OPTIONAL Flashcards
Client Regs:
• Who was at the DTM?
Agency Manager
Agent
WPA
Professional team - Me, building services specialist, infrastructure team.
Client Regs:
• What were the essential and non-essential works?
Essential Works:
level accessible office
lighting / heating / infrastructure requirements.
Non-essential Works:
non standard furniture, decorations and finishes.
M’ment:
• Explain GEA, GIA and NA – how do they differ from the International Prop Measurement Standards?
????
What are the surveying accuracy tolerance for a engineering surveying and setting out, high accuracy measured building surveying, heritage recording at 1:20?
Accuracy (X,Y) = 0.5%
Final valuation accuracy = +/- 5mm
Minimum size of feature to be shown to scale without generalisation = 10mm
What are the surveying accuracy tolerance for a engineering surveying and setting out, measured
building surveys, high accuracy topographic surveys, determined boundaries, area registration at 1:50?
Accuracy (X,Y) = 1%
Final valuation accuracy = +/- 10mm
Minimum size of feature to be shown to scale without generalisation = 20mm
What are the surveying accuracy tolerance for a measured building surveys, low accuracy setting out, net area surveys, valuation surveys at 1:100?
Accuracy (X,Y) = 2%
Final valuation accuracy = +/- 25mm
Minimum size of feature to be shown to scale without generalisation = 50mm
What are the surveying accuracy tolerance for a low accuracy measured building surveys at 1:200?
Accuracy (X,Y) = 4%
Final valuation accuracy = +/- 50mm
Minimum size of feature to be shown to scale without generalisation = 100mm