Performance, Termination, Breach, Damages and Equitable Remedies Case Cards Flashcards
Arcos v Ronasen
Standard of performance; Strict liability sale of goods as contracted. Purchase of wood 1/2” thick and many were not that thickness. Breach of Condition.
Re Moore & Landauer
Strict liability. Sale of cans 3000 total in boxes of 30. Came in boxes of 24.
Roberts v Havelock
A shipwright agreed to repair a ship. The contract did not expressly state when payment was to be made. He chose not to go on with the work. It was held that the shipwright was not bound to complete the repairs before claiming some payment.
Planche v Colburn
Quantum Meruit. Contract to write book, did all research and was cancelled, he was to be paid for work done.
Dakin v lee
The defendants promised to build a house according to specification and failed to carry out exactly all the specifications, for example, concrete not four feet deep as specified, wrong joining of certain rolled steel joists and concrete not properly mixed. The Court of Appeal held that the builders were entitled to recover the contract price, less so much as ought to be allowed in respect of the items found to be defective.
Universal cargo Carriers v Citati
Repudiatory Conduct.No cargo was at place of loading past lay days, frustrated so allowed to terminate.
Eminence Property developments v Heaney
Objective test. has the contract breaker shown the innocent party that they clearly intend to breach the contract.
Union Eagle v Golden Achievement
Broken term is a condition, breach allows termination & Damages. Sale of Land at or before 5pm. $ was 10 mins late.
Schüler v Wickman
Parties designate a term a condition unless it creates unreasonable results. 1500 total visits. Made 90%, held breach of condition, court made it a warranty.
Hochester v De La Tour
Anticipatory breach. Hired courier and then told him he wouldn’t need him. Courier allowed to sue before contract began.
Johnson v Agnew
there was continuing repudiatory action by A. J sought SP but house repossessed and sold before then. Breach of contract is prospective. Assess damages from Date of breach. Expectation interest awarded, original sale price - what it sold for.
White & Carter Councils v Macgregor
They were hired by one of the D’s managers to put adverts on bins. The owner didn’t want the adverts so said he wouldn’t go through with it. They were held liable to pay for the whole contract
Jarvis v Swan Tours
Cannot usually claim for disappointment/discomfort. Exception being Holiday cases. Holidays were not as advertised and they were compensated for discomfort.
Malik v BCCI
Loss of Reputation can be recoverable with damages where there exists a duty of care
Paula Lee v Zehil
Reasonable Valuation of Damages. 16k dresses to be bought, wanted it based all on cheapest. Court said based on reasonable valuation.
South Australia Asset management v York Montague
Building negligently valued at 15 mil, only worth 5 mil They were awarded 10 mil in damages.
Ruxley v Forsyth
Loss of Amenity. Pool was built not to specifications, they wouldn’t award full damages as it wouldn’t have been used for that purpose. so just damages for loss of Amenity.
Tito v Waddell
Island strip mined. Court wouldn’t award damages to replant all the trees as the company would not use it for that. it wasn’t economically realistic.
Aerospace Publishing v Thames Water
Water damages their property. Not only were they able to recover damages for the loss of property, but they were also able to recover damages or loss of income due to the damages.
Hadley v Baxendale
The crankshaft broke in the Claimant’s mill. He engaged with the D to repair the crank shaft. IT was returned 7 days late
The damages available for breach of contract include:
- Those which may fairly and reasonably be considered arising naturally from the breach of contract or
- Such damages as may reasonably be supposed to have been in the contemplation of both the parties at the time the contract was made.
Victoria Laundry v Newman
Remoteness. Does damages arise naturally from breach. was it within contemplation of patties at outset. Delay of boiler resulted in loss of contract. this was not foreseeable or within contemplation.
The Heron II
Remoteness. Ship with sugar was 9 days late. It was reasonable to contemplate that sugar prices would fluctuate.
Parsons v Uttley Ingham
Pig feeder improperly installed and all the pigs dies. IT was within contemplation that if the feeder was installed improperly the food would go bad and kill the pigs.
Payzu v Suanders
Duty to Mitigate. contract for sale of goods, failed that. Given chance to pay cash. Terminated and sued. NO they had a duty to mitigate damages.