NRM Flashcards
What is the status of NRM?
It is a guidance note - meaning it is not compulsory but is seen as ““best practice””
If it is not taken into account, this could be seen as ““negligent”” in a claim
What is the purpose of NRM1?
- Provides guidance on the quantification of building works for OCE and Cost Plans
- Provides rules of measurement to aid understanding through design team
- Provides direction on how to describe and deal with costs and allowance that are part of the cost of a building, but that aren’t reflected in measurable work items
- Second edition allows better distinguishment between capital building works and building maintenance
What is NRM1 used for?
- OCE
- Elemental cost models
- Cost plans
- Cost analysis
- Benchmark analysis
What abbreviations are there in NRM?
EUQ - Element Unit Quantity unit of measurement that relates solely to quantity of element
EUR - Element Unit Rate (total cost of element (incl. Plant, materials, subcont prelims and OH&P)/ EUQ)
NIA
GIA
PC Sum - Prime Cost Sum
NRM Definition: Base Cost Estimate
Sum of works cost estimate + project / design fees estimate + other development costs estimate
Excludes allowances for risk or element inflation
NRM Definition: Base Cost Estimate
Sum of works cost estimate + project / design fees estimate + other development costs estimate
Excludes allowances for risk or element inflation
NRM Definition: Base date of cost data
Date that rates and prices contained within cost analysis / benchmark analyses are taken
NRM Definition: Component
Measured item that forms part of an element
NRM Definition: Construction inflation
Allowance included for fluctuations in basic prices of labour, plant, equipment and materials during the period from date of tender return, to the mid point of construction period
NRM Definition: Cost limit
Authorised budget / approved estimate. Maximum expenditure the employer is prepared to make for completed building
NRM Definition: Cost target
Recommended total expenditure for an element. Derived from number of components
NRM Definition: Element
Major part of a group element e.g. 3: Internal Finishes = 3.1 Wall, 3.2 Floor, 3.3 Ceiling
NRM Definition: Elemental cost analysis
Appraisal of costs in previously constructed buildings aimed at providing reliable information
NRM Definition: Elemental cost plan
Breakdown if cost limit for the building into cost targets for each element . Provides work / cost breakdown structure
NRM Definition: Enabling works
Works executed ahead of the main building contract. Include a mixture of new building works and facilitating works such as major demolition, removal of contaminated materials and new access road, new drainage etc
NRM Definition: Estimate base date
Date cost limit is established (excluding inflation) as a basis for calculating inflation, changes etc
NRM Definition: GIA
Area of a building measured up to the internal face of the perimeter walls at each level
NRM Definition: Functional unit method
Rough budget setting technique consisting of selecting a suitable standard functional unit, including for circulation space
NRM Definition: Group Elements
Refers to the main heading used to describe the facets of an elemental cost plan:
- Substructure
- Superstructure
- Internal finishes
- Fittings, furnishings and equipment
- Services
- Complete buildings and building units
- Work to existing buildings
- External works
- Facilitating Works
- MC Prelims
- MC OH&Ps
- Project / design fees
- Other development costs
- Risks
- Inflation
NRM Definition: MC OH&P’s
Costs associated with head office administration proportioned to each building. Exclude costs associated with subcontractors OH&P
NRM Definition: MC Prelims
Items which cannot be allocated to a specific element or component but that are necessary to complete the works. E.g insurances, bonds, cleaning etc
Time - management and staff, security
Fixed - site establishment,
NRM Definition: Other development costs
Costs not directly associated with cost of constructing building e.g. Section 106 / 278
What is the purpose of an OCE? NRM1
- Is the project affordable?
- What is a realistic cost limit?
- Support with the identification of procurement methods to be used
What is needed to prepare an OCE? NRM1
o Location and availability of site
o Building use
o Floor area and accommodation schedule
o Requirements for refurbishment
o Initial project brief
o Enabling works details
o Indicative programme
o Any particular restraints
o Site conditions
o Budget/ cash flow constraints
o Life span
o Storey heights
o M&E
o Requirements of
Project team fees
Other project costs
Treatment of inflation
Treatment of VAT
- Design (floor plans, services specifications, advice on ground conditions, elevations)
- Initial risk registers from deign team
What items are included in an OCE? NRM1
o Project title & description
o Statement of cost incl cost limit
o Details on the information it has been prepared from
o Statement of floor areas
o Assumptions
o Estimate base date (that inflation has been applied to)
o Estimated costs and requests for alternative proposals (e.g. option costs)
o Inclusions and exclusions
What are the headings of the cost build up for an OCE? NRM1
- Facilitating works estimate
- Building works estimate
- MC Prelims
- Sub total
- MC OH&P
- Works cost estimate total
- Project / design team fees
- Other development costs
Applied on to total base cost estimate:
- Risk allowance estimate
- Tender inflation estimate
- Construction inflation estimate
Give examples in the categories of risk you should apply when costing construction works (NRM1)
Design
- inadequate design, unrealistic programme, inadequate site investigation
Construction
- Archaeological remains, inadequate site investigation, ecological issues
Employer change
- Change in quality, time, employer driven variations, change in scope
Employer other
- Third party (planning refusal), Management (ineffective cost control procedures), Financial (unavailability of funds), Timescales (unrealistic programmes), Project brief (end user requirements), Other (force majeure)
How do you calculate measurement of facilitating works? NRM1
- SA, area affected, linear meters, number or itemised
- SA = total area of site - existing building footprints
What is the elemental method of OCE? NRM1
- Considers the major elements and prices and OCE based on the breakdown
0 - Facilitating Works (m2)
1 - Substructure (m2)
2 - Superstructure (m2)
3 - Internal finishes (m2)
4 - Fittings, furnishings and equipment (m2)
5 - Services (nr / kW / m2)
6 - Prefabricated buildings (m2)
7 - Work to existing buildings (m2)
8 - External works (m2)
What are the sub-components of the superstructure? NRM1
- Frame
- Upper floors
- Roof
- Stairs and Ramps
-External walls - External windows and doors
- Internal walls
- Internal doors
What are the sub-components of the services? NRM1
- Sanitary installations
- Services equipment
- Disposal installations
- Water installations
- Heat source
- Space heating and air conditioning
- Ventilation
- Electrical installations
- Fuel installations
- Lift and conveyor installations
- Fire & lighting protection
- Communication, security and control systems
- Specialist installations
- BWIC
What is included in rates? NRM1
Material, plant, equipment, subcontractors OH&P and prelims
What is excluded from rates? NRM1
Main Contractor OH&P / prelims
Inflation
Risk
VAT