined fair market value plus any other damages the court deems appropriate.
  • The power of eminent domain may be transferred to a private company, such as a utility company, railroad, port authority, and so on, when that entity is working on a project that is determined to serve the public interest. The U.S. Supreme Court’s decision in Kelo v. City of New London determined that the power of eminent domain may be also used by a private, for-profit company when the project serves the public interest by promoting economic development.
224
Q

Inclusionary zoning

A

Inclusionary zoning requires construction of low-income housing as a condition of approval.

225
Q

Construction submittals

A
  • shop drawings
  • samples
  • product data
226
Q

Master specifications

A

Master specifications are a collection of standardized, pre-written technical specifications or guide specifications used by designers, architects, and other construction professionals.

They save time and help prevent mistakes by serving as a base for customization for a particular project or spec. They are arranged by type in sections.

227
Q

Responsible bidder

A

a responsible bidder is considered by the owner and architect to be fully responsible and qualified to perform the work for which the bid is submitted.

228
Q

proprietary specification

A
  • It specifies a particular product by brand name and allows no substitution This is the easiest type of specification for the architect to write, but puts all of the responsibility for choosing a material that is code-compliant and technically correct onto the architect
229
Q

base bid with alternates specification

A
  • A base bid with alternates specification is similar in format to the base bid with “approved equal” language specification.
  • Both call for a specific product but allow substitution of other materials
  • However, an important difference between the two is that the base bid with alternates allows a contractor to substitute a product that he feels is equal, and does not require the architect’s approval.
  • The product he submits may not be comparable to the one defined in the specification but must be accepted due to the way the specification is written.
  • This type of specification does not give the owner and architect control over the quality of the products used.
230
Q

descriptive specification

A
  • A descriptive specification defines the type of outcome desired but does not list specific products. It is the most difficult type of specification for an architect to write because it requires listing all of the criteria that a material or assembly must meet. Therefore, it is more likely one would erroneously report the required standards, resulting in lowered performance from the product.
231
Q

base bid with “approved equal” language

A
  • The base bid with “approved equal” language lists the desired product and states that an alternative product proposed by a contractor will be considered by the architect.
  • This establishes a minimum level of quality based upon the characteristics of the specified product, but it puts the responsibility on the contractor to find and submit an alternative product if he or she wishes.
  • This type of specification will require the architect to evaluate the proposals during the bidding phase and issue addenda notifying all bidders of the decisions.
  • When using a base bid with an “approved equal” type of specification, it is important to include a deadline for submission of proposed substitutions during the bidding phase to allow the architect enough time to research the products and issue notification to the bidders of the substitutions’ acceptance or rejection.
232
Q

Typical off-site costs routinely include what?

A
  • Typical off-site costs routinely include costs of improvements outside project property lines, such as utilities.
  • Access road costs are sometimes included, but would not be considered a routine cost as they may be paid for either by the owner or a government agency, depending on the situation
233
Q

RFI types

A
  • Type 1: Graphic/Confirming, 2hr
  • Type 2: Coordination/Missing Information, 5hr
  • Type 3: Code/Contract Information, 8hr
234
Q

architect responsibility during construction

A
  • the architect is responsible only for providing administration of the construction contract.
  • The architect endeavors to protect the owner from defects and deficiencies in the work, and they may be held responsible by the owner if due care is not used in evaluating the work.
  • Superintendence and supervision of construction are responsibilities of the contractor or an agent of the contractor.
  • Inspection is generally performed by building inspectors who represent the public interest.
235
Q

reduced bidding time affects construction. true or false?

A

After the CD phase has been completed, the project is ready to enter the bidding process. When bidding a project,the bidders should be allowed sufficient time to review and estimate the project. Reducing this time could result in fewer and less accurate bids, which could then lead to issues during construction.

236
Q

architects are not responsible for job site safety or OSHA compliance common sense

A
237
Q

Statutes of limitations

A
  • Statutes of limitations and statutes of repose both place limits on the amount of time that claims can be filed relative to design or construction issues.
  • The state’s statute of limitations establishes the amount of time that a party has to take legal action upon discovery of a design or construction defect.
  • Some states have “right to cure” laws that are relevant to construction deficiencies. Where they exist, the requirements vary from state to state. Some require the owner or claimant to notify the other party of the issue and give them the opportunity to inspect the site and either repair the problem or compensate the claimant appropriately before legal action can be taken. Others simply require the claimant to notify the other party before starting legal action.
238
Q

statutes of repose

A
  • Statutes of limitations and statutes of repose both place limits on the amount of time that claims can be filed relative to design or construction issues.
  • statutes of repose extend beyond Statutes of limitations
  • The statute of repose establishes the time during which legal action may be taken once construction has completed. The statute of repose for a construction project begins at a fixed time (such as substantial completion, final inspection, or first use for the intended purpose, depending on the state), and the length of time varies by state. Some state laws include language that allows the established length of time to be extended in cases of injury, or when defects are discovered near the end of the time period.
  • The American Institute of Architects (AIA) documents limit the time in which a claim may be made to 10 years, or the length of time prescribed by state law, whichever is shorter.
239
Q

The amount of the performance bond is normally what percentage of the contract sum?

A
  • A performance bond amount of less than 100 percent indicates that the surety does not believe that the contractor can perform the work according to the surety’s standards. The surety may believe that the project is too big for the contractor, or that the contractor has too many commitments to other projects
240
Q

what is “build out” project and which additional engineering needs?

A
  • work done to make a structure or system ready for use
  • no structural modifications should be required. Geotechnical services, should already have been arranged by the building owner and completed. Acoustical services should not be necessary, as minimum required sound insulation would be part of the demising wall
241
Q

building code analysis first step

A
  • At the beginning of the building code analysis, the architect must determine the local regulations, which include the type and edition of adopted building codes (e.g., the International Building Code, International Mechanical Code, National Electrical Code), as well as modifications adopted by the local jurisdiction that add, delete, or modify parts of the building codes.
  • After determining the local regulations, other building factors can be considered such as occupancy (use group), allowable building height and area, and allowable construction type
242
Q

who inspect building to be occupied

A

the owner, contractor, and architect should jointly inspect the area to be occupied and record its condition immediately prior to the partial occupancy.

243
Q

Which series of American Institute of Architects documents deals with contract administration and project management forms

A

G series

244
Q

who designs foundation?

A
  • The geotechnical engineer makes the various soil tests required for a particular site and suggests the type of foundation based on the bearing capacity of the soil and other factors.
  • However, responsibility for the design of the foundation and type of system employed is ultimately the structural engineer’s
  • Typically, the geotechnical engineer’s report is contracted and paid for by the client, and the services of the structural engineer are included in the architect’s scope of services.
245
Q

ISO 9000

A
  • ISO 9000, which was established by the International Standards Organization (ISO), refers to a quality assurance program that can be applied to a variety of processes and industries, including service providers, manufacturing, management, and design.
  • The seven quality management principles on which all ISO 9000 standards are based are as follows.
    customer focus : meeting customer expectations and objectives
    leadership : all employees are working toward a common purpose
    engagement of people : the skills of all employees are being utilized and recognized appropriately
    process approach : the company has established clear guidelines for systems and processes
    improvement : organization reacts to successes and failures in a proactive way
    evidence-based decision making : choices are made after thorough investigation of objective data
    relationship management : maintain open communication with all parties with whom the company interacts
  • ISO 9000 is an umbrella term that refers to a number of quality standards;
  • ISO 9001 applies to architectural design processes. To participate, a design firm must develop and implement programs that satisfy the requirements of each section of the standard; all aspects of practice are evaluated, including purchasing procedures (including the qualifications of consultants that a firm employs), record keeping, systems for preparing and checking work, and financial management. An organization’s process can be certified to an ISO standard, if it complies with the program requirements, and compliance is validated by frequent third-party audits of the company’s policies and practices.
246
Q

Structure engineer job for SD and DD

A
  • After receiving concept and early-stage information about the design, the structural engineer will make preliminary selections of the major structural components and systems during schematic design. Load calculations and member sizing are primarily performed during the design development phase, further along in the project.
247
Q

performance-based specifications

A
  • If performance-based specifications are used, bidders can submit any product that meets the performance requirements established.
  • This type of specification does not list products that would comply. The responsibility to design a system or propose an item that meets the requirements is the contractor’s.
  • The architect would review the proposed materials for compliance during the submittals process.
248
Q

Architect’s working schedule consideration

A
  • During preliminary scheduling, the architect should allow additional time for coordination with consultants’ work.
  • The architect should make the timeline accord with the client’s decision-making process, not vice versa.
  • A preliminary project timeline should be made immediately after a commission has been awarded, not after completion of schematic design.
  • It is standard to plan for client reviews at the end of each phase of design, although additional reviews may be accommodated for larger projects.
249
Q

Definition of
- Work in progress
- billed
- spent

A
  • work in progress (WIP) is defined as time and expenses that have not yet been included on client invoices,
  • billed refers to amounts already invoiced to clients,
  • spent refers to the total time and expenses expended on the project at the given billing rates and markup.
250
Q

Who approves partial occupancy before substantial completion?

A

contractor, insurance company, AHJ

251
Q

Deed restrictions

A
  • Deed restrictions are clauses in a deed that place conditions, limitations, or restrictions on the use of property. Private developers often impose such restrictions on buyers for the purpose of maintaining the consistency or integrity of a development. All of the other terms listed refer to restrictions imposed by, or approvals granted by, local governmental agencies.
252
Q

Construction document naming

A

G- General
H-Hazardous Materials
V- Survey/Mapping
B- Geotechnical
C- Civil
L- Landscape
S- Structural
A- Architectural
I- Interiors
Q- Equipment
F- Fire Protection
P- Plumbing
D-Process
M-Mechanical
E-Electrical
W-Distributed Energy
T-Telecommunications
R-Resource (Existing conditions / buildings
X-Other Disciplines
Z-Contractor/Shop Drawings
O-Operations

253
Q

Property air rights

A
  • whomever owns the land shall own the earth to its center and up to the heavens.
  • Air rights permit a party to use the open space above land or an existing structure. Air rights can be sold or transferred to another party.
  • Air rights do not give a property owner the right to prohibit aircraft from entering that space; in the United States, the Federal Aviation Administration controls where aircraft can and cannot fly, not individual property owners.
254
Q

Riparian rights

A
  • Riparian rights allow property owners whose lots abut a natural river the right to make use of that resource.
  • Littoral rights are similar to riparian rights but apply to areas along the shores of bodies of water affected by tidal currents, such as oceans and navigable lakes.
  • State laws vary, but generally, man-made bodies of water do not have the same usage rights attached to them as natural waterways.
255
Q

abut

A

(of an area of land or a building) be next to or have a common boundary with.

256
Q

contractor discovered adversarial underground condition that affects contract sum and time, how soon he has to report to the owner and architect?

A
  • if the contractor discovers conditions that differ from the contract documents and would necessitate changes to the contract sum or length, the contractor must report this to the owner and architect before the conditions are disturbed and no later than 14 days after the conditions were first discovered.
257
Q

How surety completes the contractor’s defaulted work?

A
  • the surety may complete the work with its own forces
  • hire another contractor to complete the work
  • pay for the cost of completing the work to the amount of the penal sum of the bond
  • use the defaulted contractor
258
Q

How surety is notified when the change of work occurs?

A
  • The Performance Bond and Payment Bond (Document A312) does not require that the surety be notified when change orders are issued
  • Non-AIA bond forms, however, may require such notification. If so, this is usually the contractor’s responsibility
  • Change orders usually do not invalidate bonds
  • increases in the contract sum may result in increased bond premium costs
259
Q

Fee structure for owner’s pre selected contractor

A
  • When an owner negotiates a contract with a contractor, the agreement may be based on a stipulated sum, such as AIA Document A101-2017 or on the cost of the work plus a fee, with a guaranteed maximum price, such as AIA Document A102-2017 .
  • the agreement for the construction of a project is never based on the architect’s estimate.
  • A percentage of construction cost agreement is a contract for professional services, such as an AIA Owner-Architect Agreement, not an owner-contractor agreement
260
Q

General obligation bond

A
  • General obligation bonds are typically used to fund a specific project, such as a library or fire station. They are not used to encourage private development, although later private development could be a consequence of the new public facility being constructed (such as apartments or restaurants built in the vicinity of a publicly funded baseball stadium). Because all taxpayers in the jurisdiction issuing the general obligation bonds must pay off the bonds through a property tax, a voter majority is required.
261
Q

Developer impact fees

A
  • Developer impact fees are generally used to fund infrastructure improvements made necessary by new development. Although these fees are a common method of raising money, they can have a negative effect because developers look for areas to build in where impact fees are not charged.
262
Q

Business improvement districts

A
  • Business improvement districts are used to fund public space improvements, such as streetscapes, to enhance an area’s appeal and, indirectly, its property values.
  • Taxes are assessed on those property owners in the district who will benefit from the improvements, so this type of financing is not intended to encourage private development
263
Q

Tax increment financing

A
  • Tax increment financing is a method cities use to issue bonds to pay for improvements (such as new sewers or streets) within a specified district. These improvements are intended to stimulate private development within the district by providing better infrastructure and city services.
  • During the time of redevelopment, taxes are based on the assessed valuation of the properties prior to the redevelopment. (A tax based on the value of the property being taxed is known as ad valorem tax.) After the improvements are complete, the increase in tax revenue attributable to the development (the tax increment) is used to repay the bonds
264
Q

Pro forma

A
  • A pro forma is an analysis of the costs and revenues projected for a potential project and should be a part of the owner’s initial planning.
  • Generally this analysis and documentation is required to secure adequate funding for the project from lenders or investors
265
Q

Forego

A

omit or decline to take (something pleasant or valuable); go without.

266
Q

work breakdown structure

A
  • A work breakdown structure is the project’s to-do list or the list of the tasks that must be performed to complete the project. This can take the form of a list, spreadsheet, or mind map, depending on the project manager’s preferences.
  • It is generally developed by breaking the project into sections (by discipline, phase, or both) and then further “decomposing” the project into smaller, single tasks.
  • Unlike a responsibility matrix, a work breakdown structure does not assign the tasks to specific people. Unlike a critical path method (CPM) chart or other scheduling tool, it does not establish dependencies
267
Q

responsibility matrix

A
  • A responsibility matrix is a document that the project manager prepares that assigns tasks to specific team members. - The matrix can be used on a micro level to clarify individuals’ responsibilities and manage day-to-day workflow.
  • Likewise, it can be used on a macro level to assess whether the firm or team has the resources available to complete the project within the proposed time frame.
268
Q

general obligation bonds
vs
Revenue bonds

A
  • Municipal facilities are most often financed by means of bonds, of which there are two types:
  • general obligation bonds are used to finance the construction of facilities which do not collect revenue, such as schools.
  • Revenue bonds are used to finance the construction of facilities which produce revenue. Since the sale of water to residential, commercial, and industrial users generates revenue, the treatment plant in this question would probably be financed by revenue bonds
269
Q

typical components of an effective work plan.

A
  • project description and client requirements
  • statement of deliverables
  • team organization
  • responsibility matrix
  • preliminary project schedule
  • preliminary staffing needs
  • project directory
  • internal project budget and profit plan
  • code information (optional)

While the project program and initial concept design sketches are important for any project, they are not part of a work plan.

270
Q

Contract document is legal relationship between which parties?

A

Owner and contractor

271
Q

Full wall schedule

A
  • The full wall schedule technique requires everyone on the project to work on developing the project schedule.
  • This facilitates discussion about work tasks, responsibilities, and project deadlines.
  • Participation of all team members is encouraged, and as a result, everyone has a vested interest in the final schedule.
272
Q

what is last resort

A

something you choose only after you’ve eliminated every other possibility

273
Q

what is contract document

A
  • agreement
  • contract condition
  • drawing
  • specification
  • addenda
  • any listed document
274
Q

what is green field

A

land that has not yet been built on, or buildings built on land that had never been used before for building

275
Q

What are the three major features of the design-build delivery method?

A

The three major features of this type of project delivery are

  • the owner contracts with one entity
  • a fixed price is established early in the process
  • the overall project time is reduced
276
Q

Which two types of delivery method has the advantage of providing the owner with early advice on the constructability of a design?

A

This type of advice to the owner is part of the construction manager as adviser (CMa) and construction manager as constructor (CMc) delivery methods.

277
Q

What type of bidding is required in public projects?

A

Competitive bidding is required for this type of project.

278
Q

What are the three common methods of project delivery, as identified by the AIA and the AGC?

A

The American Institute of Architects (AIA) and the Associated General Contractors of America (AGC) identify the three common methods for this as

design-bid-build
design-build
construction manager at risk

279
Q

In what kind of document would you find the term “conditional use permit” defined?

A

A definition for this term, which is often abbreviated as CUP, can be found in a zoning code.

280
Q

What is the architect’s role in a design-build advisor contract?

A

In this method of delivery, the architect is responsible for

  • setting performance requirements
  • assisting the owner in selecting the design-build team
  • evaluating the project progress administering the contract
281
Q

If a code or law revision makes changes necessary to the drawings or specifications, what is the architect entitled to?

A
  • If changes to these are needed due to a code or law revision, the architect is entitled to additional compensation for changes in service.
282
Q

What is a bid security?

A
  • This is a bond that a contractor submits with a bid to guarantee that the bidder, if successful, intends to enter into a contract for the amount bid.
  • The bond is forfeited if the bid is successful but the bidder does not sign a contract.
283
Q

What is the main source of claims of negligence?

A
  • Deficiencies in the construction documents lead to this problem.
284
Q

What are the most important aspects of successful project execution?

A

These activities must be addressed to maintain the overall quality of the project

  • monitoring fees, time, and the construction budget
    controlling changes in the work
    compiling accurate and organized documentation
    during the design and construction phases
  • conforming with applicable codes and requirements of local authorities
285
Q

partial occupancy

A
  • Owner occupancy of a portion of the building or buildings before completion of the entire project.
286
Q

project manager

A
  • Term used to describe the professional responsible for the oversight and delivery of their discipline of professional work or services, typically having administrative and technical responsibilities to the project.
287
Q

specifications

A
  • A portion of the contract documents that formally list the written requirements for equipment, performance, quality, standard of workmanship, building materials, and construction systems. Are included in the project manual
288
Q

addendum

A
  • Documentation issued by the architect—after issuing project documents for bidding and prior to the execution of the construction contract—that modifies, clarifies, or corrects the intent of the project documents. The method of making a change before bidding is complete.
289
Q

Request for Proposal RFP

A
  • A process by which an owner solicits qualified professionals to perform work or services. Also, an evaluation and selection process for services
290
Q

design development (DD)

A
  • The third phase of design work after programming and schematic design.
  • Design development shows the integration of preliminary building systems designs and fully develops the design of floor plans and elevations.
  • Owner final approval of design is often achieved at the end of design development.
291
Q

schematic design (SD)

A
  • A preliminary level of design;
  • the second phase of design work, after programming, that gives form, shape, and itinerary to the project program.
  • Schematic level design should suggest overall building dimensions, footprint and profile, locations of building core items, egress, and preliminary floor plans.
292
Q

What should be done after every project, meeting, action, and decision?

A
  • After any of these events has occurred, it should be documented in writing and sent to all involved parties.
293
Q

What does a steep project perfection curve indicate?

A
  • This an indication that the project team has a high degree of experience and skill.
294
Q

How should a client be involved in project discussions?

A
  • This person’s contributions should be directed to areas where their ideas will be most valued.
295
Q

Name seven elements included in a good work plan.

A
  • scope of services
  • breakdown of services into phases dependencies
  • milestones
  • staff needed to complete the work
  • allocation of time and fees
  • consultant scope of work
296
Q

What is another name for a fee projection?

A
  • This document is also called a work plan, since it includes fee breakdown information.
297
Q

What is another name for a work plan?

A
  • A detailed project schedule is another name for this.
298
Q

What are the four basic types of communication in a design office?

A
  • Work assignments,
  • instructions,
  • reward and punishment,
  • social interaction
299
Q

Once a consultant is hired, what should the project manager communicate to the consultant?

A
  • Code requirements for the project are included in this communication and final project schedule.
300
Q

Name three items typically kept in a project notebook.

A
  • Contracts,
  • project communications,
  • approved project program

Other items include budget, schedule, and eventually the closeout documents.

301
Q

What leadership tools should a project manager employ if a team member becomes angry?

A
  • This person should remain calm when a team member becomes angry and be prepared to listen.
302
Q

Name the type of scheduling tool used to develop a project schedule.

A
  • A Gantt, or bar, chart is used to develop this.
303
Q

At what phase of a project is a work plan developed?

A
  • This is developed at the very beginning of the project.
304
Q

ASHRAE

A

American Society of Heating, Refrigeration and Air Conditioning Engineers

305
Q

ANSI

A

American National Standards Institute

306
Q

OSHA

A

Occupational Safety and Health Administration.

307
Q

FEMA

A

Federal Emergency Management Agency

308
Q

EPA

A

Environmental Protection Agency

309
Q

consultant

A
  • An engineer or other specialist retained by the architect to provide specified professional services that the architect is required to provide to the owner under the owner-architect agreement.
310
Q

What team member is added to the project team if minimizing sound transmission is included in the scope of work?

A
  • An acoustical engineer is added to this group as a specialty consultant if this is included in the project.
311
Q

Who are the three non-construction participants, at a minimum, who are involved in a project team?

A
  • The owner, the architect, and the consultant are included in this group.
312
Q

What is the primary role of the project manager?

A
  • The role of this position is to coordinate all design and construction administration activities.
313
Q

Allocation of project resources within the office is dependent upon what?

A
  • Owner preferences for staff selection and the firm’s organizational structure are used to determine
314
Q

What is the primary criterion for consultant selection?

A
  • Past working relationship is the primary criterion.
  • Other considerations are fee proposal and firm expertise for this.
315
Q

Name four criteria typically considered when assembling a project team.

A
  • experience
  • availability
  • billing rate
  • personality