PICC (Change Control) Flashcards
1
Q
What must a project manager do before PICC?
A
- Prevent the root cause of changes
- Identify the need for a change
- Evaluate the impact of the change within the project constraints
- Create a change request
2
Q
What is the Perform Integrated Change Control process?
A
- Assess the change.
- Identify options.
- Get the change approved, rejected or deferred.
- Update the status of change in the change log.
- Adjust the project management plan, project documents, and baselines as necessary.
- Manage stakeholders’ expectations by communicating the change to stakeholders affected by the change
- Manage the project to the revised project management plan and other project artifacts.
3
Q