Performance, Breach and Remedies Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

Hadley v Baxendale (1854)

Remoteness- reasonable foreseeability test

A

Not possible to recover lost profits – D could have expected the claimant to have had a replacement for use in the meantime
two limb test:
- loss foresseable in the ordinary course of things (imputed knowledge)
- loss foreseeable bc special cirmstances brought to the attention of the defendant ? (actual knowledge)

Alderson B:

“the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, ie, according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it”

=> what losses could the defendant reasonably contemplate as likely to result from a breach of the contract?

Claimant owned a corn mill – shaft broke;
Manufacturer of new shaft needed the broken shaft to ensure that it would fit into the existing engine/mill;
Claimant engaged the defendant carrier to take the broken shaft to the manufacturer;
Defendant delivered late = caused the mill to be at a standstill for an additional 5 days => Loss of profits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Victoria Laundry (Windsor) Ltd. v. Newman Industries Ltd [1949] 2 K.B 528

remoteness - reasonable foreseeability

A

Held: C could recover damages for losses flowing from the inability to run business as usually but not the loss linked to the impossibility to perfom a lucrative contract.

D agreed to deliver a boiler to C’s laundry business. However (in breach of contract) D delivered the boiler five months late.

C was unablle to run the business ant full capacity and consequently lost their profirs on ‘its ordinary business’

C lost pofits for a lucratiuve contract with the ministry of Supply

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

British Westinghouse Electric & Manufacturing Co Ltd v Underground Electric Rlys Co Ltd (no 2) [1912]

mitigation - limitations on compensatory damages

The standard of reasonableness that must be attained is relatively low: there should be a “tender approach to those who have been placed in a predicament by a breach of contract”(Tomlinson J in Britvic Soft Drinks Ltd v Messer UK Ltd [2002]) = The most that is expected is that you do what is reasonable in the circumstances rather than what is possible

A

= A claimant cannot recover damages for losses which he could have reasonably avoided

held: The losses from breach of contract had been entirely mitigated by the more efficient replacements

C were in breach of contract with D by supplying defective turbines
D replaced them with turbines which were more efficient than D’s turbines even if working
The savings from the new turbines had exceeded the losses from the defective turbines
C claimed for sums owed under contract and D counterclaimed for breach of contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Transfield Shipping Inc v Mercator Shipping Inc (The Achilleas) [2008] UKHL 48

test for remoteness

This test was marginalised in Att-Gen of the Virgin Islands v Global Water Associates Ltd [2020]

A

The House of Lords suggested a refined version of the remoteness test to be used to determine what losses are recoverable in The Achilleas [2008] : Instead of asking what losses the defendant could reasonably have contemplated, Lords Hoffmann and Hope asked what losses the defendant (could reasonably be understood to have) assumed responsibility for. Lord Hoffmann thought this followed simply from the nature of contractual obligation:

the HoL found for D

Charterer (D) was bound to redeliver the ship to the ship owner (C) on 2 May, but delivered it late on 11 May
Owners had entered into a follow-on time charter with a third party beginning on 8 May, which due to the delay had to be renegotiated to a lower price due to fall in market price
Dispute

C sued for the difference in price of $8000 daily for the whole period of the new follow-on charter which comes up to $1.3m
D accepted liability only for the difference between price during the overrun period from 3 May to 11 May, amounting to $158,000
Arbitrators found for C on the basis that the loss was foreseeable under Hadley v Baxendale, although it was against the market expectations of the parties that D be liable for such loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Attorney General v Blake [2001]

Gain-based damages - account of profit

A

. The HoL allowed disorgement of prfits but emphasied that an account of profits will only be appropriate in exceptional circumstances. That is circumstances where:

Ordinary remedies for breach are inadequate (on the facts injunction no longer available after publication + no loss, sensitive info does not have market value).

The injured party has a ‘legitimate interest in preventing D’s profit-making activity’

Blake was British double-agent for the Russian KGB. After being sentenced to prison, he escaped and fled to the Soviet Union. While in exile, Blake published his autobiography. The publisher paid Blake £60,000 under the deal, with an agreement to pay a further 90,000 pounds. Blake’s contract of employment with the government contained an express undertaking obliging him not to “divulge any official information”=> breach of contract

Government unable to prove any loss:
oToo late to stop publication
oBy the time of publication the secrets were no longer confidential
oThe interest of the Crown in preserving the confidentiality of sensitive information did not have a market value

Instead the government sought disgorgement of the £90,000 unpaid profits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Wrotham Park Estate Co Ltd v Parkside Homes Ltd

Negotiating damages - gain based damages

A

Damages quantified as a reasonable sum that the promisee could have demanded for the relaxation of the covenant – 5% of profits

: houses built on a plot of land that was adjoining the land of the promisee in breach of restrictive covenant and made a profit

Demolishing houses: no, waste of useful properties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Morris Garner v One Step [2018]

availability of negotiating damages - restitutionary or compensatory

SC looks at availability of negotiating damages

When are negotiating damages available? Can they be claimed in the alternative to the standard compensatory damages?

ØWhen will a BoC result ‘in the loss of a valuable asset created or protected by the right which was infringed’?

Lord Reed at [92]: cases falling in this category are ‘the breach of a restrictive covenant over land, an intellectual property agreement or confidentiality agreement’

A

Held: C is not free to elect to receive negotiating damages in all cases of BoC (on the facts none awarded)

ØWhere the claimant’s interest in the performance of a contract is purely economic, and he cannot establish that any economic loss has resulted from its breach, the normal inference is that he has not suffered any loss. In that event, he cannot be awarded more than nominal damages

ØCommon law damages for breach of contract cannot be awarded merely for the purpose of depriving the defendant of profits made as a result of the breach, other than in exceptional circumstances, following Attorney General v Blake

=>No negotiating damages award on the facts
=> The substance of the claimant’s case is that it suffered financial loss in the form of lost profits and goodwill. Though difficult to quantify, this is a familiar type of loss, which can be quantified in a conventional manner. The claimants did not suffer the loss of a valuable asset created or protected by the right which was infringed.

Facts: Defendants used to own and run One Step, a company which provided living services to children leaving care and vulnerable adults. They entered into a contract to sell One Step to the claimants, which contained restrictive covenants not to compete with the business or solicit its clients/customers. Unbeknown to One Step, the defendants had already set up a rival business, called Positive Living, and had breached the covenants by operating in competition and poaching clients/customers. One step sought negotiating damages even though they could demonstrate loss of profits from the breaches – that’s because negotiating damages would have resulted in a larger sum. Defendants argued that negotiating damages should only be available where the defendant has suffered no conventional financial loss.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Hochster v De la Tour (1853) 2 E & B 678

breach of contract

A

Held:

Where one party communicates their intention not to perform the contract, the innocent party need not wait until the breach has occurred before bringing their claim.

=> Breach can occur at the time of the promised performance or before the due date for performance

The claimant agreed to be a courier for the defendant for 3 months starting on 1st June 1852. On the 11th May the defendant wrote to the claimant stating he no longer wanted his services and refused to pay compensation. The claimant obtained a service contract elsewhere but this was not to start until 4th July. The claimant brought an action on 22nd May for breach of contract. The defendant argued that there was no breach of contract on 22nd May as the contract was not due to start until 1st of June.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Anglia Television v Reed [1971] 3 All ER 690

expectation damages

Why/when would an injured party seek reliance damages as an alternative to expectation damages? (Anglia Television v Reed [1972])

  • Where he cannot prove his loss of profit
  • Where he has entered into a bad bargain! Expenses higher than the profits (but the courts do not allow this see C&P Haulage v Middleton [1983] )

“It is not the function of the courts where there is a breach of contract … to put a plaintiff in a better financial position than if the contract had been properly performed”

A

Held:
Whilst damages generally seek to put the parties in the position they would have been in had the contract been performed, the parties may elect to claim reliance loss and recover expenses incurred in an abortive transaction. Thus Anglia was able to recover their expenses from the defendant.

The claimant, Anglia Television, engaged Oliver Reed to play the leading role in a television play. Subsequently Reed pulled out and Anglia was unable to find a replacement. They abandoned the play but had incurred expenses amounting to £2,750.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Omak Maritimes Ltd v Mamola Challenger Shipping Co [2010]

expectation damages - forward-looking only

are expectation damages derivative in nature ?

A

claim failed => If a measure taken to reduce losses effectively eliminates the damage incurred, it nullifies any claim for damages that would have otherwise been valid.

Charterers (D) repudiated a charterparty even though the hire price was below market rate
The ship owner (C) elected to terminate and chartered out the ship at a higher rate
C claimed for damages for lost expenses made in preparation for the charterparty, although they had entirely been entirely mitigated by the higher rate of the new charterparty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Ruxley Electronics v Forsyth [1995]

compensatory damages - cost of cure v difference in value

Strong and diverse reactions. Could the HL have found a different balance between the parties? Note that the CA had taken a different view.

A

In most construction cases, the court will order the cost of cure compensatory damages. But in that case, the difference btw the 2 was such that the HoL held that the cost of cure was unreasonable:

oThe high cost of demolishing the pool and building a new pool was out of proportion to the benefit that would accrue to Mr. Forsyth
oThe breach was minor, the pool was safe for swimming and diving

oMr Forsyth did not intend to cure the breach (played a key role)

But he was still awarded damages of 2,500 pounds for loss of pleasure and amenity.

Facts

Contract to build swimming pool with max depth 7ft 6inch. Builders constructed pool with max depth 6ft 9 inch

The pool was safe for swimming and diving . The only way to make the pool compliant involved demolishing the work and starting again from scratch
There is a breach => compensatory damages
oDifference in value :£0

oCost of cure: over £21,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Addis v Gramophone Co Ltd [1909] AC 488 (HL):

compensatory damages - non-pecuniary loss - GR

A

GR : non-compensation of non-pecuniary loss

the House of Lords declined to award damages for injury to feelings and a loss of reputation caused by the abrupt and oppressive way in which, in breach of contract, an employer terminated the employment contract of its employee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Farley v Skinner [2001] (HL)

compensatory damages - non-pecuniary loss - exception

broadened the objection in W v M, it suffices to show that it is one aim.

A

HoL held: it is enough that of the aim of the contract was to provide pleasure. upheld trial judge’s award of £10,000 for mental distress
= Damages for mental distress can be awarded where the claimant’s distress is directly consequential on physical inconvenience caused by the breach of contract

Facts: F wanted to buy a hious near an international airport. Was worried about the noise. Hied a surveyor to know whether the property can be affected that the noise. The surveyor concluded that it wouldn’t impact the property. The very object of the contract was not pleasure. Skinner negligently surveyed Farley’s house – failed to highlight aircraft noise from proximity to Gatwick flight path…No difference in value of property (because house still worth what Farley paid for it)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Watts v Morrow [1991] 1 WLR 1421

compensatory damage s- non-compensation of pecuniary loss - exception

A

= when the very object of the contract is pleasure you can claim damages.

Cs bought a second home in the country in reliance on a land survey prepared by D surveyor
The survey was negligently prepared and failed to mention substantial defects
C claimed for damages for breach of contract, including damages for mental distress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cutter v Powell [1795] EWHC KB J13

breach of contract - conditional payment and part-performance -GR

A

Held: The wife’s action failed. Payment was on condition that he worked the ship to Liverpool, since he did not fulfil this condition the widow was entitled to nothing.

The claimant’s husband agreed by contract to act as a second mate on the ship the ‘Governor Parry’ on a return voyage to Jamaica. The voyage was to take eight weeks and he was to be paid on completion. A term in the contract stated:

“Ten days after the ship ‘Governor Parry,’ myself master, arrives at Liverpool, I promise to pay to Mr. T. Cutter the sum of thirty guineas, provided he proceeds, continues and does his duty as second mate in the said ship from hence to the port of Liverpool. Kingston, July 31st, 1793.”

Six weeks into the voyage the claimant’s husband died. The claimant sought to claim a sum to represent the six weeks work undertaken.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Sumpter v Hedges [1898] 1 QB 673

breach of contract - conditional payment and part-performance -GR

obiter: sometimes a “‘fresh contract’’ for the work done can be ‘inferred’ based on quantum meruit:
“Where, as in the case of work done on land, the circumstances give the defendant no option whether he will take the benefit of the work or not, then one must look to other facts than the mere taking the benefit of the work in order to ground the inference of a new contract. In this case I see no other facts on which such an inference can be grounded.”: p. 676

A

Held: the buildings on Hedges ‘land can’t be refused. It was held that S was entitled to recover the value of the materials left which H used, for H had the choice whether or not to use these to complete the building. But S could not recover for the work he had done, for H had no option but to accept the partly erected building which was on his land.

Facts: Sumpter is contracted to build two houses and a stable on Hedge’s Lands. S runs out of money and abandons the contract when the buildings are about half finished. H uses materials left by S to finish the buildings. S sues for payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Bettini v Gye (1875) 1 QB 183

breach of contract - repudiatory breach - termination

A

Held: the breach was not repudiatory as it did not go to the root of the contract. + because of the non-competition clause: the contract is bigger than the obligation breached. Therefore, the breach is a realtively less significant part of the K comparted to Poussard v Spiers.

Facts: Bettini to perform for Gye for fifteen weeks from March, and not compete for a year from January. “B agrees to be in London without fail at least six days before the commencement of his engagement, for the purpose of rehearsals”. B, ill, misses the first four days of rehearsals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Poussard v Spiers (1876) 1 QBD 410

repudiatory breach

A

Held:

Madame Poussard was in breach of condition and Spiers were entitled to end the contract. She missed the opening night which was the most important performance as all the critics and publicity would be based on this night.

Facts: Poussard to perform for Spiers for three months, implied to include rehearsals. P falls ill, misses the last five days of rehearsals, and is still ill on opening night, since she has been replaced. P can perform six days later. Is the breach repudiatory?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Hong Kong Fir v Kawasaki Kisen Kaisha [1962] 2 QB 26 (Hong Kong Fir)

repudiatory breach test - innominate terms

A

The CA: not repudiatory breach

Diplovk LJ restates the Test for repudiatory breach: ‘ Does the occurrence of the event deprive the party who has further undertakings still to perform of substantially the whole benefit which it was the intention of the parties as expressed in the contract that he should obtain as the consideration for performing those undertakings? ‘

= the consequences of the repudiatory breach goes to the root of the contract, or frustrates its purpose, or deprives the counterparty of substantially the whole benefit it was to receive as consideration ect.

Two-year charterparty, vessel to be seaworthy, needed thirty days ‘repair, then fifteen weeks more. K treated those as repudiation; H sues for rest of the two years fee.

The answer depends on how the shipping industry: scope of the contract as a whole; how important is the breach;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

L Schuler AG v. Wickman Machine Tool Sales Ltd [1974] AC 235

innominate terms - construction

A

Held: Upon construction of the contract, it is clear that 7(b) did NOT mean that it was condition in the technical legal sense. Does not mean that writing condition can never mean ‘condition’. The contract was simply badly drafted.

Lord Reid concluded that breach of clause 7(b) did not confer upon Schuler an immediate right to terminate the contract, irrespective of the consequences of the breach. Rather, a breach of clause 7(b) was automatically a material breach for the purposes of clause 11 and thus gave Schuler the right to invoke the machinery of clause 11.

Facts: W sole seller of Schuler products in a certain region. The contract required Wickman to make ‘best endeavours to promote and extend the sale of Schuler products in the territory’. In particular, cl 7(b) required weekly visits by particular salespeople to six particular firms over several years, the same salespeople every week.

7(b) ‘it shall be a condition of this agreement that,…’

11(a) This agreement ‘shall continue in force [for a certain period]… PROVIDED that Schuler or W may by notice in writing to the other determine this Agreement forthwith if:

The other shall have committed a material breach of its obligations hereunder and shall have failed to remedy the same within 60 days of being required in writing to do so…”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Rice v Great Yarmouth BC (2001) 3 LGLR 4

innominate terms - construction

A

Court: Y did not mean any breach of any clause. The breach had to be material.

Facts: Garden Guardian maintains Yarmouth’s grounds. In part due to drought, many minor breaches such as late planting of the summer beds. Clause23.2.1: “if the contractor commits a breach of any of its obligation under the contract… the Council may terminate the contract by notice in writing having immediate effect.”

22
Q

Johnsonv.Agnew[1980] AC 367 andSafehavenv.Springbok(1998) 71 P & CR 59

right to terminate

A
  • continuing repudiatory conduct by the party in breach. In such a case an innocent party who has elected to affirm the contract after the first breach of contract may be able to treat the continued non-performance as a fresh act of repudiation
23
Q

White and Carter v McGregor

affirmation - anticipatory breach -

on award of the agreed sum: The effect of a repudiatory breach by the party who will become liable to pay the agreed sum but before the agreed sum has fallen due has been considered in the context of discharge.White and Carter (Councils) Ltd v McGregorestablished that an injured party who can perform without the co-operation of the contract-breaker18has an almost unfettered option to hold the contract open, to perform, and to recover the sum once it becomes due.

Had it been a claim in damages, the appellants would have been subject to a requirement that they take reasonable steps to mitigate their loss (through seeking to find other people to take over the advertising space vacated by the respondent). But the claim was held to be one in debt. Clause 8 of the contract was critical in reaching the conclusion that the claim was one in debt because the effect of the clause was to declare that the entire price for the three-year period was ‘immediately due and payable’. The claim was therefore for a debt that was owed rather than for the loss of an entitlement to an income stream over a period of years. The obligation to mitigate was therefore not in play.

A

W wins the case (3:2). HoL: the appellants were entitled to recover the contract price on the ground that the respondent’s unaccepted repudiation of the contract had not operated to terminate the contract between the parties. The appellants were therefore entitled to continue with performance of the contract and recover the contract price.

see also The Alaskan Trader [1984] 1 All ER 129( ship ket fully crewed and empt = no legitimate interest)

W displayed ads for M’s garage over three years. Immediately after renewing the deal for another 3 years, M renounced the contract and sought to cancel. W refused to terminate the contract and displayed the ads for 3 years anyways. W sued for the fee. (Acceleration clause)

24
Q

Hounslow London Borough Councilv.Twickenham Garden Developments Ltd

affirmation (exceptions) - breach

Further, the courts have adopted a broad notion of co-operation so that the innocent party can neither require the active nor the passive co-operation of the party in breach. In

A

When the innocent party is dependent upon the co-operation of the party in breach in order to be able to continue with performance.

25
Q

Attica Sea Carriers Corporationv.Ferrostaal Poseidon Bulk Reederei GmbH

affirmation - (exception) - breach

A

where the innocent party has no legitimate interest in performance of the contract, cannot affirm

26
Q

Hoenig v Isaacs [1952] 2 ALL ER 176

substantial performance doctrine

A

Where a party has substantially performed his obligations under contract, he is entitled to claim for payment in an action for the agreed sum, deducting any cost of repairs for defects in his performance

Mr Hoenig was contracted to decorate and furnish Mr Isaacs’ flat for £750. When the work was done, there were problems with a bookcase and wardrobe, which would cost £55 to fix. Mr Isaacs refused to pay the £350 outstanding.

27
Q

McRae v CommonWealth

expectation vs reliance - monetary damages (compensatory damages)

A

can’t claim expectation damages if too speculative

28
Q

Photo Production Ltd v Securicor Ltd [1980]: Lord Diplock:

fundamental breach doctrine

A

Lord Denning in several prior cases (including the Court of Appeal in this case) had argued that contract law has a doctrine of ‘fundamental breach’: J Spurling Ltd v Bradshaw [1956] 1 WLR 461. This doctrine meant that if a contract was terminated because of a repudiatory breach, the parties’ ability to rely on any exclusion or limitation clauses terminated also.

Lord Wilberforce in this case affirmed that there is no such doctrine in English law.

29
Q

Robinson v Harman (1848):

expectation damages

A

“The rule of the common law is, that where a party sustains a loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation with respect to damages, as if the contract had been performed”

30
Q

Ruxley Electronics v Forsyth [1995]

expectation damages - cost of cure vs. difference in value

Strong and diverse reactions. Could the HL have found a different balance between the parties? Note that the CA had taken a different view.

A

In most construction cases, the court will order the cost of cure compensatory damages. But in that case, the difference btw the 2 was such that the HoL held that the cost of cure was unreasonable:

oThe high cost of demolishing the pool and building a new pool was out of proportion to the benefit that would accrue to Mr. Forsyth

oThe breach was minor, the pool was safe for swimming and diving

oMr Forsyth did not intend to cure the breach (played a key role)

But he was still awarded damages of 2,500 pounds for loss of pleasure and amenity.

Contract to build swimming pool with max depth 7ft 6inch
Builders constructed pool with max depth 6ft 9 inch
The pool was safe for swimming and diving
The only way to make the pool compliant involved demolishing the work and starting again from scratch.

There is a breach => compensatory damages

oDifference in value :£0

oCost of cure: over £21,000

31
Q

The Golden Victory [2007] UKHL 12; [2007] 2 WLR 691

date of assessment of damages

A

the SC has held that events subsequent to the breach could be taken into account to the assessment of damages. (usually damages are assessed at the date of breach)

A 7-year charterparty was made between the shipowners (C) and the charterers (D)
D repudiated the charterparty by redelivering the ship after 3 years and the repudiation was accepted by C
15 months later, the Second Gulf War broke out and pursuant to a ‘war clause’, D would have been entitled to lawfully terminate in the event of war had it not already repudiated
C sued D for damages for breach of contract

32
Q

Malik v Bank of Credit and Commerce International SA [1998] 1 AC 20

loss of reputation - compensatory damages (non-pecuniary damages)

no longer necessary to distinguish a breach of contract which causes injury to a reputation which a person already possesses from a breach of a specific undertaking to protect or enhance a person’s reputation, for which damages were awarded prior to the decision inMalik’s case.35So, where a contract entitles an actor to be advertised as playing a leading part at a well-known music-hall, the actor may recover damages for the loss of publicity and for any injury that the failure to appear may cause to the actor’s existing reputation.

A

held: The House of Lords held that contracts of employment contained an implied term of mutual trust and confidence so that the defendant was under an implied obligation not to carry on a dishonest or corrupt business, and that, in principle, financial loss in respect of damage to reputation caused by breach of this term is recoverable in a contractual action. It will, however, often be difficult to prove a handicap on the labour market.

facts: M and other relatively senior employees of BCCI, were dismissed following the bank’s insolvency. They claimed that they were unable thereafter to obtain employment in the financial services industry because of the stigma attached to former employees of BCCI, and sought substantial compensation for this handicap in the labour market. For the purposes of the proceedings it was assumed that BCCI had carried on its business in a corrupt and dishonest manner, that this had become widely known, that M and the other employees were innocent of any involvement, were at a handicap in the labour market because of the stigma, and had suffered financial loss as a result.

33
Q

Kemp v Intasun Holidays Ltd

damages - remoteness

note that thos rarely applies (here the agent had not been made aware)

A

no damage on the 2nd hadley limb

P’s wife booked a package holiday in Spain. Upon arrival,the hotel where they were supposed to be staying was fully booked and P and his family had no alternative but to stay in staff quarters at another hotel. Indeed, the room in which they stayed was unhygienic and dusty which aggravated P’s asthma. However, the travel agent had not been made aware of this condition during the booking process.

34
Q

Koufos v C Czarnikow Ltd (The Heron II) [1969] 1 AC 350

remoteness - limitations on damages

A

For loss to be recoverable, there must be a ‘serious possibility’ of it resulting from the breach.``
= The loss in profits was sufficiently likely to be recoverable in damages
( under H v B first limb) A reasonable person would have contemplated that loss due to fluctuations in the market price was likely to result from the breach of contract

A contract for the carriage of a cargo of sugar was delayed by 9 days. The market price of sugar dropped following this delay due to the arrival of another cargo of sugar. The claimant sought to recover the difference from the defendant for their breach of contract. The defendant argued the damages were too remote since it was just as likely that the market price could increase.

35
Q
  • Globalia Business Travel v Fulton Shipping Inc [2017] UKSC 43; [2017] 1 WLR 2581

mitiagation - limitation on damages

reasons:

  • the sale of the ship did not constitute successful mitigation
  • nothing about the premature termination of the charterparty which made it necessary to sell the vessel, at all or at any particular time. It could also have been sold during the term of the charterparty. When to sell the vessel was a commercial decision made at the owners’ own risk [32]. The owners would not have been able to claim the difference in the market value of the vessel if the market value had risen between the sale in 2007 and the time the charterparty would have terminated in 2009. The premature termination of the charterparty was at most the occasion for selling the vessel, but it was not the legal
    cause of it
A

held: **The Supreme Court allows the owners’ appeal. The charterers are not entitled to a credit for the difference in the value of the vessel when sold in 2007, in comparison to its diminished value in 2009.

  • Charterers (D) redelivered the vessel to the owners (C) two years before the charterparty was to end, C accepted the repudiation
  • Subsequently, C sold the vessel for $23.7 million
  • C sued for breach of contract, seeking damages amounting the loss profits from the remaining two years of the charterparty
  • Had the vessel been sold at the end of the charterparty, it would have an estimated value of only $7m, C thus avoided a loss of about $17m
36
Q

Chaplin v Hicks [1911] 2 KB 786 Court of Appeal

monetary damages - expectation damages

A

The appeal was dismissed. The claimant was entitled to recover damages for her loss of a chance of gaining employment. She did not have to demonstrate that she would have been successful at interview.

The claimant was an actress. She entered a beauty contest organised by Hicks. Hicks was a famous actor and theatre manager and advertised the contest in a newspaper. The readers of the newspaper were to vote and the top 50 would be invited to an interview where 12 would be selected for employment. The claimant got through to final 50 but did not receive her invitation for interview until it was too late to attend. She brought an action based on her loss of a chance of gaining employment. She was awarded £100 assessed by the jury. Hicks appealed contending that the damages were speculative in nature and incapable of assessment.

37
Q

Societe des Industries Metallurgiques SA v Bronx Engineering Co Ltd [1975] : s

specific peformance - damages must be inadequate

A

Held: damages will be adequate. Although it will take a long time to obtain a substitute, you still can. Ts only where good are unique that you can get specific performance.

sale of machinery worth 270 000 pounds, the promisor is in breach of contract. The innocent parties goes to court claiming that they can’t get

38
Q

Sky Petroleum v VIP Petroleum [1974]

SP - damages must be inadequate

A

Held: the court awarded specific performance.

the contract regarded the sale of petrol (the oil crisis) = the promisor refuses to sell the petrol. Because of the circumstances, petrol has become a unique and rare commodity.

39
Q

Co-operative Insurance Society Ltd v Argyll Stores (Holdings) Ltd [1998]:

specific performance - constant supervision

+ also undue hardship : If the HoL had awarded SP for the remainder of the lease. It would basically amount to forcing the supermarket to be in a loss situation.

Beswick v Beswick [1968] AC 58 = a more expensive approach to which Argyll put an end.

A

Held: can’t be awarded SP because of the “constant supervision” objection. Would give rise to an indefinite series of rulings on whether D complies with the order.

Facts: C (owner of shopping center), D (owner of supermarket). C had agreed to let a unit to D for 35 years. After 15 years the supermarket is losing money and decides to close. D goes to court and seeks SP arguing that the supermarket was an anchor tenant, the key attraction of the shopping center (attracts customers).

40
Q

Patel v Ali [1984]

SP - undue hardship

A

Held: it would cause undue hardship with Ds. The D has suffered cancer and been amputated. The husband had become bankrupt and was sent to prison + D was extremely reliant on others.

Facts: sale of house. Ds (a couple) had agreed to sell the house and then refused. C brought a claim for SP (normally no prob because house is unique and can’t get a substitute)

41
Q

The Aquafaith [2012]:

White and Carter has been affirmed and Lord Reid’s limitations applied in later cases. this one is an example

=> However, the courts have never satisfactorily unpacked the notion of “legitimate interest” - Lord Reid did not explain its meaning and no clear definition/guidance has emerged in subsequent cases. Some light has however been shed on when a legitimate interest will arise

A

the injured party has no legitimate interest in keeping the contract alive where damages are an adequate remedy and his insistence on performing is “wholly unreasonable”, a “commercial absurdity” or “perverse”

NB: This suggests that in most circumstances, the injured party should be able to insist on performance and claim the agreed price

FACTS: Charterers stated that they would redeliver the vessel early in anticipatory breach. The owners refused this early redelivery, thereby affirming, so that the charterers would be liable for the charter hire for the minimum term. The charterers claimed (i) that the owners could not affirm as they had no legitimate interest in performing rather than claiming damages, and (ii) they could not claim the hire since the charter involved the cooperation of the charterer.. I that case, they coukld affirm despite the White and carter criteria

42
Q

Lumley v Wagner

prohibitory injunction

A

Held: The injunction was granted. Preventing her from singing for others.

Facts: singer contract 3 months would sing exclusively for Mr. Lumley (exclusivity clause). Agreed to sing for another.

43
Q

Warner Bros v Nelson [1937] 1 KB 209

prohibitory injuction

A

An injunction was granted but only in so far as it prevented Bette Davis from acting or performing for another. The term relating to no employment of any kind was severed and did not form part of the injunction.

= if the injunction is very expansive, it amounts to SP = it is not likely to be valid.

Facts: By contract, the defendant actress Bette Davis, agreed to act exclusively for Warner Bros for two years. The contract stipulatednot only that could she not act for another but also she could take no employment of any kind. Bette Davis then moved to England and in breach of contract entered an agreement to act for another. Warner Bros sought an injunction to prevent her from doing so.

44
Q

Mortimer v Beckett

prohibitory injunctions

A

If not specifically written in the contract, the injunction cannot be enforced

45
Q

Cavendish Square v Makdessi

TEST FOR PENALTY CLAUSES

penalty clause test

  • is the amount payable on breach ?
  • does the innocent party have a legitimate interest in the performance ?
  • is the sum payable out of proportion to the legitimate interest ?

+ also bargaining position will be taken into account.

‘The true test is whether the impugned provision is a secondary obligation which imposes a detriment on the contract-breaker out of all proportion to any legitimate interest of the innocent party in the enforcement of the primary obligation.’

A

held: neither clauses are unenforceable penalty clauses;

By an agreement, Mr Makdessi agreed to sell to Cavendish a controlling stake in the holding company of the largest advertising and marketing communications group in the Middle East. The contract
provided that if he was in breach of certain restrictive covenants against competing activities, Mr Makdessi would not be entitled to receive the final two instalments of the price paid by Cavendish
(clause 5.1) and could be required to sell his remaining shares to Cavendish, at a price excluding the value of the goodwill of the business (clause 5.6). Mr Makdessi subsequently breached these covenants. Mr Makdessi argued that clauses 5.1 and 5.6 were unenforceable penalty clauses.

46
Q

Dunlop Pneumatic Tyre v New Garage and Motor Co [1915] AC 79.

the penalty doctrine

see also - Andrews v Australia and New Zealand Banking Group, [2012] HCA 30.

facts: 38,000 group members, commenced representative proceedings in the Federal Court of Australia. They sought, amongst other remedies, declaratory relief that certain provisions between each of them and the ANZ were void or unenforceable as penalties. On that basis, the applicants claimed repayment of fees charged to them by way of “honour fees”, “dishonour fees”, “late payment fees”, “non-payment fees” and “over limit fees” (collectively, “exception fees”).

held: appeal allowed. The fact that particular fees were not charged by the respondent, Australia and New Zealand Banking Group Ltd (“the ANZ”), upon breach of contract did not render the fees incapable of being characterised as penalties.

A

The clause was a liquidated damages clause not a penalty clause.

Lord Dunedin set out the differences between a liquidated damages clause and a penalty clause
+ Though the parties to a contract who use the words ‘penalty’ or ‘liquidated damages’ may prima facie be supposed to mean what they say, yet the expression used is notconclusive.

Facts: The claimant, Dunlop, manufactured tyres and distributed them to retailers for resale. The contract between Dunlop and New Garage contained a clause preventing New garage from selling the tyres below list price. In the event that they were in breach the contract specified that 5/. would be payable for each tyre sold below the list price. The defendants sold some tyres below the list price and the claimant brought an action for damages based on the amount specified in the contract. The defendant argued that the relevant clause was a penalty clause and thus unenforceable. The trial judge held it was a liquidated damages clause and awarded the claimant 5/. per tyre. The Court of Appeal reversed this holding that the clause was a penalty clause and awarded the claimant 2/. per tyre representing the actual loss suffered. The claimant appealed to the House of Lords.

47
Q

ParkingEye v Beavis [2015] UKSC 67.

the penalty doctrine

A

Unlike in Cavendish v El Makdessi, the penalty rule is engaged. However, the £85 charge is not a penalty.Both ParkingEye and the landowners had a legitimate interest in charging overstaying motorists, which extended beyond the recovery of any loss. The interest of the landowners was the provision and efficient management of customer parking for the retail outlets. The interest of ParkingEye was in income from the charge, which met the running costs of a legitimate scheme plus a profit margin

facts: Mr Beavis had a contractual licence to park in the car park on the terms of the notice posted at the entrance, including the two hour limit. The £85 was a charge for contravening the terms of the
contractual licence. This is a common scheme, subject to indirect regulation by statute and the British Parking Association’s Code of Practice. The charge had two main objects: (i) the management of the
efficient use of parking space in the interests of the retail outlets and their users by deterring long-stay or commuter traffic, and (ii) the generation of income in order to run the scheme [94-98].

48
Q

Triple Point Technology Inc v PTT Public Co Ltd [2019] EWCA Civ 230 (delay schedule)

penalty doctrine

The Court of Appeal said that the question of whether such a clause applied in these circumstances would depend on the wording of the clause itself. In relation to the specific clause before the court, the clause was focused specifically on delay between the contractual completion date and when the work was actually completed by the contractor and accepted by the employer. If that never occurred, the liquidated damages clause did not apply.

A

CA: held that a clause providing for liquidated damages for delay did not apply where the contractor failed to complete the contracted work (the installation of a new software system). The employer under the contract was therefore entitled to recover damages for breach assessed on ordinary principles, rather than liquidated damages?
+ was not a penalty clause

Facts: T was contracted to provide a software system for PTT on a certain timeline. Each of nine successive “milestones” came with the deadline, and if T missed it, they were to suffer a penalty calculated as a proportion (0.1%) of the share of the price assigned to the outstanding milestones per day’s delay.
Carefully crafted and the care taken with formula aspect => seems proportionate.

49
Q

Beswick v Beswick [1968] AC 58

A

This case demonstrates some of the ways the courts tried to avoid the limitations of the privity of contract rule. In the modern era, the wife would likely be able to sue in her own right under the Contracts (Rights of Third Parties) Act 1999.

the wife sued as executor of the estate

The deceased, being 70 years old and became ill, decided to step back from his business. He agreed with the defendant to transfer his business’ goodwill and tools to the defendant. In return, the defendant would employ the deceased as a consultant for the remainder of his life. After his death, the defendant was to pay the deceased’s wife £5 a week. The wife was not a party to this contract.

When the man died, the defendant paid the wife one sum of £5 and then refused to make further payments. The wife sued for specific performance of the agreement.

50
Q

C&P Haulage v Middleton [1983]

reliance damages ( interest)

His action failed on the ground that the breach had not caused him any loss because he would have been in the same position had the contract been terminated lawfully. The Court of Appeal held that the claimant’s loss did not flow from the breach but from the fact that he had entered into a contract under which he had agreed that he would not be able to remove the fixtures at the end of the lease. It was held that a claimant could not recover his reliance losses where that would enable him to escape from his bad bargain or would reverse the contractual allocation of risk.

A

=> action failed, he would not have bee able to recover his losses had the contract been terminated without breach

the claimant was given a licence to occupy premises on a renewable six-monthly basis. He spent some money on improving the property, even though it was expressly provided in the contract that the fixtures were not to be removed at the end of the licence. The defendants ejected the claimant from the premises in breach of contract and the claimant sought to recover as damages the cost of the improvements which he had carried out to the property.