NRM Flashcards
What is the status of NRM?
It is a guidance note - meaning it is not compulsory but is seen as ““best practice””
If it is not taken into account, this could be seen as ““negligent”” in a claim
What is the purpose of NRM1?
- Provides guidance on the quantification of building works for OCE and Cost Plans
- Provides rules of measurement to aid understanding through design team
- Provides direction on how to describe and deal with costs and allowance that are part of the cost of a building, but that aren’t reflected in measurable work items
- Second edition allows better distinguishment between capital building works and building maintenance
What is NRM1 used for?
- OCE
- Elemental cost models
- Cost plans
- Cost analysis
- Benchmark analysis
What abbreviations are there in NRM?
EUQ - Element Unit Quantity unit of measurement that relates solely to quantity of element
EUR - Element Unit Rate (total cost of element (incl. Plant, materials, subcont prelims and OH&P)/ EUQ)
NIA
GIA
PC Sum - Prime Cost Sum
NRM Definition: Base Cost Estimate
Sum of works cost estimate + project / design fees estimate + other development costs estimate
Excludes allowances for risk or element inflation
NRM Definition: Base Cost Estimate
Sum of works cost estimate + project / design fees estimate + other development costs estimate
Excludes allowances for risk or element inflation
NRM Definition: Base date of cost data
Date that rates and prices contained within cost analysis / benchmark analyses are taken
NRM Definition: Component
Measured item that forms part of an element
NRM Definition: Construction inflation
Allowance included for fluctuations in basic prices of labour, plant, equipment and materials during the period from date of tender return, to the mid point of construction period
NRM Definition: Cost limit
Authorised budget / approved estimate. Maximum expenditure the employer is prepared to make for completed building
NRM Definition: Cost target
Recommended total expenditure for an element. Derived from number of components
NRM Definition: Element
Major part of a group element e.g. 3: Internal Finishes = 3.1 Wall, 3.2 Floor, 3.3 Ceiling
NRM Definition: Elemental cost analysis
Appraisal of costs in previously constructed buildings aimed at providing reliable information
NRM Definition: Elemental cost plan
Breakdown if cost limit for the building into cost targets for each element . Provides work / cost breakdown structure
NRM Definition: Enabling works
Works executed ahead of the main building contract. Include a mixture of new building works and facilitating works such as major demolition, removal of contaminated materials and new access road, new drainage etc
NRM Definition: Estimate base date
Date cost limit is established (excluding inflation) as a basis for calculating inflation, changes etc
NRM Definition: GIA
Area of a building measured up to the internal face of the perimeter walls at each level
NRM Definition: Functional unit method
Rough budget setting technique consisting of selecting a suitable standard functional unit, including for circulation space
NRM Definition: Group Elements
Refers to the main heading used to describe the facets of an elemental cost plan:
- Substructure
- Superstructure
- Internal finishes
- Fittings, furnishings and equipment
- Services
- Complete buildings and building units
- Work to existing buildings
- External works
- Facilitating Works
- MC Prelims
- MC OH&Ps
- Project / design fees
- Other development costs
- Risks
- Inflation
NRM Definition: MC OH&P’s
Costs associated with head office administration proportioned to each building. Exclude costs associated with subcontractors OH&P
NRM Definition: MC Prelims
Items which cannot be allocated to a specific element or component but that are necessary to complete the works. E.g insurances, bonds, cleaning etc
Time - management and staff, security
Fixed - site establishment,
NRM Definition: Other development costs
Costs not directly associated with cost of constructing building e.g. Section 106 / 278
What is the purpose of an OCE? NRM1
- Is the project affordable?
- What is a realistic cost limit?
- Support with the identification of procurement methods to be used
What is needed to prepare an OCE? NRM1
o Location and availability of site
o Building use
o Floor area and accommodation schedule
o Requirements for refurbishment
o Initial project brief
o Enabling works details
o Indicative programme
o Any particular restraints
o Site conditions
o Budget/ cash flow constraints
o Life span
o Storey heights
o M&E
o Requirements of
Project team fees
Other project costs
Treatment of inflation
Treatment of VAT
- Design (floor plans, services specifications, advice on ground conditions, elevations)
- Initial risk registers from deign team