Who prepare the LL SoC?
The landlords property surveyor
Were you involved in checking it?
No, as this had already been undertaken prior to my involvement.
What were you looking for?
At first I wanted to check what the LL report included, so I could cross reference it with my report, however, it was at this stage I identified the issue with progressing with the LL chosen method of construction.
Why was the Conservation Case Officer involved?
As part of the expansion project, we was also instructed to replace the existing shop front window.
As the property is located within a conservation area, we needed to apply for planing permission for approval.
M & E & SE procurement – how done?
A service-level agreement between the my client and consultants, for one of projects. Their fee is then negotiated, depending of the size and complexity of the project.
Level of involvement? What service did they provide?
The structural engineer provided his service for inspecting the property (area of works) completing a design and specification for the works, and they for signing off the works on site.
How instructed?
???
What was level of PI required?
5m
How was is it checked?
as they are approved consultants for NFUM, they had already undergone dul, which included having a copy of the most recent insurance documents on file.
What other procurement methods are available?
???
How was the liquidated damages calculated?
???
What happened between end of tender adjudication 13.1.17 to 5.08-1.3.17 (6 weeks)
???
Staff in occupation? Temp accommodation provided?
No, we had a separate entrance, so we were able to
What were Party Wall issues to consider?
the right notice to used, the timescale involved, the award needed.
What investigations were undertaken to the floor and when?
we allowed for opening up the floor in a 5-6 locations, to establish the condition of the sub floor and void.
Why was Option 3 better than Option 1?
less disruptive, required less storage of materials, existing, quicker to installed, given the access restrictions.
What was the required floor loading?
Historically, UK office buildings have been designed and marketed with live loadings significantly higher than the British Standard loading threshold of 2.5 kN/m2 (typically 3.5–4.0 kN/m2).
What were the Party Wall issues?
Replacing a rear outbuilding asbetos roof covering, that bridge the adjacency property owners building.
What measures could be taken/did you take to ensure variations were competitively priced by the contractor?
Bench marked the costs using a BCIS, and cross referenced the project cost against other like projects.
What is the difference between a PS and Contingency? (Insufficient contingency in the tender).
???
What was the difference between programme Options 1 and 2 (Client variation?).
Option 1 Programme 6 weeks
Option 2 Programme 8 weeks
2 weeks were included to allow for the clients variation.
How was the PW issue addressed?
Via communication with the adjacent property owner, and discussed about the works. we established that a section two notice would be required (party structure notice).
What were the issues regarding lines of communications?
???
Asbestos issues and Landlord?
???