OM - GB335 - Chapter 3 Flashcards

1
Q

Project Management Activities

A
  1. Planning
  2. Scheduling
  3. Controlling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Planning

A
Establishing objectives
Defining project
Creating work breakdown structure
Determining resources
Forming Organization
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The Role of the Project Manager

A

HIGHLY VISIBLE
Responsible for making sure that:
1. all necessary activities are finished in order and on time
2. The project comes in within budget
3. The project meets quality goals
4. The people assigned to the project receive motivation, direction, and information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Work breakdown Structure

A

Level

  1. Project
  2. Major tasks
  3. Sub-tasks
  4. Activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project Scheduling

A
identifying precedence relationships
sequencing activities 
determining activity times and costs
estimating material and worker requirements
determining critical activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Purpose of project scheduling

A
  1. shows the relationship of each activity to others and the whole project
  2. identifies the precedence relationships among activities
  3. Encourages the setting of realistic time and cost estimates for each activity
  4. helps make better use of resources by identifying critical bottlenecks in the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Project Management Techniques

A

Gantt Chart
CPM (Critical Path Method)
PERT (Program Evaluation and Review Technique)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

6 Steps PERT & CPM

A
  1. Define the project and prepare the work breakdown structure
  2. Develope relationships among the activities
  3. Draw the network connecting all of the activities
  4. Assign time and/or cost estimates to each activity
  5. Compute the longest time path through the network (this is called the critical path)
  6. Use the network to help plan, schedule, monitor, and control the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

8 questions PERT & CPM can answer

A
  1. when will the entire project be completed?
  2. What are the critical activities or task in the project?
  3. which are the noncritical activities?
  4. What is the probability the project will be completed by a specific date?
  5. is the project on/behind/ahead of schedule?
  6. is the money spent equal/less/more than the budget?
  7. Are there enough resources available to finish the project on time?
  8. if the project must be finished in a shorter time, what is the way to accomplish this at least cost?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Determining the project schedule

A

Perform a Critical Path Analysis

  • the critical path is the longest path through the network
  • the critical path is the shortest time in which the project can be completed
  • any delay in critical path activities delays the projects
  • critical path activities have no slack time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Variability in Activity Times

A

3 time estimates are required:
Optimistic time
Pessimistic time
Most likely time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Project Crashing

A

shortening the duration of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Advantages of PERT/CPM

A
  1. useful when scheduling and controlling large projects
  2. straightforward concept and not mathematically complex
  3. graphical networks help highlight relationships among project activities
  4. critical path and slack time analyses help pinpoint activities that need to be closely watched
  5. project documentation and graphics point out who is responsible for various activities
  6. applicable to a wide variety of projects
  7. useful in monitoring not only schedules but costs as well
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Limitations of PERT/CPM

A
  1. Project activities have to be clearly defined, independent, and stable in their relationships
  2. Precedence relationships must be specified and networked together
  3. Time estimates tend to be subjective and are subject to fudging by managers
  4. there is an inherent danger of too much emphasis being placed on the critical path
How well did you know this?
1
Not at all
2
3
4
5
Perfectly